Switch Las Vegas Core Campus
Las Vegas,Clark County,NevadaExpandingFiling entity: SwitchLast checked Nov 13, 2026
SwitchDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Still to confirm: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Switch Las Vegas Core Campus is an expanding data center project in Las Vegas, Clark County, Nevada. Switch is named as operator. It was announced at 495 MW.
Switch Las Vegas Core Campus is an expanding data center project in Las Vegas, Clark County, Nevada. Switch is named as operator. It was announced at 495 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Las Vegas, Clark County, Nevada. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nevada EO 2026-005: Sets state standards data centers must meet for tax abatements
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 495 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Nevada
- EO 2026-005 · In effect · Sep 18, 2026Sets state standards data centers must meet for tax abatements
Who's involved
- Developer and operatorSwitch
Power
Capacity, as announced or filed
- 495 MW · Full buildout (company claim)Mar 2026 · what the figure measures is not stated
- 315 MW · At Las Vegas 10 openingwhat the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Switch Las Vegas Core Campus?
- Switch Las Vegas Core Campus is a data center project in Las Vegas, Clark County, Nevada.
- Who operates Switch Las Vegas Core Campus?
- Switch is named as the operator of Switch Las Vegas Core Campus.
- How big is Switch Las Vegas Core Campus?
- Switch Las Vegas Core Campus was announced at 495 MW of capacity.
- What stage is Switch Las Vegas Core Campus?
- Switch Las Vegas Core Campus is expanding.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Switch launches Las Vegas 10 data center
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source - 2Switch buys more land at industrial park outside Las Vegas
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source - 3Clark County, Nev., Commissioners Approve Data Center Project
Las Vegas Sun via Government TechnologyTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page