PowerHouse Reno

Storey County,NevadaUnder constructionFirst public 2024Filing entity: PowerHouse Data CentersLast checked Nov 8, 2026

PowerHouse Data CentersDeveloperHarrison StreetDeveloper

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: City or address
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

PowerHouse Reno is a under-construction data center project in Storey County, Nevada. PowerHouse Data Centers is named as developer. It was first public in 2024. It was announced at 65 MW.

PowerHouse Reno is an under-construction data center project in Storey County, Nevada. PowerHouse Data Centers is named as developer. It was announced at 65 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Storey County, Nevada. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

65 MWAnnounced capacity
13Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Storey County, Nevada.See every project on the map

The land, to scale

One football field
49 acres, about 37 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of PowerHouse RenoUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nevada EO 2026-005: Sets state standards data centers must meet for tax abatements

    The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 65 MW on record (not stated), but whether this project seeks a partial tax abatement is not on record.

    “data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)

    Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Nevada

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 65 MW · Bridging powerJan 2024 · what the figure measures is not stated

Public records

13 records found so far. 7 kinds of record are still being collected.

See every record

Court cases and commission dockets

All 10 court cases and commission dockets for this project

Questions people ask

Where is PowerHouse Reno?
PowerHouse Reno is a data center project in Storey County, Nevada.
Who is developing PowerHouse Reno?
PowerHouse Data Centers is named as the developer of PowerHouse Reno.
How big is PowerHouse Reno?
PowerHouse Reno was announced at 65 MW of capacity. The site covers 49 acres.
What stage is PowerHouse Reno?
PowerHouse Reno is under construction. It was first public in 2024.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    PUCN docket information list (all utilities)
    Public Utilities Commission of Nevada
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Opening Comments of the Alliance of Western Energy Consumers, Oregon PUC Docket UM 2024 (filed March 16, 2020)
    Public Utility Commission of Oregon (party filing of the Alliance of Western Energy Consumers)
    Tier 2 · Captured 2026-11-09 · Open the source
  3. 3
    The PUCN Connection newsletter, April 2026 edition
    Public Utilities Commission of Nevada
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    2026 Joint Integrated Resource Plan Volume 1 (Nevada Power and Sierra Pacific, Docket 26-05007)
    NV Energy
    Tier 2 · Captured 2026-11-08 · Open the source
  5. 5
    2026 Joint IRP, Volume 2 (Narrative), Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy
    NV Energy
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Storey County Board of County Commissioners minutes, July 21, 2026 (as published in the September 1, 2026 meeting packet)
    Storey County
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    PowerHouse Data Centers Closes on Nevada Site for PowerHouse Reno
    PowerHouse Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  8. 8
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page