Sierra Pacific, the NV Energy utility serving Storey County, sought Commission approval of Renewable Energy Agreements with Switch, Ltd. and Apple Inc. This is the record that grounds Sierra Pacific Power as the serving utility for the Citadel campus: the northern utility, not Nevada Power, contracted with Switch for renewable energy supply in the north.
The facts
- Regulator
- Public Utilities Commission of Nevada
- Docket number
- 15-11025
- Type
- Other
- Utility
- Sierra Pacific Power Co
- State
- Nevada
- Filed
- Nov 30, 2015
- Large-load rules
- Yes
Projects served by Sierra Pacific Power Co
- Amazon Storey County Data Center (Peru Drive)
- Apple Reno data center
- Colovore RNO01
- Copia Power Monarch Data Center
- EdgeCore Reno Campus
- Fleet Data Centers Peru Ridge (Storey County)
- Fleet Data Centers South Valley (Storey County)
- Google Storey County (Tahoe Reno Industrial Center)
- Microsoft Silver Springs land (Lyon County)
- Microsoft Storey County land (Tahoe Reno Industrial Center)
- Novva Tahoe Reno
- PowerHouse Reno
Related cases and proceedings
- Utility commission · DecidedApplication of Nevada Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers
- Utility commission · DecidedApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Switch Ltd. for Leave to Exit the System of Nevada Power Company d/b/a NV Energy in Accordance with the Provisions of NRS Chapter 704B and NAC Chapter 704B
In the record
- Utility case, Nov 30, 2015. Utility case filed: Application of Sierra Pacific Power Company d/b/a NV Energy for approval of Renewable Energy Agreements with Switch, Ltd. and Apple Inc. Public Utilities Commission of Nevada, 15-11025
Sources
- 1PUCN docket information list (all utilities)
Public Utilities Commission of NevadaTier 1 · PUCN docket information list (caption and filing date, read firsthand 2026-11-09) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Sierra Pacific Power Company d/b/a NV Energy for approval of Renewable Energy Agreements with Switch, Ltd. and Apple Inc.." Last activity 2015-11-30. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pucn-15-11025-sierra-pacific-rea