NevadaExecutive Office of the Governor2026Executive order
EO 2026-005: Sets state standards data centers must meet for tax abatements
Official title: Executive Order 2026-005: Nevada Standard for Responsible Data Center Development
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
In effect as of Sep 18, 2026. The official record says: in effect.
- Issued (executive or agency action) (done)
- In effect (current stage)
- Ended or expired (not reached)
What it means for a household (draft rating)
Helps households. The order bars a data center abatement unless the project pays a combined sales and use tax rate of at least 4.6 percent and pays the school support tax in full.
"The Executive Director of the Governor's Office of Economic Development shall not bring before the Board of Economic Development (the "Board") an application for a partial abatement under NRS 360.754 for a data center unless the application provides for a combined sales and use tax rate of not less than 4.6 percent, consisting of the tax imposed by the Sales and Use Tax Act and the Local School Support Tax, neither abated in any amount."Section 2, Minimum terms for an application (official scanned PDF, read from the page image)
We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.
What it does
Who pays for grid costs
Applies to: Data centers seeking partial tax abatements (Nevada)
Starts: 2026-09-18.
“cover the cost of serving the facility without passing those costs on to ratepayers…”
Governor's announcement of Executive Order 2026-005 (Community Support Commitment requirements)
Tax increment
Applies to: Data centers seeking partial tax abatements (Nevada)
Starts: 2026-09-18.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.”
Governor's announcement of Executive Order 2026-005
Who it touches (32)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon Storey County Data Center (Peru Drive)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 1212.78 MW on record (generator capacity), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Apple Reno data center
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CENTRA RNO1
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 0.25 MW announced on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CENTRA RNO2
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 4.4 MW announced on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Colovore RNO01
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 17.45 MW on record (generator capacity), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Copia Power Monarch Data Center
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 1,000 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LAS1 (Las Vegas)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 3.55 MW on record (IT load), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026EdgeCore Reno Campus
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 216 MW announced on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Fleet Data Centers Peru Ridge (Storey County)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 230 MW on record (grid connection), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Fleet Data Centers South Valley (Storey County)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Henderson
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Storey County (Tahoe Reno Industrial Center)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Jet.AI / CCE Moapa Data Center Campus
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 50 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Silver Springs land (Lyon County)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Storey County land (Tahoe Reno Industrial Center)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Novva Apex (North Las Vegas)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Novva North Las Vegas
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 100 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Novva Tahoe Reno
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 100 MW on record (grid connection), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026PowerHouse Reno
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 65 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Apex (Core 2.0), North Las Vegas
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Citadel Campus (TAHOE RENO)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 650 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Las Vegas AI factories (Jones Boulevard)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Las Vegas Core Campus
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 495 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Switch LAS VEGAS (Las Vegas)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 495 MW announced on record, but whether this project seeks a partial tax abatement is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Switch Switch TAHOE RENO (Reno)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Townsite Solar 2 Data Center (Boulder City)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 170 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tract Peru Shelf Technology Park
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 810 MW on record (grid connection), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tract Silver Springs
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 1,600 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tract South Valley Technology Park
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 1,215 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Tract Virginia Highlands Technology Park
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 2,500 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Data Centers Reno Campus (Reno)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has no capacity figure on record, but whether this project seeks a partial tax abatement is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage NV1 (Storey County)
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 224 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
Who acted
- RequesterGov. Joe LombardoExecutive Office of the Governor
Sources
- 1Gov. Lombardo Signs Executive Order Placing Guardrails on Data Center Development (Executive Order 2026-005)
Office of the Governor, State of NevadaTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "EO 2026-005: Sets state standards data centers must meet for tax abatements." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/nv-2026-eo-2026-005
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page