Project File

Lancium Clean Campus data centers (Crusoe)

Abilene,Taylor County,TexasUnder constructionFirst public 2021Filing entity: LanciumLast checked Nov 13, 2026

CrusoeDeveloper and operatorLanciumDeveloper and sold the landNVIDIAChip and hardware supplierOracleCompute provider

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Lancium Clean Campus data centers (Crusoe) is a under-construction data center project in Abilene, Taylor County, Texas. Crusoe is named as operator. It was first public in 2021. It was announced at 1,200 MW.

Lancium Clean Campus data centers (Crusoe) is an under-construction data center project in Abilene, Taylor County, Texas. Crusoe is named as operator. It was announced at 1,200 MW. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Abilene, Taylor County, Texas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

Lancium Clean Campus video · 1 min 59 sec

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

1,200 MWAnnounced capacity
37Public records we have found
6Tax agreements on record
34.1Generator capacity, MW per GE LM2500 turbine (site-rated)

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    Reporting on the county deals says Taylor County abates 80 percent of campus property tax for 10 years.

    Goes both ways
  2. Tax breaks

    Three rounds of county tax agreements cover this campus; the newest was adopted December 16, 2025.

    Goes both ways
  3. Money for schools and services

    The city development corporation agreed to repay $2.5 million of the campus water and sewer costs.

    Goes both ways
  4. Electricity bill

    The campus runs 10 gas turbines rated about 360 megawatts for its own power, under a state permit.

    Not known yet
  5. Water

    The campus buys city water and sewer service; the city covers $2.5 million of those costs under its deal.

    Comes from the community
  6. Jobs

    Job counts for this campus are not in our records yet.

    Not known yet
  7. Next door: height, setbacks, noise

    No county setback, noise, or height rule for this campus is in our records.

    Not known yet
  8. Your say

    Reporting on the county minutes says commissioners approved the newest tax agreements 4 to 1 on December 16, 2025.

    How to take part
Aerial view of Lancium Clean Campus data centers (Crusoe) in Abilene, Taylor County, Texas, captured 2022
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2022Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Taylor County, Texas.See every project on the map

Timeline

  1. · DecisionTexas Commission on Environmental Quality: Executive director completed the technical review and prepared a draft permit (preliminary decision); final approval not yet issued (air permit) for Lancium Clean Campus data centers (Crusoe)Permit No. 182126 / PSDTX1688 / GHGPSDTX263
  2. · Tax dealTax agreement approved: Tax abatement agreement and second tax abatement agreement (chapter 312) for Lancium LLC, Abilene DC 9, LLC, Abilene DC 10, LLC, Abilene DC TPP, LLC
  3. · VoteTaylor County Commissioners Court voted on Adoption of the resolution approving the Taylor County tax abatement agreements for Lancium Clean Campus phases 9 and 10 and the electricity generation plant (Lancium LLC with Abilene DC 9, DC 10, and DC TPP)1 no, 4 yes
  4. · Tax dealTax agreement approved: Tax abatement agreements and second tax abatement agreements (chapter 312) for Lancium LLC, Abilene DC 9, LLC, Abilene DC 10, LLC, Abilene DC TPP, LLCThe executed Phase 10 Second Tax Abatement Agreement posted by the city grants an abatement of 75 percent of the taxable value of new improvements and tangible personal property for ten consecutive years, in Reinvestment Zone No. RZ25-1....
  5. · FilingFiled with Texas Commission on Environmental Quality: air permit for Lancium Clean Campus data centers (Crusoe)Permit No. 182126 / PSDTX1688 / GHGPSDTX263
  6. · FilingFiled with Texas Commission on Environmental Quality: air permit for Lancium Clean Campus data centers (Crusoe)Permit No. 182126 / PSDTX1688 / GHGPSDTX263
  7. · DecisionTexas Secretary of State: Texas charter of ABILENE DC 10, LLC (Secretary of State file number 0806231864) for Lancium Clean Campus data centers (Crusoe)0806231864
  8. · DecisionTexas Secretary of State: Texas charter of ABILENE DC 9, LLC (Secretary of State file number 0806231869) for Lancium Clean Campus data centers (Crusoe)0806231869
All 39 events for this project

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Texas SB 6: Sets grid connection and cost rules for large loads in Texas

    A 1,200 MW grid interconnection at a single Taylor County site in the ERCOT power region is on record and the campus is still expanding, over the 75 MW threshold for new or expanded interconnections.

