Skip to content

Utility commission

Review of ERCOT's Interconnection Processes for Large Loads

Where it stands: Pending before the commission as of Aug 20, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

ERCOT system-wide review opened after Governor Abbott’s August 3, 2026 directive for a comprehensive verification and audit of data centers in the interconnection process. ERCOT paused the Batch Zero study and delayed final classification of all large loads, and paused approvals to energize data centers and crypto facilities of 75 MW or more until Batch Zero eligibility verification is complete. ERCOT requested three PGRR 145 good cause exceptions: conditional classification by August 31, 2026 instead of the August 7 deadline; inclusion of conditionally classified base loads in the August 1 and November 1, 2026 Quarterly Stability Assessments (6 loads, about 1,959 MW, expected in the August QSA; 17 loads, about 6,874 MW, potentially eligible for November); and a dynamic-data review with the 24-day cure period for late notices. The Batch Zero Eligibility Verification Report is due December 10, 2026 for the December 17 open meeting; loads that fail verification or do not respond are disqualified from Batch Zero.

The facts

Regulator
Public Utility Commission of Texas
Docket number
Project No. 59142
Type
Other
State
Texas
Status date
Aug 20, 2026
Large-load rules
Yes, for loads of 75 MW or more

Related cases and proceedings

Sources

  1. 1
    ERCOT Updates: Good Cause Exceptions for PGRR 145, Batch Zero Verification and Audit Process, and Community Impact Review Process (Project No. 59142, Item 52)
    Electric Reliability Council of Texas, Inc.
    Tier 1 · Filing Receipt (filed 2026-08-20, Control 59142, Item 52) and the attached ERCOT presentation: directive response slide (75 MW large load and 25 MW medium load definitions, energization pause), QSA scope slide (1,959 MW and 6,874 MW), and Batch Zero Eligibility Verification slide (December 10 report, December 17 meeting) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Review of ERCOT's Interconnection Processes for Large Loads." Last activity 2026-08-20. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-59142-ercot-review