Project File · Public records
Every public record we have for Galaxy Helios campus
Dickens County, TexasExpandingLast checked Nov 13, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
9 of 10 records · showing power and utility only ·
2026
Utility proceedingProposedJul 9, 2026Public Utility Commission of Texas
Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region
Proposal, not yet adopted. Transmission costs would move from four summer coincident peaks (4CP) to twelve monthly coincident peaks (12CP), measured on a 30-minute interval. New rule 16 TAC 25.252 would set the terms every transmission provider and investor-owned distribution utility tariff must contain for large load customers, including a minimum billing demand fixed for 20 years, billed from when service is made available whether or not the customer has energized or is fully using the capacity. Interconnection fees and forfeited security under 25.194 would offset the transmission revenue requirement.
Project No. 58000
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Proposal for Publication, Item 8, filed 2026-07-09, preamble (12CP, 25.252, minimum billing demand) and question 2 (minimum fixed for 20 years as proposed); Texas Register, July 24, 2026, Proposed Rules (TRD-202602812)
Utility proceedingPending before the commissionJul 1, 2026Public Utility Commission of Texas
Joint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement
Net metering arrangement under PURA Sec. 39.916 pairing the Willow Springs wind facility with the Haskell DC data center load; Electric Transmission Texas, LLC and AEP Texas Inc. filed notices to participate (July 30 and 31, 2026). The latest filing is an October 8, 2026 motion for extension of time; no terms are approved yet.
Docket No. 59943
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Index of filings: joint application of July 1, 2026; notices to participate of Electric Transmission Texas, LLC (July 30, 2026) and AEP Texas Inc. (July 31, 2026); extension motion of October 8, 2026
2025
Utility proceedingDecidedDec 12, 2025Public Utility Commission of Texas
Joint Application of West Texas Solar Project II LLC and Silver Basin Digital Infrastructure LLC for Approval of a Net Metering Arrangement
Net metering arrangement under PURA Sec. 39.916: the West Texas Solar facility’s capacity factor test exhibit was filed under seal, and the final order’s findings included a condition that the facility achieve the specified level of customer capacity satisfaction. The order carries no load threshold and no tariff terms.
Docket No. 59115
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Index of filings: joint application of December 12, 2025; Sealed Exhibit DML-2 (November 18, 2026) notice of filing; final order signed October 15, 2026
Utility proceedingPending before the commissionJun 30, 2025Public Utility Commission of Texas
SB 6 Implementation
Umbrella project coordinating the five SB 6 child projects already staged (Project Nos. 58479, 58480, 58481, 58482, 58484): ERCOT demand management (new and existing loads of 75 MW or more), net metering protocols under PURA Sec. 39.916 with Exhibit A the 2026 ERCOT Large Load Interconnection Process Handbook (September 2026 version), a large load interconnection cost responsibility rulemaking under PURA Sec. 39.168, transmission planning criteria for large loads under PURA Sec. 37.0561, and virtual power plant programs. Staff’s implementation roadmap was updated in September 2026.
Project No. 58317
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Interchange docket record: SB 6 Implementation Roadmap memorandum (updated September 2026 version filed September 22, 2026) and the Exhibit A cover memorandum (ERCOT Large Load Interconnection Process Handbook, September 2026)
Utility proceedingPending before the commissionJun 20, 2025Public Utility Commission of Texas
Evaluation of Transmission Cost Recovery
The Commission's evaluation of the four coincident peak (4CP) method of assigning transmission costs, which SB 6 required it to complete and act on by December 31, 2026. The question is whether charging on four summer peaks lets large, flexible loads avoid paying for the grid they use all year. The evaluation sets no terms itself; the rulemaking that carries the result is Project No. 58000.
Project No. 58484
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
PUCT SB 6 rulemakings chart, row for Project 58484 (evaluation period; staff questions issued 2025-08-05)
Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas
Rulemaking for Net Metering Arrangements Involving a Large Load Co-Located with an Existing Generation Resource Under PURA 39.169
Rule 16 TAC 25.205: a net metering arrangement between an existing stand-alone generation resource and a new large load of 75 MW or more needs an ERCOT study and prior Commission approval. ERCOT has 120 days to study the arrangement after it receives the needed information; the Commission then has 60 days to approve, deny, or approve with conditions, including hold-harmless protection against stranded or underutilized transmission assets.
