Utility commission
Application of El Paso Electric Company for Approval of a High Load Factor Large Power Service Tariff
Where it stands: Pending before the commission as of Nov 5, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Proposed Schedule No. 27, HLFLP (High Load Factor Large Power Service), would replace the approved Schedule No. 33A data center rider (see the Docket No. 56903 row). Applicability: non governmental customers with contracted peak demand of 75,000 kW or greater, average monthly load factor of 85 percent or more, served at 115 kV or higher, under an Electric Service Agreement with a minimum term of 20 years and a load ramp of no more than four years. Monthly billing demand is not less than 85 percent of contract demand; billing commences when the company commences providing service whether or not the customer has energized load. Financial assurance acceptable to the company is required, waived or reduced only with at least two of S&P A-, Moody’s A3, or Fitch A- ratings; the customer pays all facilities, metering, and dedicated equipment costs plus a termination fee if it cancels or materially reduces service; the company may require the customer to meet ERCOT’s Large Load Interconnection Study requirements.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- Docket No. 59611
- Type
- Large load tariff
- Utility
- El Paso Electric Co
- State
- Texas
- Filed
- Apr 7, 2026
- Status date
- Nov 5, 2026
- Large-load rules
- Yes, for loads of 75 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions
- Utility commission · Pending before the commissionJoint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionApplication of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for a 366 MW Natural Gas Generation Facility
- Utility commission · Pending before the commissionApplication of Southwestern Electric Power Company for Authority to Amend Tariffs for Retail Service to Include New Standard Form Contract for Electric Service, Large Load
- Utility commission · DecidedJoint Application of West Texas Solar Project II LLC and Silver Basin Digital Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionJoint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionSB 6 Implementation
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
In the record
- Utility case, Apr 7, 2026. Utility case filed: Application of El Paso Electric Company for Approval of a High Load Factor Large Power Service Tariff Public Utility Commission of Texas, Docket No. 59611
Sources
- 1PUCT Interchange filing index, Project or Docket No. 59611
Public Utility Commission of TexasTier 1 · Application and proposed tariff sheet JS-1 (Schedule No. 27 applicability: 75,000 kW, 85 percent load factor, 115 kV, 20 year ESA term, 85 percent billing demand floor, financial assurance and ratings waiver); docket index (filed April 7, 2026; latest filing November 5, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of El Paso Electric Company for Approval of a High Load Factor Large Power Service Tariff." Last activity 2026-11-05. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-el-paso-electric-hlflp-59611