Microsoft San Antonio data centers

San Antonio,Bexar County,TexasOperatingLast checked Nov 10, 2026

MicrosoftDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Still to confirm: Capacity
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Microsoft San Antonio data centers is an operating data center project in San Antonio, Bexar County, Texas. Microsoft is named as operator. No site capacity figure is published for this project.

Microsoft San Antonio data centers is an operating data center project in San Antonio, Bexar County, Texas. Microsoft is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in San Antonio, Bexar County, Texas. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

3Public records we have found
1Tax agreement on record
31Backup generators, emergency engines
245,000Floor area, sq ft

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Bexar County, Texas.See every project on the map

Timeline

  1. · FilingFiled with Texas Department of Licensing and Regulation for Microsoft San Antonio data centersTABS2024013318

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Texas SB 6: Sets grid connection and cost rules for large loads in Texas

    The reliability service covers large load customers in the ERCOT power region with a demand of at least 75 megawatts, and bars customers that curtail in response to wholesale prices or take part in another reliability or ancillary service; this project has no capacity figure on record, and its demand and its participation in another reliability or ancillary service are not on record.

    “The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.” (SECTION 4, Utilities Code Sec. 39.170(b))

    Rule checks: Project is in Texas. Still to check: size: unknown, who it covers: not checked

Bills and laws in Texas

Open Bill Watch

Who's involved

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Texas Commission on Environmental Quality, Permit No. O4781

    Backup generators
    31 emergency engines
    Backup generators
    27 emergency engines
    Backup generators
    31 emergency engines
  • Texas Department of Licensing and Regulation, TABS2024013318

    Stated in the filing
    $215 million
    Floor area
    245,000 sq ft

Public records

3 records found so far. 6 kinds of record are still being collected.

See every record

Questions people ask

Where is Microsoft San Antonio data centers?
Microsoft San Antonio data centers is a data center project in San Antonio, Bexar County, Texas.
Who operates Microsoft San Antonio data centers?
Microsoft is named as the operator of Microsoft San Antonio data centers.
What stage is Microsoft San Antonio data centers?
Microsoft San Antonio data centers is operating.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Statement of Basis, Federal Operating Permit O4781, Microsoft SAT15 SAT16 SAT17
    Texas Commission on Environmental Quality
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    TABS project record: SAT 16 (Microsoft), 3555 Westover Link, San Antonio
    Texas Department of Licensing and Regulation
    Tier 1 · Captured 2026-11-10 · Open the source
  3. 3
    Local Development Agreement Database (SB 1340), Chapter 380/381 agreements dataset
    Texas Comptroller of Public Accounts
    Tier 1 · Captured 2026-11-17 · Open the source
  4. 4
    Microsoft Datacenters in Texas (fact sheet)
    Microsoft
    Tier 4 · Captured 2026-11-08 · Open the source
  5. 5
    EIA Form 861, Utility Data file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page