TexasSenate89th Legislature (2025)Bill
SB 6: Sets grid connection and cost rules for large loads in Texas
Official title: Relating to the planning for, interconnection and operation of, and costs related to providing service for certain electrical loads and to the generation of electric power by a water supply or sewer service corporation
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Jun 20, 2025. The official record says: signed into law.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it does
Study or report
Applies to: wholesale transmission cost allocation (Texas)
“The Public Utility Commission of Texas shall evaluate whether the existing methodology used to charge wholesale transmission costs to distribution providers under Section 35.004(d), Utilities Code, continues to appropriately assign costs for transmission investment.”
SECTION 6(a)
Who pays for grid costs
Applies to: large load customers subject to the Sec. 37.0561 standards (Texas)
“The commission by rule shall ensure that a large load customer who is subject to the standards adopted under Section 37.0561 contributes to the recovery of the interconnecting electric utility's costs to interconnect the large load to the utility's system.”
SECTION 1, Utilities Code Sec. 35.004(c-1)
Demand response · threshold 75 MW
Applies to: large load customers in the ERCOT region (Texas (ERCOT region))
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.”
SECTION 4, Utilities Code Sec. 39.170(b)
Disclosure
Applies to: large load customers subject to the Sec. 37.0561 standards (Texas)
“The standards must require each large load customer subject to Subsection (c) to disclose to the interconnecting electric utility or municipally owned utility whether the customer is pursuing a substantially similar request for electric service in this state the approval of which would result in the customer materially changing, delaying, or withdrawing the interconnection request. The disclosure may withhold or anonymize competitively sensitive details. The commission by rule shall prohibit an electric utility or municipally owned utility from selling, sharing, or disclosing information submitted to the utility under this subsection other than a disclosure to the commission or the independent organization certified under Section 39.151 for the ERCOT power region, subject to appropriate confidentiality protections.”
SECTION 2, Utilities Code Sec. 37.0561(d)
Effective date
Applies to: the whole act (Texas)
“This Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution. If this Act does not receive the vote necessary for immediate effect, this Act takes effect September 1, 2025.”
SECTION 8
Financial commitment
Applies to: large load customers subject to the Sec. 37.0561 standards (Texas)
“The standards must include uniform financial commitment requirements for the development of transmission infrastructure needed to serve a large load customer subject to Subsection (c). The standards must provide that satisfactory proof of financial commitment may include: (1) security provided on a dollar per megawatt basis as set by the commission; (2) contribution in aid of construction; (3) security provided under an agreement that requires a large load customer to pay for significant equipment or services in advance of signing an agreement to establish electric delivery service; or (4) a form of financial commitment acceptable to the commission other than those provided by Subdivisions (1)-(3).”
SECTION 2, Utilities Code Sec. 37.0561(h)
Fee · threshold 100000 USD
Applies to: large load customers subject to the Sec. 37.0561 standards (Texas)
“The standards must set a flat study fee of at least $100,000 to be paid to the interconnecting electric utility or municipally owned utility for initial transmission screening studies for large loads subject to Subsection (c). A large load customer that requests additional capacity following the screening study must pay an additional study fee based on the new request. The interconnecting electric utility or municipally owned utility shall apply any unused portion of the initial transmission screening study fee as a credit toward satisfying financial obligations for procurement or interconnection agreements at the same geographic site.”
SECTION 2, Utilities Code Sec. 37.0561(f)
Definition · threshold 75 MW
Applies to: large load customers seeking interconnection in Texas (Texas)
“The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).”