    “The standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region. The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).” (SECTION 2, Utilities Code Sec. 37.0561(c))

    Rule checks: Project is in Texas; 1,200 MW on record (not stated), threshold 75 MW (SECTION 2, Utilities Code Sec. 37.0561(c)). Still to check: who it covers: not checked

Bills and laws in Texas

Open Bill Watch

Who's involved

Power and water

Water, as reported by the operator

Per building per year: anticipated water use for cooling system maintenance and water quality purposes. An anticipated figure stated by the operator, not measured use

  • Annual maintenance: 50,000 gal
  • Initial fill: 1,000,000 gal

Capacity, as announced or filed

  • 200 MW · Phase 1 (initial data center, two buildings)Jul 2024 · what the figure measures is not stated
  • 206 MW · Phase 1 (two buildings, as financed)Oct 2024 · what the figure measures is not stated
  • 1,200 MW · Campus total (eight buildings)Mar 2025 · what the figure measures is not stated
  • 1,200 MW · Campus totalMar 2025 · grid connection

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Texas Commission on Environmental Quality, Standard Permit Registration No. 177263 (Project No. 387309)

    Permitted run hours
    8,760 hours per year per GE LM2500 turbine
    Generator capacityEstimated
    360.5 MWOur arithmetic: 5 x 38 MW plus 5 x 34.1 MW. On-site generation nameplate, not data center load; the permit states no combined total.
    Generator capacity
    34.1 MW per GE LM2500 turbine (site-rated)
    Stated in the filing
    10 natural gas simple-cycle turbines (5 Titan 350 and 5 GE LM2500)
    Generator capacity
    38 MW per Titan 350 turbine (site-rated)
  • Texas Commission on Environmental Quality, Permit No. 182126 / PSDTX1688 / GHGPSDTX263

    Stated in the filing
    760.33 tons per year of nitrogen oxides (NOx), proposed emissions
    Stated in the filing
    451.1 tons per year of particulate matter, 10 microns or less (PM10), proposed emissions
    Stated in the filing
    313.2 tons per year of particulate matter, 2.5 microns or less (PM2.5), proposed emissions
    Stated in the filing
    815.59 tons per year of volatile organic compounds (VOC), proposed emissions
    Stated in the filing
    49.77 tons per year of hazardous air pollutants (HAPs), proposed emissions
    Stated in the filing
    233.9 tons per year of sulfur dioxide (SO2), proposed emissions
    Stated in the filing
    870.07 tons per year of carbon monoxide (CO), proposed emissions
    Buildings
    2 buildings (Buildings 9 and 10)

Public records

37 records found so far. 3 kinds of record are still being collected.

