Large Load Demand Management Service

Where it stands: Pending before the commission

Draft research, not yet verified. Open a source to check any detail.

What it is

The rule, still in scoping on the last Commission chart found, must implement PURA 39.170: each utility must be able to curtail transmission-voltage large loads interconnected after December 31, 2025 during firm load shed, with curtailment equipment installed before the customer interconnects; ERCOT may direct a large load with backup generation able to serve 50 percent or more of its demand to run that generation or curtail in an emergency; and ERCOT must competitively procure voluntary demand reductions from large loads over 75 MW, deployable on at least 24 hours notice.

The facts

Regulator
Public Utility Commission of Texas
Docket number
Project No. 58482
Type
Other
Utility
AEP Texas North Company
State
Texas
Filed
Jun 20, 2025
Large-load rules
Yes, for loads of 75 MW or more

Projects served by AEP Texas North Company

Related cases and proceedings

In the record

  1. Utility case, Jun 20, 2025. Utility case filed: Large Load Demand Management Service Public Utility Commission of Texas, Project No. 58482

Sources

  1. 1
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · PUCT SB 6 rulemakings chart, row for Project 58482 (scoping; restyled title); SB 6 enrolled bill analysis, Sec. 39.170 summary · Open the source
  2. 2
    Senate Bill 6 enrolled bill analysis
    Texas Senate Research Center
    Tier 1 · PUCT SB 6 rulemakings chart, row for Project 58482 (scoping; restyled title); SB 6 enrolled bill analysis, Sec. 39.170 summary · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Large Load Demand Management Service." Last activity 2025-06-20. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-58482