Project No. 58479
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
PUCT SB 6 rulemakings chart, row for Project 58479 (adopted March 26, 2026); SB 6 enrolled bill analysis, section on PURA 39.169 (120-day study, 60-day decision)
Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas
Rulemaking to Establish Large Load Forecasting Criteria Under PURA 37.0561
Rule 16 TAC 25.370: a large load counts in ERCOT's official planning forecast only if it has executed an interconnection agreement meeting the Project 58481 standards. No agreement and no posted security, no place in the forecast.
Project No. 58480
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
PUCT SB 6 rulemakings chart, row for Project 58480 (adopted at the February 6, 2026 open meeting); ERCOT Large Load Update, 2026-04-09, Related PUCT Activities slide (rule 25.370, effective March 1, 2026)
Utility proceedingDecidedJun 20, 2025Public Utility Commission of Texas
Rulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
ERCOT-wide rule 16 TAC 25.194 for loads of 75 MW or more at a single site. Before study, the customer signs an intermediate agreement, makes officer-level disclosures (site control, backup generation, duplicate requests elsewhere), pays a $100,000 study fee, and posts financial security of $50,000 per MW of requested peak demand, figured on gross demand. After transmission capacity is allocated, the customer must sign a Standard Large Load Interconnection Agreement within 60 days and post security at the greater of $50,000 per MW or its allocated upgrade costs. Withdrawing after allocation forfeits 20 percent of the security tied to the withdrawn capacity; withdrawing before the study begins returns it in full; missing the agreement deadline forfeits all of it. Security returns in 20 percent steps from energization as minimum billing demand milestones are met. The proposal's separate non-refundable $50,000 per MW interconnection fee was removed at adoption.
Project No. 58481
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
PUCT SB 6 rulemakings chart, row for Project 58481 (scoping, drafts, adoption); White and Case alert (September 2026), PUCT Rule section and footnotes 1, 5, 6 (adoption terms); SiteBraid analysis citing Item 218 at page 28 (withdrawal forfeiture)
Utility proceedingPending before the commissionJun 20, 2025Public Utility Commission of Texas
Large Load Demand Management Service
The rule, still in scoping on the last Commission chart found, must implement PURA 39.170: each utility must be able to curtail transmission-voltage large loads interconnected after December 31, 2025 during firm load shed, with curtailment equipment installed before the customer interconnects; ERCOT may direct a large load with backup generation able to serve 50 percent or more of its demand to run that generation or curtail in an emergency; and ERCOT must competitively procure voluntary demand reductions from large loads over 75 MW, deployable on at least 24 hours notice.
Project No. 58482
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
PUCT SB 6 rulemakings chart, row for Project 58482 (scoping; restyled title); SB 6 enrolled bill analysis, Sec. 39.170 summary
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Chapter 312 Tax Abatement Agreements detail file (registry download), last updated 2026-10-10
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 2Proposal for Publication of Amendments to 25.192 and 25.193 and New 25.252, Project No. 58000, Item 8
Public Utility Commission of TexasTier 1 · Captured 2026-11-07 · Open the source - 3Texas Register, Proposed Rules, Title 16 (July 24, 2026 issue)
Texas Secretary of StateTier 1 · Captured 2026-11-07 · Open the source - 4SB 6 Rulemakings Chart
Public Utility Commission of TexasTier 1 · Captured 2026-11-07 · Open the source - 5Senate Bill 6 enrolled bill analysis
Texas Senate Research CenterTier 1 · Captured 2026-11-07 · Open the source - 6Large Load Update, presentation to the House State Affairs Committee
ERCOTTier 1 · Captured 2026-11-07 · Open the source - 7PUCT sets financial commitments for data center interconnection as governor pauses permit approvals
White and Case LLPTier 2 · Captured 2026-11-07 · Open the source - 8PUCT Adopts 16 TAC 25.194: Texas Large Load Financial Security Replaces the Interconnection Fee
SiteBraidTier 3 · Captured 2026-11-07 · Open the source - 9PUCT Interchange filing index, Project or Docket No. 59943
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 10PUCT Interchange filing index, Project or Docket No. 58317
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 11PUCT Interchange filing index, Project or Docket No. 59115
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 12Galaxy Digital Form 8-K: Helios Campus ERCOT Approval for Additional 830 MW
Galaxy Digital Inc. (SEC Form 8-K)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page