Project File
Google Midlothian data center
Midlothian,Ellis County,TexasExpandingFirst public 2019Filing entity: Sharka LLCLast checked Nov 9, 2026
GoogleDeveloper and operatorSharka LLCDeveloperJet Stream, LLCOther role
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Google Midlothian data center is an expanding data center project in Midlothian, Ellis County, Texas. Google is named as operator. It was first public in 2019. No site capacity figure is published for this project.
Google Midlothian data center is an expanding data center project in Midlothian, Ellis County, Texas. Google is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Midlothian, Ellis County, Texas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
No property tax record for this campus is in our records yet.
Not known yet - Tax breaks
No signed tax break agreement for this campus appears in the state registries we searched.
Not known yet - Money for schools and services
Google gave the Midlothian school district a $100,000 grant for STEM programs when it announced this campus.
Comes from the community - Electricity bill
Oncor Electric Delivery is the wires utility for this campus, but no campus electricity record is in our files yet.
Not known yet - Water
The City of Midlothian sells this campus its water under a contract the City Council approved in 2020.
Comes from the community - Jobs
Google promised hundreds of construction jobs at this campus in 2019, and no campus headcount has been published since.
Comes from the community - Next door: height, setbacks, noise
The campus sits in a planned district created in 2017 for heavy industrial use, with a list of banned uses.
Local rule - Your say
This campus was rezoned at a public hearing in 2017, and its water contract won a public council vote in 2020.
How to take part
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · FilingFiled with Texas Commission on Environmental Quality: air permit for Google Midlothian data centerPermit by Rule Registration 153622 (30 TAC 106.511 and related rules); CN605692540, RN110495884
- · FilingFiled with Texas Department of Licensing and Regulation (TABS) for Google Midlothian data centerTABS2026007415
- · FilingFiled with Texas Commission on Environmental Quality: air permit for Google Midlothian data centerFederal Operating Permit (Title V) O4262; minor revision Project 38479; RN110495884
- · FilingFiled with Texas Department of Licensing and Regulation (TABS) for Google Midlothian data centerTABS2025020576
- · FilingFiled with Texas Department of Licensing and Regulation (TABS) for Google Midlothian data centerTABS2024013301
- · DecisionCity of Midlothian: Item 2020-168 approved unanimously (6-0): the City Manager was authorized to execute a retail water supply contract with Sharka LLC for furnishing potable water to the data center at the RailPort Industrial Park for Google Midlothian data centerMinutes of the May 26, 2020 regular City Council meeting, Item 2020-168 (carried in the June 9, 2020 packet as Attachment 1)
- · FilingFiled with City of Midlothian for Google Midlothian data centerMinutes of the May 26, 2020 regular City Council meeting, Item 2020-168 (carried in the June 9, 2020 packet as Attachment 1)
- · FilingFiled with Texas Department of Licensing and Regulation (TABS) for Google Midlothian data centerTABS2020010011
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Texas SB 6: Sets grid connection and cost rules for large loads in Texas
The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.
“The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))
Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked
Bills and laws in Texas
- SB 6 · Signed into law · Jun 20, 2025Sets grid connection and cost rules for large loads in Texas
- SB 2222 · Died or failed · Mar 25, 2025Would exempt data center property and energy equipment from property tax
Who's involved
- Developer and operatorGoogle
- DeveloperSharka LLC
- Other roleJet Stream, LLC
Power and water
Water, as reported by the operator
Midlothian, TX facility as named in the location table of Google's 2025 Environmental Report (2024 data)
- 2024 · Consumption: 182.3 Mgal
- 2024 · Discharge: 38.7 Mgal
- 2024 · Withdrawal: 221 Mgal
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
Texas Department of Licensing and Regulation (TABS), TABS2020010011
- Floor area
- 64,000 sq ft (as filed with TDLR)
- Estimated cost
- $37 million estimated cost as filed with TDLR
Texas Department of Licensing and Regulation (TABS), TABS2019018578
- Floor area
- 3,113 sq ft (as filed with TDLR)
- Estimated cost
- $850,000 estimated cost as filed with TDLR
Texas Commission on Environmental Quality, Federal Operating Permit (Title V) O4262; minor revision Project 38479; RN110495884
- Stated in the filing
- Site equipment authorized: diesel-fired engine-driven emergency generators, a diesel-fired engine-driven emergency firewater pump, diesel storage tanks, mechanical draft cooling towers, and natural gas-fired space heaters; the site is a major source for NOx
Texas Department of Licensing and Regulation (TABS), TABS2019012848
- Floor area
- 288,000 sq ft (as filed with TDLR)
- Estimated cost
- $300 million estimated cost as filed with TDLR
Texas Department of Licensing and Regulation (TABS), TABS2026007415
- Estimated cost
- $491.7 million estimated cost as filed with TDLR
- Floor area
- 288,000 sq ft (as filed with TDLR)
Texas Department of Licensing and Regulation (TABS), TABS2019008945
- Estimated cost
- $300 million estimated cost as filed with TDLR
