Reno,Washoe County,NevadaUnder constructionFirst public 2025Last checked Nov 9, 2026
CENTRA Digital InterconnectDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
CENTRA RNO2 is a under-construction data center project in Reno, Washoe County, Nevada. CENTRA Digital Interconnect is named as operator. It was first public in 2025. It was announced at 4.4 MW.
CENTRA RNO2 is an under-construction data center project in Reno, Washoe County, Nevada. CENTRA Digital Interconnect is named as operator. It was announced at 4.4 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Reno, Washoe County, Nevada. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Timeline
- · New projectFirst public record of CENTRA RNO2Under construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Nevada EO 2026-005: Sets state standards data centers must meet for tax abatements
The act covers data centers seeking a partial tax abatement, whose applications may not go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment; this project has 4.4 MW announced on record, but whether this project seeks a partial tax abatement is not on record.
“data center applications seeking a partial tax abatement cannot be brought before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.” (Governor's announcement of Executive Order 2026-005)
Rule checks: Project is in Nevada. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Nevada
- EO 2026-005 · In effect · Sep 18, 2026Sets state standards data centers must meet for tax abatements
Who's involved
- Developer and operatorCENTRA Digital Interconnect
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordQuestions people ask
- Where is CENTRA RNO2?
- CENTRA RNO2 is a data center project in Reno, Washoe County, Nevada.
- Who operates CENTRA RNO2?
- CENTRA Digital Interconnect is named as the operator of CENTRA RNO2.
- How big is CENTRA RNO2?
- CENTRA RNO2 was announced at 4.4 MW of capacity.
- What stage is CENTRA RNO2?
- CENTRA RNO2 is under construction. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Development Services initiatives and updates page: Data Center Text Amendment and Moratorium
City of Reno, Development ServicesTier 1 · Captured 2026-11-10 · Open the source - 2
- 3CENTRA RNO1 One Sheet (Q2 2025)
CENTRA Digital InterconnectTier 3 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page