Project File

Galaxy Helios campus

Dickens County,TexasExpandingLast checked Nov 13, 2026

GalaxyDeveloper and operatorAEP TexasElectric utilityCoreWeaveEnd user

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Still to confirm: City or address
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Galaxy Helios campus is an expanding data center project in Dickens County, Texas. Galaxy is named as operator. It was announced at 1,600 MW.

Galaxy Helios campus is an expanding data center project in Dickens County, Texas. Galaxy is named as operator. It was announced at 1,600 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Dickens County, Texas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1,600 MWAnnounced capacity
10Public records we have found
1Tax agreement on record

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Dickens County, Texas.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Texas SB 6: Sets grid connection and cost rules for large loads in Texas

    The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has 1,600 MW announced on record, but its demand as the service measures it and its participation in another reliability or ancillary service are not on record.

    “The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))

    Rule checks: Project is in Texas; 1,600 MW on record (announced), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked

Bills and laws in Texas

Open Bill Watch

Who's involved

Public records

10 records found so far. 7 kinds of record are still being collected.

See every record

Court cases and commission dockets

All 9 court cases and commission dockets for this project

Questions people ask

Where is Galaxy Helios campus?
Galaxy Helios campus is a data center project in Dickens County, Texas.
Who operates Galaxy Helios campus?
Galaxy is named as the operator of Galaxy Helios campus.
How big is Galaxy Helios campus?
Galaxy Helios campus was announced at 1,600 MW of capacity.
What stage is Galaxy Helios campus?
Galaxy Helios campus is expanding.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Chapter 312 Tax Abatement Agreements detail file (registry download), last updated 2026-10-10
    Texas Comptroller of Public Accounts
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  3. 3
    Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
    Texas Secretary of State
    Tier 1 · Captured 2026-11-07 · Open the source
  4. 4
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  5. 5
    Senate Bill 6 enrolled bill analysis
    Texas Senate Research Center
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    Large Load Update, presentation to the House State Affairs Committee
    ERCOT
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
    White and Case LLP
    Tier 2 · Captured 2026-11-07 · Open the source
  8. 8
    PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
    SiteBraid
    Tier 3 · Captured 2026-11-07 · Open the source
  9. 9
    PUCT Interchange filing index, Project or Docket No. 59943
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    PUCT Interchange filing index, Project or Docket No. 58317
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    PUCT Interchange filing index, Project or Docket No. 59115
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Galaxy Digital Form 8-K: Helios Campus ERCOT Approval for Additional 830 MW
    Galaxy Digital Inc. (SEC Form 8-K)
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page