- Floor area
- 281,792 sq ft (as filed with TDLR)
Texas Department of Licensing and Regulation (TABS), TABS2025020576
- Estimated cost
- $1 million estimated cost as filed with TDLR
- Floor area
- 13,200 sq ft (as filed with TDLR)
Texas Department of Licensing and Regulation (TABS), TABS2024013301
- Estimated cost
- $350 million estimated cost as filed with TDLR
- Floor area
- 170,600 sq ft (as filed with TDLR)
Texas Commission on Environmental Quality, Permit by Rule Registration 153622 (30 TAC 106.511 and related rules); CN605692540, RN110495884
- Stated in the filing
- PBR Registration 153622 was originally authorized in October 2018; updates were approved in February 2019, September 2020, July 2022, December 2024, and October 2025; the March 26, 2026 update covers Emergency Generator Group 4 hourly emission rates from manufacturer data for engines being installed in that group
Texas Department of Licensing and Regulation (TABS), TABS2020008045
- Estimated cost
- $850,000 estimated cost as filed with TDLR
- Floor area
- 3,113 sq ft (as filed with TDLR)
City of Midlothian, Agenda Item 2017-300; Case Z32-2017-137; Planned Development District No. 106 (PD 106)
- Stated in the filing
- PD 106 applies the Heavy Industrial (HI) district regulations plus a prohibited-uses list (including residential uses, junk or salvage yards, and any use offensive because of odor, fumes, dust, smoke, noise or pollution); backup energy generators and cooling towers are expressly not prohibited
- Stated in the filing
- 375.68 acres
- Stated in the filing
- Both City water and sewer serve this site
Public records
18 records found so far. 4 kinds of record are still being collected.
- Land and zoning rules1
- Environmental permits2
- Power and utility2
- Tax breaks and payments2
- Votes and minutes11
Court cases and commission dockets
- Utility commission · Pending before the commission · Nov 5, 2026Joint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement
- Utility commission · Decided · Apr 23, 2026Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC, and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
Questions people ask
- Where is Google Midlothian data center?
- Google Midlothian data center is a data center project in Midlothian, Ellis County, Texas.
- Who operates Google Midlothian data center?
- Google is named as the operator of Google Midlothian data center.
- How big is Google Midlothian data center?
- The site covers 375.68 acres.
- What stage is Google Midlothian data center?
- Google Midlothian data center is expanding. It was first public in 2019.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1TDLR TABS project records for the Sharka Data Center, 3441 Railport Parkway, Midlothian, TX
Texas Department of Licensing and RegulationTier 1 · Captured 2026-11-09 · Open the source - 2City Council agenda packet, June 9, 2020, Attachment 1: minutes of the May 26, 2020 regular meeting
City of Midlothian, TexasTier 1 · Captured 2026-11-09 · Open the source - 3Statement of Basis, Federal Operating Permit O4262, Sharka LLC, Sharka Data Center (Project 38479, minor revision)
Texas Commission on Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 4PBR Registration 153622 update submittal, Sharka LLC, Sharka Data Center (CN605692540, RN110495884), March 26, 2026
Texas Commission on Environmental Quality (records portal)Tier 1 · Captured 2026-11-09 · Open the source - 5City Council agenda packet, August 8, 2017 (Item 2017-300, PD 106 rezoning, Case Z32-2017-137)
City of Midlothian, TexasTier 1 · Captured 2026-11-09 · Open the source - 6Local Development Agreement Database (SB 1340), Chapter 380/381 agreements dataset
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-17 · Open the source - 7Chapter 312 Tax Abatement Agreements detail file (registry download), last updated 2026-10-10
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 8PUCT Interchange filing index, Project or Docket No. 58881
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 9PUCT Interchange filing index, Project or Docket No. 59399
Public Utility Commission of TexasTier 1 · Captured 2026-11-08 · Open the source - 10Planning and Zoning Commission packet, August 15, 2017, carrying the July 18, 2017 P&Z minutes
City of Midlothian, TexasTier 1 · Captured 2026-11-09 · Open the source - 11Expanding in Texas with new office space and a data center (Midlothian groundbreaking, $600M)
Google (The Keyword blog)Tier 4 · Captured 2026-11-08 · Open the source - 12Texas - Google Data Center Locations (Midlothian and Red Oak, Ellis County)
GoogleTier 4 · Captured 2026-11-08 · Open the source - 13Google 2025 Environmental Report (2024 data), Water use by data center location table
GoogleTier 4 · Captured 2026-11-09 · Open the source - 14Biennial Report 2020, Central Registry of Reinvestment Zones and Tax Abatement Agreements (Chapters 311 and 312)
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 15Biennial Report 2022, Central Registry of Reinvestment Zones and Tax Abatement Agreements (Chapters 311 and 312)
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 16Chapter 313 agreement documents list (Texas Tax Code Ch. 313 / JETI predecessor program)
Texas Comptroller of Public AccountsTier 1 · Captured 2026-11-09 · Open the source - 17Governor Abbott, Google Announce $40 Billion Investment In Texas (press release, dateline Midlothian, Texas)
Office of the Texas GovernorTier 1 · Captured 2026-11-09 · Open the source - 18Form EIA-861 final 2025 detailed data files
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page