Project File · Public records

Every public record we have for Lancium Clean Campus data centers (Crusoe)

Abilene, Taylor County, TexasUnder constructionFirst public 2021Filing entity: LanciumLast checked Nov 13, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

37 of 37 records

2026

  • Air permitUnder reviewAug 5, 2026Texas Commission on Environmental Quality

    Texas Commission on Environmental Quality, Permit No. 182126 / PSDTX1688 / GHGPSDTX263

    Executive director completed the technical review and prepared a draft permit (preliminary decision); final approval not yet issued

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    NAPD, Application and Preliminary Decision section; Notice Issuance Date: August 5, 2026

  • Utility proceedingProposedJul 9, 2026Public Utility Commission of Texas

    Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region

    Proposal, not yet adopted. Transmission costs would move from four summer coincident peaks (4CP) to twelve monthly coincident peaks (12CP), measured on a 30-minute interval. New rule 16 TAC 25.252 would set the terms every transmission provider and investor-owned distribution utility tariff must contain for large load customers, including a minimum billing demand fixed for 20 years, billed from when service is made available whether or not the customer has energized or is fully using the capacity. Interconnection fees and forfeited security under 25.194 would offset the transmission revenue requirement.

    Project No. 58000

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Proposal for Publication, Item 8, filed 2026-07-09, preamble (12CP, 25.252, minimum billing demand) and question 2 (minimum fixed for 20 years as proposed); Texas Register, July 24, 2026, Proposed Rules (TRD-202602812)

  • Utility proceedingPending before the commissionJul 1, 2026Public Utility Commission of Texas

    Joint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement

    Net metering arrangement under PURA Sec. 39.916 pairing the Willow Springs wind facility with the Haskell DC data center load; Electric Transmission Texas, LLC and AEP Texas Inc. filed notices to participate (July 30 and 31, 2026). The latest filing is an October 8, 2026 motion for extension of time; no terms are approved yet.

    Docket No. 59943

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Index of filings: joint application of July 1, 2026; notices to participate of Electric Transmission Texas, LLC (July 30, 2026) and AEP Texas Inc. (July 31, 2026); extension motion of October 8, 2026

2025

  • Setback ruleProposedDec 18, 2025Abilene

    Adopted 200-foot open-space buffer for the data center campus district

    Ordinance 100-2025 requires a 200-foot buffer, designated on the district exhibit map, to be maintained as open space with all existing vegetation kept. Ordinance 56-2025 replaced the buffer map (Exhibit D) with a revised one (Exhibit E). This is an adopted district condition, not just a staff recommendation as first staged.

    PDD-181 conditions, Ordinance 100-2025 Exhibit A; buffer map amended by Ordinance 56-2025

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Ordinance 100-2025 Exhibit A items (6)-(7); Ordinance 56-2025 Exhibit A

  • Zoning ruleIn effectDec 18, 2025Abilene

    Data center campus zoned through Planned Development District 181

    The Land Development Code use matrix names no data center use, so the Crusoe and Lancium campus runs through its own district ordinance. PDD-181, created by Ordinance 25-2023, has Light Industrial as its base district, and Ordinance 100-2025 permits Data Center: High Performance Computing and Data Center: Bitcoin Mining by right anywhere in the district, under Light Industrial development standards.

    Planned Development District 181 (PDD-181), created by Ordinance No. 25-2023; third amendment Ordinance 100-2025

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Ordinance 100-2025 Exhibit C (permitted uses); Land Development Code Sections 2.3.4.5 and 2.4.2.1 (Municode)

  • Tax agreementDec 16, 2025Taylor County

    Tax Abatement Agreement and Second Tax Abatement Agreement (Chapter 312)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    City of Abilene council agenda, December 4, 2025, item 17 (names the same project entities and agreement types); Taylor County Commissioners Court minutes, December 16, 2025, item 7D, pp. 5-6 (county adoption, carried 4-1, Commissioner Kendrick against), verified firsthand 2026-11-11.

