Application of Nevada Power Company d/b/a NV Energy for approval of revisions to Tariff No. 1, Rule 9 (Line Extensions), addressing large load and data center service requests

Where it stands: Pending before the commission as of Nov 8, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Companion Rule 9 (line extension) revisions to the LLESA framework, filed March 5, 2026: customer-specific charges for Rule 9 (contract-required) generation additions, return of unused contract-required generation amounts, and security requirements when the interconnection study begins. The proposed security is a letter of credit or cash equal to the greater of 50 percent of forecasted 24-month bills at full load or $10 million, with a readiness milestone schedule.

The facts

Regulator
Public Utilities Commission of Nevada
Docket number
26-03010
Type
Interconnection rule
Utility
Nevada Power Co
State
Nevada
Filed
Mar 5, 2026
Status date
Nov 8, 2026
Large-load rules
Yes

Projects served by Nevada Power Co

Related cases and proceedings

In the record

  1. Utility case, Mar 5, 2026. Utility case filed: Application of Nevada Power Company d/b/a NV Energy for approval of revisions to Tariff No. 1, Rule 9 (Line Extensions), addressing large load and data center service requests Public Utilities Commission of Nevada, 26-03010

Sources

  1. 1
    PUCN docket information list (all utilities)
    Public Utilities Commission of Nevada
    Tier 1 · PUCN docket information list (Commission's own docket system), as read firsthand by the Q5 WG2 sweep on 2026-11-08 and staged as this source. The list is session-based; this conversion pass could not re-open it (two failed fetches, 2026-11-09), so captions and statuses rest on the WG2 reading. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Nevada Power Company d/b/a NV Energy for approval of revisions to Tariff No. 1, Rule 9 (Line Extensions), addressing large load and data center service requests." Last activity 2026-11-08. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-nevada-power-rule9-26-03010