Utility commission
Application of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions
Where it stands: Pending before the commission as of Nov 6, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Tariff provisions for large load additions of 75 MW or more (the SB 6 statutory size), covering new and incremental load including New Large Load Growth Facilities included in the Uncontested Stipulation in Docket No. 59586. Under the stipulation’s tariff terms: a minimum Electric Service Agreement term of 15 years for New Large Load Growth Customers; a minimum bill based on the customer’s contracted peak demand or availability agreement; a $120,000 non refundable application fee for studies; exit and termination fees at the conclusion of the initial term; and financial security in the form of a letter of credit, security deposit, surety bond, investment grade parent guarantee, or equivalent until the minimum initial term is fulfilled.
The facts
- Regulator
- Public Utility Commission of Texas
- Docket number
- Docket No. 60332
- Type
- Large load tariff
- Utility
- Southwestern Public Service Co
- State
- Texas
- Filed
- Sep 25, 2026
- Status date
- Nov 6, 2026
- Large-load rules
- Yes, for loads of 75 MW or more
Projects served by Southwestern Public Service Co
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of El Paso Electric Company for Approval of a High Load Factor Large Power Service Tariff
- Utility commission · Pending before the commissionJoint Application of Comanche Peak Power Company LLC and Amazon Data Services, Inc. for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionApplication of El Paso Electric Company to Amend Its Certificate of Convenience and Necessity for a 366 MW Natural Gas Generation Facility
- Utility commission · Pending before the commissionApplication of Southwestern Electric Power Company for Authority to Amend Tariffs for Retail Service to Include New Standard Form Contract for Electric Service, Large Load
- Utility commission · DecidedJoint Application of West Texas Solar Project II LLC and Silver Basin Digital Infrastructure LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionJoint Application of Willow Springs Wind Farm, LLC and Haskell DC Owner LLC for Approval of a Net Metering Arrangement
- Utility commission · Pending before the commissionSB 6 Implementation
- Utility commission · DecidedRulemaking to Implement Large Load Interconnection Standards Under PURA 37.0561
In the record
- Utility case, Sep 25, 2026. Utility case filed: Application of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions Public Utility Commission of Texas, Docket No. 60332
Sources
- 1PUCT Interchange filing index, Project or Docket No. 60332
Public Utility Commission of TexasTier 1 · Uncontested Stipulation (Exhibit A, September 25, 2026): 75 MW threshold and New Large Load Growth Facility definition; tariff provisions (15 year minimum ESA term, minimum bill, $120,000 application fee, exit fees, financial security); docket index (latest filing November 6, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions." Last activity 2026-11-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-southwestern-public-service-large-load-60332