  • Recorded voteDec 16, 2025Taylor County Commissioners Court

    Adoption of the resolution approving the Taylor County tax abatement agreements for Lancium Clean Campus phases 9 and 10 and the electricity generation plant (Lancium LLC with Abilene DC 9, DC 10, and DC TPP)

    4 yes, 1 no. Brad Birchum (Commissioner, Precinct 3): yes; Chuck Statler (Commissioner, Precinct 4): yes; Kyle Kendrick (Commissioner, Precinct 2): no; Phil Crowley (County Judge): yes; Randall D. Williams (Commissioner, Precinct 1): yes.

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    Minutes of December 16, 2025, item 7D, pp. 5-6: motion by Judge Crowley, seconded by Commissioner Birchum, carried 4-1 with Commissioner Kendrick voting no; all five members present (p. 1).

  • Recorded voteDec 16, 2025Taylor County Commissioners Court

    Resolution approving Tax Abatement Agreement and Second Tax Abatement Agreement with Lancium LLC and Abilene DC 9, LLC (Phase 9), Abilene DC 10, LLC (Phase 10), and Abilene DC TPP, LLC (Electricity Generation Plant)

    1 no. Kyle Kendrick (Commissioner, Precinct 2): no.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Minutes, item 7D: the motion was seconded by Commissioner Birchum and carried with 4-1 vote, Commissioner Kendrick voted No

  • Utility proceedingDecidedDec 12, 2025Public Utility Commission of Texas

    Joint Application of West Texas Solar Project II LLC and Silver Basin Digital Infrastructure LLC for Approval of a Net Metering Arrangement

    Net metering arrangement under PURA Sec. 39.916: the West Texas Solar facility’s capacity factor test exhibit was filed under seal, and the final order’s findings included a condition that the facility achieve the specified level of customer capacity satisfaction. The order carries no load threshold and no tariff terms.

    Docket No. 59115

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Index of filings: joint application of December 12, 2025; Sealed Exhibit DML-2 (November 18, 2026) notice of filing; final order signed October 15, 2026

  • Tax agreementDec 4, 2025Abilene

    Tax Abatement Agreements and Second Tax Abatement Agreements (Chapter 312)

    The executed Phase 10 Second Tax Abatement Agreement posted by the city grants an abatement of 75 percent of the taxable value of new improvements and tangible personal property for ten consecutive years, in Reinvestment Zone No. RZ25-1. The Phase 9 and Electricity Generation Plant agreements were not read in this pass, so their percentages are not stated here.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    City Council agenda, December 4, 2025, item 17 (names the Phase 9, Phase 10 and Electricity Generation Plant agreements and entities); Phase 10 Second Tax Abatement Agreement, page 1 and Sections 4.2 to 4.5 (pages 7 and 8 of 21); premises p. 1 and Exhibit A p. 18 of 21 (read firsthand 2026-11-11): the agreement is between the City, Lancium LLC (Developer) and Abilene DC 10, LLC (Lessee); the Developer leases the Exhibit A land to the Lessee; Exhibit A closes "containing 4,761,178 square feet or 109.30 acres of land" within Lot 101, Block B, Lancium Subdivision; the Leased Parcel is located within Reinvestment Zone No. RZ25-1 (about 615 acres, described in Exhibit B, pp. 19-20). No address 615 FM 2404 appears in the agreement.

  • Air permitUnder reviewNov 7, 2025Texas Commission on Environmental Quality

    Texas Commission on Environmental Quality, Permit No. 182126 / PSDTX1688 / GHGPSDTX263

    Stated in the filing:
    760.33 tons per year of nitrogen oxides (NOx), proposed emissions
    Stated in the filing:
    451.1 tons per year of particulate matter, 10 microns or less (PM10), proposed emissions
    Stated in the filing:
    313.2 tons per year of particulate matter, 2.5 microns or less (PM2.5), proposed emissions
    Stated in the filing:
    815.59 tons per year of volatile organic compounds (VOC), proposed emissions
    Stated in the filing:
    49.77 tons per year of hazardous air pollutants (HAPs), proposed emissions
    Stated in the filing:
    233.9 tons per year of sulfur dioxide (SO2), proposed emissions
    Stated in the filing:
    870.07 tons per year of carbon monoxide (CO), proposed emissions
    Buildings:
    2 buildings (Buildings 9 and 10)
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    NORI (notice issued November 19, 2025): application by Crusoe Energy Systems LLC for Longhorn Data Center Buildings 9 and 10, 615 Farm-to-Market Road 2404, Abilene