SECTION 2, Utilities Code Sec. 37.0561(c)
Who it touches (121)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Google Goodnight campus (Armstrong County)
A 265 MW grid-connected load at a single Armstrong County site in the ERCOT power region is on record in Public Utility Commission orders, over the 75 MW threshold for new interconnections.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 525.5 MW on record (grid connection), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Lancium Clean Campus data centers (Crusoe)
A 1,200 MW grid interconnection at a single Taylor County site in the ERCOT power region is on record and the campus is still expanding, over the 75 MW threshold for new or expanded interconnections.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 1,200 MW on record (not stated), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Data Centers DFW-01 (Plano)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Data Centers DFW-03 (Mansfield)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Data Centers DFW-04 (Plano)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Data Centers LBB-01 (Abernathy)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Mansfield campus (DFW-03)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Aligned Plano campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Alpha Digital Campus
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cipher Barber Lake
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 300 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 300 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cipher Black Pearl
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 300 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 300 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cipher Odessa
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 207 MW on record (IT load), but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 207 MW on record (it load), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Compass Datacenters Red Oak Campus (Red Oak; 360 MW)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 360 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 360 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Compass Red Oak campus (N. Austin Blvd)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 360 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 360 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Compass Red Oak campus (Oglesby Road)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 400 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 400 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Core Scientific Denton
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 371 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 371 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Core Scientific Hunt County
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 431 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 431 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Core Scientific Pecos
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 600 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 600 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Crusoe Abilene AI factory campus for Microsoft
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 2,100 MW not stated on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 2,100 MW on record (not stated), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Crusoe RZ 2026 data center (Haskell County)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Allen
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 77 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 77 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Austin
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Bosque County
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 190 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 190 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Carrollton
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne DFW1 Carrollton
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne DFW10 (Bosque County)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 400 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 400 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne DFW7 Fort Worth campus
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 200 MW on record (not stated), but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 200 MW on record (not stated), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Freestone County
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Houston
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 84 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 84 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Lewisville
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Medina County
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Medina County campus (Sat14), near Castroville
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne SAT8 and SAT9, San Antonio
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Sulphur Springs
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank HOU4 (Houston)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank Red Oak campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 480 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 480 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty AUS11 (Austin)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW10 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW11 (Carrollton)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW12 (Carrollton)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW16 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW17 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW18 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW25 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW26 (Lewisville)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW28 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW29 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW35 (Richardson)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty DFW36 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty IAH10 (Houston)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA1 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA11 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA2 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA3 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA4 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA6 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA7 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix DA9 (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix HO1 (Houston)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Fermi Project Matador (Advanced Energy and Intelligence Campus)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 11,000 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 11,000 MW on record (not stated), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Flexential Talty campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 108 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 108 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Galaxy Helios campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,600 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,600 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Journey Data Center (Haskell County)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Midlothian data center
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Red Oak data center
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Google Thelma Data Center (Haskell County)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Hut 8 Beacon Point
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,000 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,000 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026IREN Childress campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 750 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 750 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026IREN Sweetwater 1
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,400 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,400 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026IREN Sweetwater 2
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 600 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 600 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta El Paso data center
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,000 MW announced on record, but its grid region, its demand as the service measures it, and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,000 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Meta Fort Worth Data Center
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Medina County data center (SAT89/SAT90)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Pecos data center campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 2,000 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 2,000 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft SAT82
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft San Antonio data centers
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Prime Garland campus (DFW02)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Hall County (Hall County; listed as in development)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Hall County (Lancium Clean Campus)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Howard County
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Howard County (Howard County; listed as in consideration)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Irving
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 165 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 165 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Irving 1
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 165 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 165 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS San Antonio
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS San Antonio 2
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 90 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 90 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS South Dallas (Wilmer; listed as in development)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS South Dallas campus (Wilmer)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Riot Corsicana data center campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 910 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 910 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Riot Rockdale data center campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 700 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 700 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Rowan Project Cinco
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Rowan Project Pirate
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026SB Energy Milam County data center (Stargate)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,200 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,200 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Infrastructure DFW02 (Dallas-Fort Worth)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 500 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 500 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026STACK Lancaster
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 220 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 220 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Sabey Data Centers SDC Austin (Austin)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 84 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 84 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Skybox PowerCampus Austin (Hutto)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 600 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 600 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Skybox PowerCampus Dallas (Lancaster)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 300 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 300 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Austin I (Austin)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW B Wilmer (Wilmer)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 90 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 90 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW C Wilmer (Wilmer)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 240 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 240 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW I (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW II (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW III (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers DFW VI (Dallas)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers San Antonio I (San Antonio)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers San Antonio III (San Antonio)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 200 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 200 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream San Antonio III
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 200 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 200 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Wilmer II campus (DFWC)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Sweetwater II
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026TeraWulf and Fluidstack Abernathy campus
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 240 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 240 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Texas Critical Data Centers (TCDC)
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 200 MW on record (IT load), but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 1,000 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Data Centers San Antonio Campus (San Antonio)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has no capacity figure on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Data Centers Shackelford County Campus (Shackelford County)
The act covers customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 1,400 MW announced on record, but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 1,400 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage Frontier campus (Shackelford County)
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,400 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas; 1,400 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Vantage TX1 campus, San Antonio (TX11 and TX12)
The standards must apply only to customers requesting a new or expanded interconnection in the ERCOT power region where the total load at a single site would exceed a demand threshold of 75 megawatts; this project has 96 MW on record (IT load), but whether this project is requesting a new or expanded interconnection and what the total load at its single site would be is not on record.
