Utility commission
Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region
Where it stands: Proposed as of Jul 24, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Proposal, not yet adopted. Transmission costs would move from four summer coincident peaks (4CP) to twelve monthly coincident peaks (12CP), measured on a 30-minute interval. New rule 16 TAC 25.252 would set the terms every transmission provider and investor-owned distribution utility tariff must contain for large load customers, including a minimum billing demand fixed for 20 years, billed from when service is made available whether or not the customer has energized or is fully using the capacity. Interconnection fees and forfeited security under 25.194 would offset the transmission revenue requirement.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- Project No. 58000
- Type
- Large load tariff
- Utility
- AEP Texas North Company
- State
- Texas
- Filed
- Jul 9, 2026
- Status date
- Jul 24, 2026
- Large-load rules
- Yes, for loads of 75 MW or more
Projects served by AEP Texas North Company
Related cases and proceedings
- Utility commission · Pending before the commissionJoint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionSB 6 Implementation
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
- Utility commission · Pending before the commissionReview of ERCOT's Interconnection Processes for Large Loads
- Utility commission · DecidedApplication of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · DecidedApplication of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · DecidedRulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169
- Utility commission · DecidedRulemaking to Establish Large Load Forecasting Criteria Under PURA 37.0561
In the record
- Utility case, Jul 9, 2026. Utility case filed: Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region Public Utility Commission of Texas, Project No. 58000
Sources
- 1Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
Public Utility Commission of TexasTier 1 · Proposal for Publication, Item 8, filed 2026-07-09, preamble (12CP, 25.252, minimum billing demand) and question 2 (minimum fixed for 20 years as proposed); Texas Register, July 24, 2026, Proposed Rules (TRD-202602812) · Open the source - 2Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
Texas Secretary of StateTier 1 · Proposal for Publication, Item 8, filed 2026-07-09, preamble (12CP, 25.252, minimum billing demand) and question 2 (minimum fixed for 20 years as proposed); Texas Register, July 24, 2026, Proposed Rules (TRD-202602812) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region." Last activity 2026-07-24. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-58000