  • Business registrationIssuedSep 23, 2025Texas Secretary of State

    Texas Secretary of State, 0806231869

    Texas charter of ABILENE DC 9, LLC (Secretary of State file number 0806231869)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 9, LLC'

  • Business registrationIssuedSep 23, 2025Texas Secretary of State

    Texas Secretary of State, 0806231864

    Texas charter of ABILENE DC 10, LLC (Secretary of State file number 0806231864)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 10, LLC'

  • Tax agreementSep 9, 2025Taylor County

    Tax Abatement Agreements and Amended Tax Abatement Agreements (Chapter 312)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Minutes, items 6A (public hearing) and 6D (resolution adoption, carried unanimously)

  • Tax agreementAug 28, 2025Abilene

    Tax Abatement Agreements and Second Tax Abatement Agreements, plus amendments (Chapter 312)

    Resolution 171-2025 approves separate Tax Abatement Agreements and Second Tax Abatement Agreements for Phase 1/2 and Phases 3 through 8, plus Amendment No. 1 to the Second Amended and Restated Tax Abatement Agreement and Amendment No. 1 to the Second Amended and Restated Second Tax Abatement Agreement. The executed Phase 5 Second Tax Abatement Agreement posted by the city grants an abatement of 85 percent of the taxable value of new improvements and tangible personal property for ten consecutive years; a second agreement runs after the first agreement period ends, so the pair spans two consecutive ten year periods. Phase 5 Second Agreement, Section 3(c): the lessee covenants to employ and maintain a minimum of 50 full-time equivalent employment positions at the leased parcel, with an annual compliance verification delivered to the city.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Resolution 171-2025, caption and Part 1 (pages 1 and 3); Phase 5 Second Tax Abatement Agreement, Sections 3(a), 3(c), 4.2, 4.3 and 4.5 (pages 5, 7 and 8 of 20)

  • Utility proceedingPending before the commissionJun 30, 2025Public Utility Commission of Texas

    SB 6 Implementation

    Umbrella project coordinating the five SB 6 child projects already staged (Project Nos. 58479, 58480, 58481, 58482, 58484): ERCOT demand management (new and existing loads of 75 MW or more), net metering protocols under PURA Sec. 39.916 with Exhibit A the 2026 ERCOT Large Load Interconnection Process Handbook (September 2026 version), a large load interconnection cost responsibility rulemaking under PURA Sec. 39.168, transmission planning criteria for large loads under PURA Sec. 37.0561, and virtual power plant programs. Staff’s implementation roadmap was updated in September 2026.

    Project No. 58317

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Interchange docket record: SB 6 Implementation Roadmap memorandum (updated September 2026 version filed September 22, 2026) and the Exhibit A cover memorandum (ERCOT Large Load Interconnection Process Handbook, September 2026)

  • Utility proceedingPending before the commissionJun 20, 2025Public Utility Commission of Texas

    Evaluation of Transmission Cost Recovery

    The Commission's evaluation of the four coincident peak (4CP) method of assigning transmission costs, which SB 6 required it to complete and act on by December 31, 2026. The question is whether charging on four summer peaks lets large, flexible loads avoid paying for the grid they use all year. The evaluation sets no terms itself; the rulemaking that carries the result is Project No. 58000.

    Project No. 58484

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    PUCT SB 6 rulemakings chart, row for Project 58484 (evaluation period; staff questions issued 2025-08-05)

  • Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas

    Rulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169

    Rule 16 TAC 25.205: a net metering arrangement between an existing stand-alone generation resource and a new large load of 75 MW or more needs an ERCOT study and prior Commission approval. ERCOT has 120 days to study the arrangement after it receives the needed information; the Commission then has 60 days to approve, deny, or approve with conditions, including hold-harmless protection against stranded or underutilized transmission assets.

