Application of Sierra Pacific Power Company d/b/a NV Energy for approval of a Large Load Electric Service Agreement with Vantage Data Centers

Where it stands: Pending before the commission as of Nov 8, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Project-specific Large Load Electric Service Agreement (LLESA) approval docket, filed alongside the 2026 Joint IRP (Docket 26-05007), which proposes the LLESA framework for loads of 25 MW or greater: customer-specific charges operating as contributions in aid of construction, minimum demand and energy charges, security requirements, and termination payments. The agreement itself is NV Energy's own filing in the Commission's docket; its project-specific terms sit in the docket filings, which this pass did not open.

The facts

Regulator
Public Utilities Commission of Nevada
Docket number
26-05028
Type
Other
Utility
Sierra Pacific Power Co
State
Nevada
Status date
Nov 8, 2026
Large-load rules
Yes, for loads of 25 MW or more

Projects served by Sierra Pacific Power Co

Related cases and proceedings

Sources

  1. 1
    PUCN docket information list (all utilities)
    Public Utilities Commission of Nevada
    Tier 1 · PUCN docket information list (Commission's own docket system), as read firsthand by the Q5 WG2 sweep on 2026-11-08 and staged as this source. The list is session-based; this conversion pass could not re-open it (two failed fetches, 2026-11-09), so captions and statuses rest on the WG2 reading. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Sierra Pacific Power Company d/b/a NV Energy for approval of a Large Load Electric Service Agreement with Vantage Data Centers." Last activity 2026-11-08. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-sierra-pacific-llesa-vantage-26-05028