Talty,Kaufman County,TexasAnnouncedFirst public 2026Last checked Nov 8, 2026

FlexentialDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Flexential Talty campus is an announced data center project in Talty, Kaufman County, Texas. Flexential is named as operator. It was first public in 2026. It was announced at 108 MW.

Flexential Talty campus is an announced data center project in Talty, Kaufman County, Texas. Flexential is named as operator. It was announced at 108 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Talty, Kaufman County, Texas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

108 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Kaufman County, Texas.See every project on the map

The land, to scale

One football field
110 acres, about 83 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Flexential Talty campusAnnounced

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Texas SB 6: Sets grid connection and cost rules for large loads in Texas

    The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 108 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.

    “The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))

    Rule checks: Project is in Texas; 108 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked

Bills and laws in Texas

Open Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Flexential Talty campus?
    Flexential Talty campus is a data center project in Talty, Kaufman County, Texas.
    Who operates Flexential Talty campus?
    Flexential is named as the operator of Flexential Talty campus.
    How big is Flexential Talty campus?
    Flexential Talty campus was announced at 108 MW of capacity. The site covers 110 acres.
    What stage is Flexential Talty campus?
    Flexential Talty campus is announced. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
      Flexential
      Tier 4 · Captured 2026-11-08 · Open the source