    Project No. 58479

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    PUCT SB 6 rulemakings chart, row for Project 58479 (adopted March 26, 2026); SB 6 enrolled bill analysis, section on PURA 39.169 (120-day study, 60-day decision)

  • Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas

    Rulemaking to Establish Large Load Forecasting Criteria Under PURA 37.0561

    Rule 16 TAC 25.370: a large load counts in ERCOT's official planning forecast only if it has executed an interconnection agreement meeting the Project 58481 standards. No agreement and no posted security, no place in the forecast.

    Project No. 58480

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    PUCT SB 6 rulemakings chart, row for Project 58480 (adopted at the February 6, 2026 open meeting); ERCOT Large Load Update, 2026-04-09, Related PUCT Activities slide (rule 25.370, effective March 1, 2026)

  • Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas

    Rulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561

    ERCOT-wide rule 16 TAC 25.194 for loads of 75 MW or more at a single site. Before study, the customer signs an intermediate agreement, makes officer-level disclosures (site control, backup generation, duplicate requests elsewhere), pays a $100,000 study fee, and posts financial security of $50,000 per MW of requested peak demand, figured on gross demand. After transmission capacity is allocated, the customer must sign a Standard Large Load Interconnection Agreement within 60 days and post security at the greater of $50,000 per MW or its allocated upgrade costs. Withdrawing after allocation forfeits 20 percent of the security tied to the withdrawn capacity; withdrawing before the study begins returns it in full; missing the agreement deadline forfeits all of it. Security returns in 20 percent steps from energization as minimum billing demand milestones are met. The proposal's separate non-refundable $50,000 per MW interconnection fee was removed at adoption.

    Project No. 58481

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    PUCT SB 6 rulemakings chart, row for Project 58481 (scoping, drafts, adoption); White and Case alert (September 2026), PUCT Rule section and footnotes 1, 5, 6 (adoption terms); SiteBraid analysis citing Item 218 at page 28 (withdrawal forfeiture)

  • Utility proceedingPending before the commissionJun 20, 2025Public Utility Commission of Texas

    Large Load Demand Management Service

    The rule, still in scoping on the last Commission chart found, must implement PURA 39.170: each utility must be able to curtail transmission-voltage large loads interconnected after December 31, 2025 during firm load shed, with curtailment equipment installed before the customer interconnects; ERCOT may direct a large load with backup generation able to serve 50 percent or more of its demand to run that generation or curtail in an emergency; and ERCOT must competitively procure voluntary demand reductions from large loads over 75 MW, deployable on at least 24 hours notice.

    Project No. 58482

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    PUCT SB 6 rulemakings chart, row for Project 58482 (scoping; restyled title); SB 6 enrolled bill analysis, Sec. 39.170 summary

  • Air permitApprovedJan 22, 2025Texas Commission on Environmental Quality

    Texas Commission on Environmental Quality, Standard Permit Registration No. 177263 (Project No. 387309)

    Revision authorized (January 2025 revision); standard permit expires August 21, 2034

    Permitted run hours:
    8,760 hours per year per GE LM2500 turbine
    Generator capacity:
    360.5 MW
    Generator capacity:
    34.1 MW per GE LM2500 turbine (site-rated)
    Stated in the filing:
    10 natural gas simple-cycle turbines (5 Titan 350 and 5 GE LM2500)
    Generator capacity:
    38 MW per Titan 350 turbine (site-rated)
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Authorization letter and Technical Review, Electric Generating Units Air Quality Standard Permit, Abilene DC 1 LLC, Longhorn Data Center

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875477

    Texas charter of ABILENE DC 3, LLC (Secretary of State file number 0805875477)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 3, LLC'

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875491

    Texas charter of ABILENE DC 7, LLC (Secretary of State file number 0805875491)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 7, LLC'

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875479

    Texas charter of ABILENE DC 4, LLC (Secretary of State file number 0805875479)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 4, LLC'

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875484

    Texas charter of ABILENE DC 6, LLC (Secretary of State file number 0805875484)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 6, LLC'

