Sierra Pacific Power Company d/b/a NV Energy, Interim Order Approving Gross-Up of Contributions in Aid of Construction (CIAC) Rate

Where it stands: Decided as of Oct 7, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Interim order (October 7, 2026) approving a gross-up of the CIAC rate for Sierra Pacific Power: new large loads, including data centers, reimburse NV Energy's tax cost on customer-funded construction contributions. The Q5 WG2 sweep recorded an interim gross-up rate of about 25.16 percent per testimony and a final gross-up rate of 23.6482 percent from secondary reporting of the order; the signed order's text was not opened in either sweep, so the rate figures are reported, not verified.

The facts

Regulator
Public Utilities Commission of Nevada
Docket number
26-09005
Type
Interconnection rule
Utility
Sierra Pacific Power Co
State
Nevada
Filed
Sep 3, 2026
Status date
Oct 7, 2026
Large-load rules
Yes

Projects served by Sierra Pacific Power Co

Related cases and proceedings

In the record

  1. Utility case, Sep 3, 2026. Utility case filed: Sierra Pacific Power Company d/b/a NV Energy, Interim Order Approving Gross-Up of Contributions in Aid of Construction (CIAC) Rate Public Utilities Commission of Nevada, 26-09005

Sources

  1. 1
    PUCN docket information list (all utilities)
    Public Utilities Commission of Nevada
    Tier 1 · PUCN docket information list (Commission's own docket system), as read firsthand by the Q5 WG2 sweep on 2026-11-08 and staged as this source. The list is session-based; this conversion pass could not re-open it (two failed fetches, 2026-11-09), so captions and statuses rest on the WG2 reading. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Sierra Pacific Power Company d/b/a NV Energy, Interim Order Approving Gross-Up of Contributions in Aid of Construction (CIAC) Rate." Last activity 2026-10-07. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-sierra-pacific-ciac-26-09005