“The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))
Rule checks: Project is in Texas; 96 MW on record (it load), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked
6 possible matches, not checked yet
These meet the bill's place and size rules as far as our records go. Rule checks are on each Project File.
Other projects we track in Texas (34), not affected
- Aligned Data Centers DFW-02 (Plano)Operating
- Cologix DAL1 (Dallas)Operating
- Cologix DAL2 (Dallas)Operating
- Cologix DAL3 (Dallas)Operating
- Csquare Allen DFW2Operating
- CyrusOne DFW3 AllenOperating
- CyrusOne RichardsonOperating
- CyrusOne SAT1, San AntonioOperating
- CyrusOne SAT2-SAT4 campus, San AntonioOperating
- CyrusOne SAT2 / SAT4 (San Antonio)Operating
- CyrusOne SAT5-SAT6 campus, San AntonioOperating
- CyrusOne SAT5 / SAT6 (San Antonio)Operating
- DataBank ACT1 (Waco)Operating
- DataBank AUS1 (Austin)Operating
- DataBank DFW4 (Dallas)Operating
- DataBank DFW5 (Dallas)Operating
- DataBank DFW6 (Dallas)Operating
- DataBank DFW9 (Dallas)Operating
- DataBank HOU1 (Houston)Operating
- DataBank HOU2 (Houston)Operating
- DataBank HOU3 (Houston)Operating
- DataBank HOU5 (Houston)Operating
- DataBank Plano campus (DFW3 and DFW8)Operating
- Element Critical Houston OneExpanding
- Lancium Fort Stockton Clean CampusOperating
- QTS Fort WorthOperating
- QTS Fort Worth 1Expanding
- Soluna and Applied Digital Project Dorothy 3Proposed
- SPRE Denton modular data centerApproved
- STACK PlanoOperating
- Stream Data Centers DFW IV (Dallas)Operating
- Stream Data Centers DFW V (Dallas)Operating
- Stream Data Centers Houston The Woodlands (The Woodlands)Operating
- Stream Data Centers San Antonio II (San Antonio)Operating
Who acted
- CosponsorCarol AlvaradoSenate
- CosponsorCésar BlancoSenate
- CosponsorDonna CampbellSenate
- CosponsorBrandon CreightonSenate
- CosponsorSarah EckhardtSenate
- CosponsorBrent HagenbuchSenate
- CosponsorBryan HughesSenate
- CosponsorMayes MiddletonSenate
- CosponsorCharles SchwertnerSenate
- Primary sponsorPhil KingSenate
- SponsorKen KingHouse
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · SenateReceived by the Secretary of the SenateStage: Filed
- · SenateFiled
- · SenateRead first time
- · SenateReferred to Business & CommerceStage: In committee
- · SenateCo-author authorized
- · SenateScheduled for public hearing on . . .
