Application of Switch Ltd. for Leave to Exit the System of Nevada Power Company d/b/a NV Energy in Accordance with the Provisions of NRS Chapter 704B and NAC Chapter 704B
Where it stands: Decided as of Jun 1, 2015
Draft research, not yet verified. Open a source to check any detail.
What it is
Switch's first application to leave NV Energy service and buy energy, capacity, and ancillary services from a provider of new electric resources was denied outright (AWEC's account, citing the docket). The parties then settled Switch's southern Nevada service: an agreement filed with the Commission on July 10, 2015 and signed by Switch, NV Energy, and Commission Regulatory Operations Staff kept Switch as a full requirements customer, served its growing southern load from a new 100 MW First Solar solar project (Switch Station, commercial operation late 2016), charged Switch a premium under the NV Green Energy Rider tariff, and put Switch on the High Load Factor tariff schedule. The settlement was implemented through Nevada Power's Renewable Energy Agreement dockets 15-08005 and 15-11028.
The facts
- Regulator
- Public Utilities Commission of Nevada
- Docket number
- 14-11007
- Type
- Other
- Utility
- Nevada Power Co
- State
- Nevada
- Filed
- Nov 14, 2014
- Status date
- Jun 1, 2015
- Large-load rules
- Yes
Projects served by Nevada Power Co
Related cases and proceedings
- Utility commission · DecidedApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of a Contract Tariff Template (CTT) for companies constructing certain generation and transmission facilities or purchasing energy, capacity, and/or ancillary services from third-party providers
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Switch Ltd. to Purchase Energy, Capacity, and/or Ancillary Services from a Provider of New Electric Resources (second 704B application)
- Utility commission · DecidedApplication of Sierra Pacific Power Company d/b/a NV Energy for approval of Renewable Energy Agreements with Switch, Ltd. and Apple Inc.
In the record
- Utility case, Nov 14, 2014. Utility case filed: Application of Switch Ltd. for Leave to Exit the System of Nevada Power Company d/b/a NV Energy in Accordance with the Provisions of NRS Chapter 704B and NAC Chapter 704B Public Utilities Commission of Nevada, 14-11007
Sources
- 1PUCN docket information list (all utilities)
Public Utilities Commission of NevadaTier 1 · PUCN docket information list (caption and filing date, read firsthand 2026-11-09); AWEC Opening Comments in Oregon PUC Docket UM 2024, page 15 and footnote 32 ('its application was denied outright'); NV Energy newsroom release, July 14, 2015 (settlement terms) · Open the source - 2Opening Comments of the Alliance of Western Energy Consumers, Oregon PUC Docket UM 2024 (filed March 16, 2020)
Public Utility Commission of Oregon (party filing of the Alliance of Western Energy Consumers)Tier 2 · PUCN docket information list (caption and filing date, read firsthand 2026-11-09); AWEC Opening Comments in Oregon PUC Docket UM 2024, page 15 and footnote 32 ('its application was denied outright'); NV Energy newsroom release, July 14, 2015 (settlement terms) · Open the source - 3First Solar, NV Energy and Switch Partner on New 100 Percent Green, Renewable Energy Program (July 14, 2015)
NV Energy (company newsroom)Tier 4 · PUCN docket information list (caption and filing date, read firsthand 2026-11-09); AWEC Opening Comments in Oregon PUC Docket UM 2024, page 15 and footnote 32 ('its application was denied outright'); NV Energy newsroom release, July 14, 2015 (settlement terms) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Switch Ltd. for Leave to Exit the System of Nevada Power Company d/b/a NV Energy in Accordance with the Provisions of NRS Chapter 704B and NAC Chapter 704B." Last activity 2015-06-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pucn-14-11007-switch-704b-exit