Joint Application of Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2027-2046 integrated resource plan (2026 Joint IRP), proposing the Large Load Electric Service Agreement

Where it stands: Pending before the commission as of May 6, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

The 2026 Joint IRP (filed May 6, 2026; 41 volumes) builds its large load planning framework on the Large Load Electric Service Agreement (LLESA), the standard agreement for customer loads of 25 MW or greater. Under the framework, large load additions pay for the infrastructure needed to serve them through customer-specific charges that operate as contributions in aid of construction toward generation and transmission additions, minimum demand and energy charges, security requirements, and termination payments; NV Energy plans on a Base Load Forecast and a reduced Base Minus forecast to isolate the costs that would not be incurred but for large load requests. The Commission's statutory decision deadline runs to December 2, 2026. Approval of the LLESA framework is requested in this docket; each signed LLESA is also filed in its own approval docket.

The facts

Regulator
Public Utilities Commission of Nevada
Docket number
26-05007
Type
Other
Utility
Sierra Pacific Power Co
State
Nevada
Filed
May 6, 2026
Status date
May 6, 2026
Large-load rules
Yes, for loads of 25 MW or more

Projects served by Sierra Pacific Power Co

Related cases and proceedings

In the record

  1. Utility case, May 6, 2026. Utility case filed: Joint Application of Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2027-2046 integrated resource plan (2026 Joint IRP), proposing the Large Load Electric Service Agreement Public Utilities Commission of Nevada, 26-05007

Sources

  1. 1
    2026 Joint Integrated Resource Plan Volume 1 (Nevada Power and Sierra Pacific, Docket 26-05007)
    NV Energy
    Tier 2 · Volume 1 (transmittal letter dated May 6, 2026; joint application for the 2027-2046 IRP) and Volume 2, Narrative (planning framework anchored by the LLESA; customer-specific charges as CIAC, minimum demand and energy charges, security requirements, termination payments; LLESA applies to loads of at least 25 MW; statutory resolution date December 2, 2026). Both volumes re-read firsthand in this pass. · Open the source
  2. 2
    2026 Joint IRP, Volume 2 (Narrative), Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy
    NV Energy
    Tier 1 · Volume 1 (transmittal letter dated May 6, 2026; joint application for the 2027-2046 IRP) and Volume 2, Narrative (planning framework anchored by the LLESA; customer-specific charges as CIAC, minimum demand and energy charges, security requirements, termination payments; LLESA applies to loads of at least 25 MW; statutory resolution date December 2, 2026). Both volumes re-read firsthand in this pass. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Joint Application of Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2027-2046 integrated resource plan (2026 Joint IRP), proposing the Large Load Electric Service Agreement." Last activity 2026-05-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-sierra-pacific-irp-2026