Utility commission
Application of Nevada Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers
Where it stands: Decided as of Mar 11, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
The Contract Tariff Template lets a large customer self-supply part of its load from third-party generation and storage while NV Energy balances and delivers it, under a 10-year minimum term (no more than 20 years). Approval came by stipulation: the Commission voted to accept the stipulation on March 11, 2025 (the stipulation was filed January 24, 2025 and signed by Regulatory Operations Staff, the Bureau of Consumer Protection, Microsoft, Google, and Switch). Tariff sheets filed April 16 and 18, 2025 state that the customer remains responsible for all costs and risks as if NV Energy supplied the full bundled requirement. The customer class overlaps NV Energy's data center load: Microsoft, Google, and Switch are parties, and the Rule 30 style Schedule CTT is the template the WECC peers cite.
The facts
- Regulator
- Public Utilities Commission of Nevada
- Docket number
- 24-05023
- Type
- Large load tariff
- Utility
- Nevada Power Co
- State
- Nevada
- Filed
- May 29, 2024
- Status date
- Mar 11, 2025
- Large-load rules
- Yes
Projects served by Nevada Power Co
Related cases and proceedings
- Utility commission · DecidedSierra Pacific Power Company d/b/a NV Energy, Interim Order Approving Gross-Up of Contributions in Aid of Construction (CIAC) Rate
- Utility commission · Pending before the commissionApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of a Large Load Electric Service Agreement with Amazon Data Services, Inc.
- Utility commission · Pending before the commissionJoint Application of Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2027-2046 integrated resource plan (2026 Joint IRP), proposing the Large Load Electric Service Agreement
- Utility commission · Pending before the commissionJoint Application of Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2027-2046 integrated resource plan (2026 Joint IRP), proposing the Large Load Electric Service Agreement
- Utility commission · DecidedApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of Renewable Energy Agreements with Switch, Ltd. and Apple Inc.
In the record
- Utility case, May 29, 2024. Utility case filed: Application of Nevada Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers Public Utilities Commission of Nevada, 24-05023
Sources
- 1PUCN docket information list (all utilities)
Public Utilities Commission of NevadaTier 1 · PUCN docket information list (Commission's own docket system), as read firsthand by the Q5 WG2 sweep on 2026-11-08 and staged as this source. The list is session-based; this conversion pass could not re-open it (two failed fetches, 2026-11-09), so captions and statuses rest on the WG2 reading. CTT terms and the March 11, 2025 stipulation vote also per the Commission's April 2026 newsletter (Tariff Corner), staged as nv-pucn-newsletter-2026-04 and read firsthand by the Q5 WG2 sweep. · Open the source - 2The PUCN Connection newsletter, April 2026 edition
Public Utilities Commission of NevadaTier 1 · PUCN docket information list (Commission's own docket system), as read firsthand by the Q5 WG2 sweep on 2026-11-08 and staged as this source. The list is session-based; this conversion pass could not re-open it (two failed fetches, 2026-11-09), so captions and statuses rest on the WG2 reading. CTT terms and the March 11, 2025 stipulation vote also per the Commission's April 2026 newsletter (Tariff Corner), staged as nv-pucn-newsletter-2026-04 and read firsthand by the Q5 WG2 sweep. · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Nevada Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers." Last activity 2025-03-11. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-nevada-power-ctt-24-05023