See every record

Court cases and commission dockets

All 9 court cases and commission dockets for this project

In the news

All stories about this project

Questions people ask

Where is Lancium Clean Campus data centers (Crusoe)?
Lancium Clean Campus data centers (Crusoe) is a data center project in Abilene, Taylor County, Texas.
Who operates Lancium Clean Campus data centers (Crusoe)?
Crusoe is named as the operator of Lancium Clean Campus data centers (Crusoe).
How big is Lancium Clean Campus data centers (Crusoe)?
Lancium Clean Campus data centers (Crusoe) was announced at 1,200 MW of capacity.
What stage is Lancium Clean Campus data centers (Crusoe)?
Lancium Clean Campus data centers (Crusoe) is under construction. It was first public in 2021.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Technical Review, Standard Permit Registration No. 177263 (Project No. 387309), Longhorn Data Center
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Electric Generating Units Air Quality Standard Permit revision authorization letter, Registration No. 177263, Abilene DC 1 LLC (Longhorn Data Center)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Plain Language Summary for New Source Review, Initial Application for Air New Source Review Permit Numbers 182126, GHGPSDTX263 and PSDTX1688, Crusoe Energy Systems LLC (CN606257079), Longhorn Data Center (RN112029061)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Notice of Receipt of Application and Intent to Obtain Air Permit (NORI), Permit 182126 / PSDTX1688 / GHGPSDTX263, Crusoe Energy Systems LLC, Longhorn Data Center Buildings 9 and 10
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Taxpayer Records (franchise tax, with Secretary of State file numbers and charter dates)
    Texas Comptroller of Public Accounts (data.texas.gov)
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    Notice of Application and Preliminary Decision for Air Quality Permits, Proposed Air Quality Permit Numbers 182126, PSDTX1688, and GHGPSDTX263, Crusoe Technologies LLC, Abilene, Taylor County
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Commissioners Court Minutes, September 9, 2025
    Taylor County
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    Taylor County commissioners approve tax abatement for Lancium, Abilene Reporter-News, December 21, 2021
    Abilene Reporter-News
    Tier 3 · Captured 2026-11-07 · Open the source
  9. 9
    Commissioners Court meeting record, December 21, 2021
    Taylor County
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    City Council Agenda, December 4, 2025
    City of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  11. 11
    Commissioners Court Minutes, December 16, 2025
    Taylor County
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    DCOA Board Meeting Packet, August 5, 2025
    Development Corporation of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    Second Tax Abatement Agreement (Phase 10), City of Abilene, Texas, Lancium LLC and Abilene DC 10, LLC
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  14. 14
    Resolution No. 171-2025, City of Abilene, approving Tax Abatement Agreements and Second Tax Abatement Agreements with Lancium, LLC and Abilene DC 1, 3, 4, 5, 6, 7 and 8, LLC (Phases 1-8)
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Second Tax Abatement Agreement (Phase 5), City of Abilene, Texas, Lancium LLC and Abilene DC 5, LLC
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  16. 16
    Abilene Ordinance 100-2025, 3rd Amendment to Planned Development District 181
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Abilene Ordinance 56-2025, PDD-181 buffer exhibit amendment
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Abilene Land Development Code, Section 4.2.9.2, Performance Standards Regulating Noise (Table 4-3)
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Abilene Code of Ordinances, Section 20-1, Noise control generally
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Abilene Land Development Code, Section 2.3.4.5, Planned Development (PD) District
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  22. 22
    Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
    Texas Secretary of State
    Tier 1 · Captured 2026-11-07 · Open the source
  23. 23
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  24. 24
    Senate Bill 6 enrolled bill analysis
    Texas Senate Research Center
    Tier 1 · Captured 2026-11-07 · Open the source
  25. 25
    Large Load Update, presentation to the House State Affairs Committee
    ERCOT
    Tier 1 · Captured 2026-11-07 · Open the source
  26. 26
    PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
    White and Case LLP
    Tier 2 · Captured 2026-11-07 · Open the source
  27. 27
    PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
    SiteBraid
    Tier 3 · Captured 2026-11-07 · Open the source
  28. 28
    PUCT Interchange filing index, Project or Docket No. 59943
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  29. 29
    PUCT Interchange filing index, Project or Docket No. 58317
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  30. 30
    PUCT Interchange filing index, Project or Docket No. 59115
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  31. 31
    The Development Corporation of Abilene City of Abilene and Taylor County Announce Expanded Development within Lancium's Clean Campus through Crusoe's 998000 Square Foot Data Center Project
    Development Corporation of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  32. 32
    Crusoe Expands AI Data Center Campus in Abilene to 1.2 Gigawatts
    Crusoe (via GlobeNewswire, on Lancium's site)
    Tier 4 · Captured 2026-11-07 · Open the source
  33. 33
    Water Production
    City of Abilene
    Tier 1 · Captured 2026-11-08 · Open the source
  34. 34
    Crusoe to Build Initial 200MW AI Data Center With Plans to Expand at 1.2 GW Lancium Clean Campus
    Crusoe / Lancium
    Tier 4 · Captured 2026-11-08 · Open the source
  35. 35
    Crusoe, Blue Owl Capital and Primary Digital Infrastructure Enter $3.4 billion Joint Venture for AI Data Center Development
    Crusoe / Blue Owl Capital / Primary Digital Infrastructure
    Tier 4 · Captured 2026-11-08 · Open the source
  36. 36
    Lancium Gigawatt AI Data Center Campuses
    Lancium
    Tier 4 · Captured 2026-11-08 · Open the source
  37. 37
    An inside look at the Abilene AI data center
    Crusoe
    Tier 4 · Captured 2026-11-09 · Open the source
  38. 38
    Announcing The Stargate Project
    OpenAI
    Tier 4 · Captured 2026-11-07 · Open the source
  39. 39
    Form EIA-861 detailed data files 2023 (Service Territory and Utility Data)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page