Rulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561

Where it stands: Decided as of Sep 18, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

ERCOT-wide rule 16 TAC 25.194 for loads of 75 MW or more at a single site. Before study, the customer signs an intermediate agreement, makes officer-level disclosures (site control, backup generation, duplicate requests elsewhere), pays a $100,000 study fee, and posts financial security of $50,000 per MW of requested peak demand, figured on gross demand. After transmission capacity is allocated, the customer must sign a Standard Large Load Interconnection Agreement within 60 days and post security at the greater of $50,000 per MW or its allocated upgrade costs. Withdrawing after allocation forfeits 20 percent of the security tied to the withdrawn capacity; withdrawing before the study begins returns it in full; missing the agreement deadline forfeits all of it. Security returns in 20 percent steps from energization as minimum billing demand milestones are met. The proposal's separate non-refundable $50,000 per MW interconnection fee was removed at adoption.

The facts

Regulator
Public Utility Commission of Texas
Docket number
Project No. 58481
Type
Interconnection rule
Utility
AEP Texas North Company
State
Texas
Filed
Jun 20, 2025
Status date
Sep 18, 2026
Large-load rules
Yes, for loads of 75 MW or more

Projects served by AEP Texas North Company

Related cases and proceedings

In the record

  1. Utility case, Jun 20, 2025. Utility case filed: Rulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561 Public Utility Commission of Texas, Project No. 58481

Sources

  1. 1
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · PUCT SB 6 rulemakings chart, row for Project 58481 (scoping, drafts, adoption); White and Case alert (September 2026), PUCT Rule section and footnotes 1, 5, 6 (adoption terms); SiteBraid analysis citing Item 218 at page 28 (withdrawal forfeiture) · Open the source
  2. 2
    PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
    White and Case LLP
    Tier 2 · PUCT SB 6 rulemakings chart, row for Project 58481 (scoping, drafts, adoption); White and Case alert (September 2026), PUCT Rule section and footnotes 1, 5, 6 (adoption terms); SiteBraid analysis citing Item 218 at page 28 (withdrawal forfeiture) · Open the source
  3. 3
    PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
    SiteBraid
    Tier 3 · PUCT SB 6 rulemakings chart, row for Project 58481 (scoping, drafts, adoption); White and Case alert (September 2026), PUCT Rule section and footnotes 1, 5, 6 (adoption terms); SiteBraid analysis citing Item 218 at page 28 (withdrawal forfeiture) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Rulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561." Last activity 2026-09-18. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-58481