- · SenateConsidered in public hearing
- · SenateTestimony taken in committee
- · SenateLeft pending in committee
- · SenateCo-author authorized
- · SenateConsidered in public hearing
- · SenateVote taken in committee
- · SenateReported favorably as substituted
- · SenateCommittee report printed and distributed
- · SenateCo-author authorized
- · SenatePlaced on intent calendar
- · SenateCo-author authorized
- · SenateRules suspended-Regular order of business
- · SenateRead 2nd time
- · SenateAmendment(s) offered (FA1 King)
- · SenateAmended
- · SenateVote recorded in Journal
- · SenatePassed to engrossment as amended
- · SenateVote recorded in Journal
- · SenateThree day rule suspended
- · SenateRecord vote
- · SenateRead 3rd time
- · SenatePassedStage: Passed one chamber
- · SenateRecord vote
- · SenateReported engrossed
- · HouseReceived from the Senate
- · HouseRead first time
- · HouseReferred to State Affairs
- · HouseScheduled for public hearing on . . .
- · HouseConsidered in public hearing
- · HouseTestimony taken/registration(s) recorded in committee
- · HouseLeft pending in committee
- · HouseConsidered in formal meeting
- · HouseCommittee substitute considered in committee
- · HouseReported favorably as substituted
- · HouseComte report filed with Committee Coordinator
- · HouseCommittee report distributed
- · HouseCommittee report sent to Calendars
- · HouseConsidered in Calendars
- · HousePlaced on General State Calendar
- · HouseRead 2nd time
- · HouseAmendment(s) offered (1-King)
- · HouseAmendment amended (2-Anchía)
- · HouseRecord vote (RV#3402)
- · HouseStatement(s) of vote recorded in Journal
- · HouseAmendment adopted as amended (1-King)
- · HouseRecord vote (RV#3403)
- · HouseStatement(s) of vote recorded in Journal
- · HouseAmended (3-Turner)
- · HouseRecord vote (RV#3404)
- · HouseStatement(s) of vote recorded in Journal
- · HouseAmended (4-Darby)
- · HouseRecord vote (RV#3405)
- · HouseStatement(s) of vote recorded in Journal
- · HousePoint of order withdrawn (Rule 4, Section 32(c)(1))
- · HouseRecommitted to committee
- · HouseConsidered in formal meeting
- · HouseCommittee substitute considered in committee
- · HouseReported favorably as substituted
- · HouseComte report filed with Committee Coordinator
- · HouseCommittee report distributed
- · HouseCommittee report sent to Calendars
- · HouseConsidered in Calendars
- · HousePlaced on Major State Calendar
- · HouseRead 2nd time
- · HouseAmendment(s) offered (1-King)
- · HouseAmendment amended (2-Anchía)
- · HouseRecord vote (RV#3555)
- · HouseStatement(s) of vote recorded in Journal
- · HouseAmendment adopted as amended (1-King)
- · HouseRecord vote (RV#3556)
- · HouseAmended (3-Raymond and McLaughlin)
- · HouseRecord vote (RV#3557)
- · HouseStatement(s) of vote recorded in Journal
- · HouseStatement of Leg. Intent Recorded in Journal
- · HousePassed to 3rd reading as amended
- · HouseRecord vote (RV#3558)
- · HouseRead 3rd time
- · HousePassedStage: Passed both chambers
- · HouseRecord vote (RV#3643)
- · HouseStatement(s) of vote recorded in Journal
- · SenateHouse passage as amended reported
- · SenateHouse amendment(s) laid before the Senate
- · SenateRead
- · SenateSenate concurs in House amendment(s)
- · SenateRecord vote
- · HouseSenate concurs in House amendment(s)-reported
- · SenateReported enrolled
- · SenateCo-author authorized
- · SenateSigned in the Senate
- · HouseSigned in the House
- · ExecutiveSent to the Governor
- · ExecutiveSigned by the GovernorStage: Signed into law
- · ExecutiveEffective immediatelyStage: In effect
More from Texas
- SB 2222 · Died or failedWould exempt data center property and energy equipment from property tax
Sources
- 189(R) SB 6, Enrolled version, Bill Text
Texas Legislature Online (capitol.texas.gov)Tier 1 · Open the source - 2
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 6: Sets grid connection and cost rules for large loads in Texas." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/tx-89-sb-6
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page