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875505

    Texas charter of ABILENE DC 8, LLC (Secretary of State file number 0805875505)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 8, LLC'

  • Business registrationIssuedJan 22, 2025Texas Secretary of State

    Texas Secretary of State, 0805875503

    Texas charter of ABILENE DC 5, LLC (Secretary of State file number 0805875503)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 5, LLC'

2024

  • Business registrationIssuedJul 18, 2024Texas Secretary of State

    Texas Secretary of State, 0805628941

    Texas charter of LANCIUM ABILENE, LLC (Secretary of State file number 0805628941)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'LANCIUM ABILENE, LLC'

  • Business registrationIssuedJun 12, 2024Texas Secretary of State

    Texas Secretary of State, 0805587707

    Texas charter of ABILENE DC 1, LLC (Secretary of State file number 0805587707)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'ABILENE DC 1, LLC'

2022

  • Business registrationIssuedMar 21, 2022Texas Secretary of State

    Texas Secretary of State, 0804512315

    Texas charter of LANCIUM ABILENE II, LLC (Secretary of State file number 0804512315)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'LANCIUM ABILENE II, LLC'

  • Business registrationIssuedMar 21, 2022Texas Secretary of State

    Texas Secretary of State, 0804512311

    Texas charter of LANCIUM ABILENE REAL ESTATE, LLC (Secretary of State file number 0804512311)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'LANCIUM ABILENE REAL ESTATE, LLC'

2021

  • Tax agreementDec 21, 2021Taylor County

    Chapter 312 property tax abatement agreements and payment in lieu of taxes (Texas Tax Code)

    The county abates 80 percent of property tax for 10 years per agreement, with a second agreement for new investment reported as extending the structure to 20 years; the payment in lieu of taxes to the county is $508,437 per year for 20 years. Investment and job commitments as announced at approval ($2.4 billion over 20 years, 57 jobs).

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    County meeting record, items 3/4 (hearing) and 12 (resolution adoption); terms as reported by the Abilene Reporter-News, December 21, 2021

  • Tax agreementDec 21, 2021Abilene

    Performance agreement (water and sewer reimbursement)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Board packet, Economic Development Program Status tables, pp. 17 and 48-52

2018

  • Business registrationIssuedApr 23, 2018Texas Secretary of State

    Texas Secretary of State, 0802996561

    Texas charter of LANCIUM LLC (Secretary of State file number 0802996561)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Texas Comptroller Taxpayer Records (dataset 9cir-efmm), taxpayer_name = 'LANCIUM LLC'

No date in the record(rules in force and undated records)

  • Development ruleIn effectNo date in the recordAbilene

    Maximum permissible octave band decibel limits at the bounding property line

    At no point at the bounding property line of any use may the sound pressure level exceed the octave band limits in Table 4-3, which run from 86 decibels in the lowest band down to 53 decibels in the highest band, with a limit of 65 decibels on the A scale for daytime. Nighttime levels take a 7-decibel deduction, and the code exempts construction and maintenance noise between 7 a.m. and 9 p.m.

    Abilene Land Development Code Section 4.2.9.2, Table 4-3

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Land Development Code Section 4.2.9.2(a), Table 4-3 (Municode)

  • Development ruleIn effectNo date in the recordAbilene

    General prohibition on unreasonable noise (no decibel limit)

    Section 20-1 declares unlawful any unreasonable loud, disturbing, unnecessary noise that causes material distress, discomfort or injury to persons of ordinary sensibility in the immediate vicinity, and any noise whose character, intensity and duration substantially interferes with the comfort and enjoyment of private homes. It sets no decibel limit; the numeric limits are in the Land Development Code, Section 4.2.9.2.

