Utility commission
Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
Where it stands: Decided as of Apr 23, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
The data center load (180 MW phase 1 plus 85 MW phase 2, assigned to Ensign Infrastructure LLC) sits behind the meter of the 265.5 MW GOODNIT1 wind facility at Oncor Midpoint Switch substation and nets against its output for settlement. On an ERCOT instruction during a transmission emergency the load must fully curtail within 30 minutes, without compensation, and the wind facility must make its capacity available to ERCOT. The load may not be offered into ERCOT or utility demand response, ancillary services, or the Emergency Response Service. The order was an early decision under PURA Section 39.169, the Senate Bill 6 co-location provision.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- 58881
- Type
- Other
- State
- Texas
- Filed
- Oct 24, 2025
- Status date
- Apr 23, 2026
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
- Utility commission · Pending before the commissionReview of ERCOT's Interconnection Processes for Large Loads
- Utility commission · ProposedRulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region
- Utility commission · DecidedApplication of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · DecidedRulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169
- Utility commission · DecidedRulemaking to Establish Large Load Forecasting Criteria Under PURA 37.0561
- Utility commission · DecidedApplication of El Paso Electric Company for an Economic Development Rate Rider for a New Data Center to be Located in El Paso, Texas
- Utility commission · Pending before the commissionEvaluation of Transmission Cost Recovery
In the record
- Utility case, Oct 24, 2025. Utility case filed: Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement Public Utility Commission of Texas, 58881
Sources
- 1Order, Docket No. 58881: Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
Public Utility Commission of TexasTier 1 · Order (22 pages), Background, Findings of Fact 51, and ordering paragraphs; signed April 23, 2026 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement." Last activity 2026-04-23. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-puct-58881-goodnight-net-metering