What it is

Rule 16 TAC 25.205: a net metering arrangement between an existing stand-alone generation resource and a new large load of 75 MW or more needs an ERCOT study and prior Commission approval. ERCOT has 120 days to study the arrangement after it receives the needed information; the Commission then has 60 days to approve, deny, or approve with conditions, including hold-harmless protection against stranded or underutilized transmission assets.

The facts

Regulator
Public Utility Commission of Texas
Docket number
Project No. 58479
Type
Other
Utility
AEP Texas North Company
State
Texas
Filed
Jun 20, 2025
Status date
Mar 26, 2026
Large-load rules
Yes, for loads of 75 MW or more

Projects served by AEP Texas North Company

Related cases and proceedings

In the record

  1. Utility case, Jun 20, 2025. Utility case filed: Rulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169 Public Utility Commission of Texas, Project No. 58479

Sources

  1. 1
    SB 6 Rulemakings Chart
    Public Utility Commission of Texas
    Tier 1 · PUCT SB 6 rulemakings chart, row for Project 58479 (adopted March 26, 2026); SB 6 enrolled bill analysis, section on PURA 39.169 (120-day study, 60-day decision) · Open the source
  2. 2
    Senate Bill 6 enrolled bill analysis
    Texas Senate Research Center
    Tier 1 · PUCT SB 6 rulemakings chart, row for Project 58479 (adopted March 26, 2026); SB 6 enrolled bill analysis, section on PURA 39.169 (120-day study, 60-day decision) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Rulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169." Last activity 2026-03-26. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-58479