    Abilene Code of Ordinances Section 20-1 (Chapter 20, Offenses)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Code of Ordinances Section 20-1(a)-(b) (Municode)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

Sources

  1. 1
    Technical Review, Standard Permit Registration No. 177263 (Project No. 387309), Longhorn Data Center
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Electric Generating Units Air Quality Standard Permit revision authorization letter, Registration No. 177263, Abilene DC 1 LLC (Longhorn Data Center)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Plain Language Summary for New Source Review, Initial Application for Air New Source Review Permit Numbers 182126, GHGPSDTX263 and PSDTX1688, Crusoe Energy Systems LLC (CN606257079), Longhorn Data Center (RN112029061)
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Notice of Receipt of Application and Intent to Obtain Air Permit (NORI), Permit 182126 / PSDTX1688 / GHGPSDTX263, Crusoe Energy Systems LLC, Longhorn Data Center Buildings 9 and 10
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Taxpayer Records (franchise tax, with Secretary of State file numbers and charter dates)
    Texas Comptroller of Public Accounts (data.texas.gov)
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    Notice of Application and Preliminary Decision for Air Quality Permits, Proposed Air Quality Permit Numbers 182126, PSDTX1688, and GHGPSDTX263, Crusoe Technologies LLC, Abilene, Taylor County
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Commissioners Court Minutes, September 9, 2025
    Taylor County
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    Taylor County commissioners approve tax abatement for Lancium, Abilene Reporter-News, December 21, 2021
    Abilene Reporter-News
    Tier 3 · Captured 2026-11-07 · Open the source
  9. 9
    Commissioners Court meeting record, December 21, 2021
    Taylor County
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    City Council Agenda, December 4, 2025
    City of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  11. 11
    Commissioners Court Minutes, December 16, 2025
    Taylor County
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    DCOA Board Meeting Packet, August 5, 2025
    Development Corporation of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    Second Tax Abatement Agreement (Phase 10), City of Abilene, Texas, Lancium LLC and Abilene DC 10, LLC
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  14. 14
    Resolution No. 171-2025, City of Abilene, approving Tax Abatement Agreements and Second Tax Abatement Agreements with Lancium, LLC and Abilene DC 1, 3, 4, 5, 6, 7 and 8, LLC (Phases 1-8)
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Second Tax Abatement Agreement (Phase 5), City of Abilene, Texas, Lancium LLC and Abilene DC 5, LLC
    City of Abilene
    Tier 1 · Captured 2026-11-09 · Open the source
  16. 16
    Abilene Ordinance 100-2025, 3rd Amendment to Planned Development District 181
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    Abilene Ordinance 56-2025, PDD-181 buffer exhibit amendment
    City of Abilene (Municode MuniDocs)
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Abilene Land Development Code, Section 4.2.9.2, Performance Standards Regulating Noise (Table 4-3)
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Abilene Code of Ordinances, Section 20-1, Noise control generally
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Abilene Land Development Code, Section 2.3.4.5, Planned Development (PD) District
    City of Abilene (Municode)
    Tier 1 · Captured 2026-11-08 · Open the source
  21. 21
    Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  22. 22
    Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
    Texas Secretary of State
    Tier 1 · Captured 2026-11-07 · Open the source
  23. 23
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-07 · Open the source
  24. 24
    Senate Bill 6 enrolled bill analysis
    Texas Senate Research Center
    Tier 1 · Captured 2026-11-07 · Open the source
  25. 25
    Large Load Update, presentation to the House State Affairs Committee
    ERCOT
    Tier 1 · Captured 2026-11-07 · Open the source
  26. 26
    PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
    White and Case LLP
    Tier 2 · Captured 2026-11-07 · Open the source
  27. 27
    PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
    SiteBraid
    Tier 3 · Captured 2026-11-07 · Open the source
  28. 28
    PUCT Interchange filing index, Project or Docket No. 59943
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  29. 29
    PUCT Interchange filing index, Project or Docket No. 58317
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  30. 30
    PUCT Interchange filing index, Project or Docket No. 59115
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  31. 31
    The Development Corporation of Abilene City of Abilene and Taylor County Announce Expanded Development within Lancium's Clean Campus through Crusoe's 998000 Square Foot Data Center Project
    Development Corporation of Abilene
    Tier 1 · Captured 2026-11-07 · Open the source
  32. 32
    Crusoe Expands AI Data Center Campus in Abilene to 1.2 Gigawatts
    Crusoe (via GlobeNewswire, on Lancium's site)
    Tier 4 · Captured 2026-11-07 · Open the source