Utility commission
Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
Where it stands: Decided as of Apr 23, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Net metering arrangement under PURA Sec. 39.916 at a 265.5 MW point of interconnection: 180 MW of load available upon commercial operation and a further 85 MW within three years. The final order (April 23, 2026) approved the arrangement with conditions, which are binding on the applicants’ successors and assigns: the customer must fully curtail load within 30 minutes on ERCOT direction (automated where possible), may not participate in demand response programs or other ancillary services, the parties must report curtailments quarterly to ERCOT and Commission Staff for five years, and FGE must provide ERCOT ten days notice before maintenance or outages exceeding 5 MW.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- Docket No. 58881
- Type
- Other
- Utility
- Oncor Electric Delivery Company LLC
- State
- Texas
- Filed
- Oct 24, 2025
- Status date
- Apr 23, 2026
- Large-load rules
- Yes
Projects served by Oncor Electric Delivery Company LLC
- Compass Datacenters Red Oak Campus (Red Oak; 360 MW)
- Csquare Allen DFW2
- DataBank Plano campus (DFW3 and DFW8)
- Digital Realty DFW10 (Dallas)
- Digital Realty DFW12 (Carrollton)
- Digital Realty DFW16 (Richardson)
- Digital Realty DFW17 (Richardson)
- Digital Realty DFW18 (Richardson)
- Digital Realty DFW25 (Richardson)
- Digital Realty DFW28 (Richardson)
- Digital Realty DFW29 (Richardson)
- Digital Realty DFW35 (Richardson)
Related cases and proceedings
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
- Utility commission · Pending before the commissionReview of ERCOT's Interconnection Processes for Large Loads
- Utility commission · ProposedRulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region
- Utility commission · DecidedApplication of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · DecidedRulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169
- Utility commission · DecidedRulemaking to Establish Large Load Forecasting Criteria Under PURA 37.0561
- Utility commission · DecidedApplication of El Paso Electric Company for an Economic Development Rate Rider for a New Data Center to be Located in El Paso, Texas
- Utility commission · Pending before the commissionEvaluation of Transmission Cost Recovery
In the record
- Utility case, Oct 24, 2025. Utility case filed: Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement Public Utility Commission of Texas, Docket No. 58881
Sources
- 1PUCT Interchange filing index, Project or Docket No. 58881
Public Utility Commission of TexasTier 1 · Final order signed April 23, 2026, pp. 2, 6-9 (265.5 MW point of interconnection; 180 MW and 85 MW phases; 30 minute curtailment and reporting conditions); index of filings (joint application of October 24, 2025; rehearing motions filed May 18, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement." Last activity 2026-04-23. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-oncor-crusoe-net-metering-58881