What it is
Net metering arrangement under PURA Sec. 39.916 pairing the Comanche Peak nuclear station with an Amazon Data Services data center load, inside ERCOT with Oncor as the interconnecting utility. Oncor’s October 2026 response to Commission Staff requests for information addressed evidence of SB 6 compliance; Order No. 11 (October 26, 2026) granted Oncor’s request for a decision on written submission. No terms are approved yet.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- Docket No. 59399
- Type
- Other
- Utility
- Oncor Electric Delivery Company LLC
- State
- Texas
- Filed
- Feb 19, 2026
- Status date
- Nov 5, 2026
- Large-load rules
- Yes
Projects served by Oncor Electric Delivery Company LLC
- Compass Datacenters Red Oak Campus (Red Oak; 360 MW)
- Csquare Allen DFW2
- DataBank Plano campus (DFW3 and DFW8)
- Digital Realty DFW10 (Dallas)
- Digital Realty DFW12 (Carrollton)
- Digital Realty DFW16 (Richardson)
- Digital Realty DFW17 (Richardson)
- Digital Realty DFW18 (Richardson)
- Digital Realty DFW25 (Richardson)
- Digital Realty DFW28 (Richardson)
- Digital Realty DFW29 (Richardson)
- Digital Realty DFW35 (Richardson)
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions
- Utility commission · Pending before the commissionApplication of El Paso Electric Company for Approval of a High Load Factor Large Power Service Tariff
- Utility commission · Pending before the commissionApplication of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for a 366 MW Natural Gas Generation Facility
- Utility commission · Pending before the commissionApplication of Southwestern Electric Power Company for Authority to Amend Tariffs for Retail Service to Include New Standard Form Contract for Electric Service, Large Load
- Utility commission · DecidedJoint Application of West Texas Solar Project II LLC and Silver Basin Digital Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionJoint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionSB 6 Implementation
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
In the record
- Utility case, Feb 19, 2026. Utility case filed: Joint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement Public Utility Commission of Texas, Docket No. 59399
Sources
- 1PUCT Interchange filing index, Project or Docket No. 59399
Public Utility Commission of TexasTier 1 · Index of filings: joint application of February 19, 2026; item 151 (Oncor response to Staff RFI Q 1-19, October 2026); item 167 (Order No. 11 of October 26, 2026); item 213 (latest filing, November 5, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Joint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement." Last activity 2026-11-05. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-oncor-comanche-peak-net-metering-59399