Project File · Public records
Every public record we have for Lancium Clean Campus data centers (Crusoe)
Abilene, Taylor County, TexasUnder constructionFirst public 2021Filing entity: LanciumLast checked Nov 13, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 37 records · showing votes and minutes only ·
2025
Recorded voteDec 16, 2025Taylor County Commissioners Court
Adoption of the resolution approving the Taylor County tax abatement agreements for Lancium Clean Campus phases 9 and 10 and the electricity generation plant (Lancium LLC with Abilene DC 9, DC 10, and DC TPP)
4 yes, 1 no. Brad Birchum (Commissioner, Precinct 3): yes; Chuck Statler (Commissioner, Precinct 4): yes; Kyle Kendrick (Commissioner, Precinct 2): no; Phil Crowley (County Judge): yes; Randall D. Williams (Commissioner, Precinct 1): yes.
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
Minutes of December 16, 2025, item 7D, pp. 5-6: motion by Judge Crowley, seconded by Commissioner Birchum, carried 4-1 with Commissioner Kendrick voting no; all five members present (p. 1).
Recorded voteDec 16, 2025Taylor County Commissioners Court
Resolution approving Tax Abatement Agreement and Second Tax Abatement Agreement with Lancium LLC and Abilene DC 9, LLC (Phase 9), Abilene DC 10, LLC (Phase 10), and Abilene DC TPP, LLC (Electricity Generation Plant)
1 no. Kyle Kendrick (Commissioner, Precinct 2): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, item 7D: the motion was seconded by Commissioner Birchum and carried with 4-1 vote, Commissioner Kendrick voted No
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
Sources
- 1Technical Review, Standard Permit Registration No. 177263 (Project No. 387309), Longhorn Data Center
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 2Electric Generating Units Air Quality Standard Permit revision authorization letter, Registration No. 177263, Abilene DC 1 LLC (Longhorn Data Center)
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 3Plain Language Summary for New Source Review, Initial Application for Air New Source Review Permit Numbers 182126, GHGPSDTX263 and PSDTX1688, Crusoe Energy Systems LLC (CN606257079), Longhorn Data Center (RN112029061)
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 4Notice of Receipt of Application and Intent to Obtain Air Permit (NORI), Permit 182126 / PSDTX1688 / GHGPSDTX263, Crusoe Energy Systems LLC, Longhorn Data Center Buildings 9 and 10
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 5Taxpayer Records (franchise tax, with Secretary of State file numbers and charter dates)
Texas Comptroller of Public Accounts (data.texas.gov)Tier 1 · Captured 2026-11-08 · Open the source - 6Notice of Application and Preliminary Decision for Air Quality Permits, Proposed Air Quality Permit Numbers 182126, PSDTX1688, and GHGPSDTX263, Crusoe Technologies LLC, Abilene, Taylor County
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 7Commissioners Court Minutes, September 9, 2025
Taylor CountyTier 1 · Captured 2026-11-07 · Open the source - 8Taylor County commissioners approve tax abatement for Lancium, Abilene Reporter-News, December 21, 2021
Abilene Reporter-NewsTier 3 · Captured 2026-11-07 · Open the source - 9Commissioners Court meeting record, December 21, 2021
Taylor CountyTier 1 · Captured 2026-11-07 · Open the source - 10
- 11Commissioners Court Minutes, December 16, 2025
Taylor CountyTier 1 · Captured 2026-11-09 · Open the source - 12DCOA Board Meeting Packet, August 5, 2025
Development Corporation of AbileneTier 1 · Captured 2026-11-07 · Open the source - 13Second Tax Abatement Agreement (Phase 10), City of Abilene, Texas, Lancium LLC and Abilene DC 10, LLC
City of AbileneTier 1 · Captured 2026-11-09 · Open the source - 14Resolution No. 171-2025, City of Abilene, approving Tax Abatement Agreements and Second Tax Abatement Agreements with Lancium, LLC and Abilene DC 1, 3, 4, 5, 6, 7 and 8, LLC (Phases 1-8)
City of AbileneTier 1 · Captured 2026-11-09 · Open the source - 15Second Tax Abatement Agreement (Phase 5), City of Abilene, Texas, Lancium LLC and Abilene DC 5, LLC
City of AbileneTier 1 · Captured 2026-11-09 · Open the source - 16Abilene Ordinance 100-2025, 3rd Amendment to Planned Development District 181
City of Abilene (Municode MuniDocs)Tier 1 · Captured 2026-11-08 · Open the source - 17Abilene Ordinance 56-2025, PDD-181 buffer exhibit amendment
City of Abilene (Municode MuniDocs)Tier 1 · Captured 2026-11-08 · Open the source - 18Abilene Land Development Code, Section 4.2.9.2, Performance Standards Regulating Noise (Table 4-3)
City of Abilene (Municode)Tier 1 · Captured 2026-11-08 · Open the source - 19Abilene Code of Ordinances, Section 20-1, Noise control generally
City of Abilene (Municode)Tier 1 · Captured 2026-11-08 · Open the source - 20Abilene Land Development Code, Section 2.3.4.5, Planned Development (PD) District
City of Abilene (Municode)Tier 1 · Captured 2026-11-08 · Open the source - 21Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
Public Utility Commission of TexasTier 1 · Captured 2026-11-07 · Open the source - 22Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
Texas Secretary of StateTier 1 · Captured 2026-11-07 · Open the source - 23SB 6 Rulemakings Chart
Public Utility Commission of TexasTier 1 · Captured 2026-11-07 · Open the source - 24Senate Bill 6 enrolled bill analysis
Texas Senate Research CenterTier 1 · Captured 2026-11-07 · Open the source - 25Large Load Update, presentation to the House State Affairs Committee
ERCOTTier 1 · Captured 2026-11-07 · Open the source - 26PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
White and Case LLPTier 2 · Captured 2026-11-07 · Open the source - 27PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
SiteBraidTier 3 · Captured 2026-11-07 · Open the source - 28PUCT Interchange filing index, Project or Docket No. 59943
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 29PUCT Interchange filing index, Project or Docket No. 58317
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 30PUCT Interchange filing index, Project or Docket No. 59115
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 31The Development Corporation of Abilene City of Abilene and Taylor County Announce Expanded Development within Lancium's Clean Campus through Crusoe's 998000 Square Foot Data Center Project
Development Corporation of AbileneTier 1 · Captured 2026-11-07 · Open the source - 32Crusoe Expands AI Data Center Campus in Abilene to 1.2 Gigawatts
Crusoe (via GlobeNewswire, on Lancium's site)Tier 4 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page