State Card
Data centers in Arizona
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 52 data center projects in Arizona as of November 2026: 30 operating, 7 proposed and 4 approved, totaling about 11,160 MW announced where a figure is published.
Arizona has 52 tracked data centers. Their announced capacity totals about 11,160 MW where a figure is published. Of those, 30 operating, 7 proposed and 4 approved. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Arizona
- Aligned Data Centers Phoenix campus (Union Hills)
OperatingPhoenix120 MW announced
- Aligned Data Centers PHX 01/02/03 (Phoenix)
OperatingPhoenix
- Aligned Data Centers PHX-04 (Chandler)
OperatingChandler51 MW announced
- Aligned Data Centers PHX-05 (Phoenix)
OperatingPhoenix
- Aligned Data Centers PHX-06 (Chandler)
OperatingChandler
- Aligned Data Centers PHX-07 (Waddell)
Operating
- Aligned Data Centers PHX-13 (Glendale)
Under constructionGlendale72 MW announced
- Apple Mesa data center (Global Command Center)
OperatingMesa
- Beale Infrastructure Marana Data Center Campus (Luckett Road)
ApprovedMarana
- Centersquare PHX1 (Phoenix)
OperatingPhoenix
- Centersquare PHX3 (Phoenix)
OperatingMesa17 MW announced
- Compass Datacenters El Mirage Campus (El Mirage; 108 MW campus in development)
ProposedEl Mirage108 MW announced
- Compass Datacenters Goodyear campus
OperatingGoodyear350 MW announced
- Compass Datacenters Goodyear Campus (Goodyear; 212 MW campus in development)
ProposedGoodyear212 MW announced
- CyrusOne Chandler
OperatingChandler
- CyrusOne Chandler campus (PHX1-PHX8)
OperatingChandler
- Digital Realty PHX10 (Phoenix)
OperatingPhoenix
- Digital Realty PHX15 (Chandler)
OperatingChandler31 MW announced
- EdgeConneX Mesa campus
AnnouncedMesa100 MW announced
- EdgeConneX PHX01 (Tempe)
OperatingTempe
- EdgeCore Mesa campus
ExpandingMesa450 MW announced
- Flexential Phoenix - Deer Valley Data Center
OperatingPhoenix
- Google Mesa data center (Project Red Hawk)
OperatingMesa
- Grande Valley Industrial Data Center Campus
ApprovedCasa Grande
- H5 Data Centers Phoenix (Chandler)
OperatingChandler26 MW announced
- Iron Mountain Data Centers AZS-1 (Scottsdale)
OperatingScottsdale6 MW announced
- Iron Mountain Data Centers Iron Mountain Phoenix (Phoenix; four facilities listed)
OperatingPhoenix130 MW announced
- Iron Mountain Phoenix campus (AZP-1, AZP-2, AZP-3)
OperatingPhoenix41 MW announced
- Iron Mountain Scottsdale (AZS-1)
OperatingScottsdale
- Meta Mesa Data Center
OperatingMesa24,657 MWh used in 2024, reported
- Microsoft Citrus Road campus (Goodyear)
ExpandingGoodyear
- Microsoft El Mirage datacenter campus
ExpandingEl Mirage
- Microsoft PHX 10-11 (Goodyear)
ExpandingGoodyear
- Novva Data Centers Mesa campus
AnnouncedMesa300 MW announced
- NTT Mesa campus (Elliot Road)
OperatingMesa240 MW announced
- NTT Mesa PH10 campus (Pacific Proving)
ProposedMesa324 MW announced
- phoenixNAP Phoenix Data Center
OperatingPhoenix
- Prime Data Centers PHX01 (Avondale)
Under constructionAvondale240 MW announced
- Project Blue data center (Tucson)
Approved
- Project Eagle data center and Project Baccara power plant
ApprovedGlendale
- QTS Phoenix 2 campus
OperatingPhoenix280 MW announced
- QTS Phoenix 2 (Phoenix; listed as in development)
ProposedPhoenix
- QTS Phoenix 3 campus (Glendale)
ProposedGlendale750 MW announced
- QTS Phoenix 3 (Glendale; listed as in development)
ProposedGlendale
- QTS Phoenix 4 (Avondale; listed as in development)
ProposedAvondale
- STACK Infrastructure PHX01 (Avondale)
AnnouncedAvondale150 MW announced
- STACK Infrastructure PHX02 (Phoenix)
AnnouncedPhoenix250 MW announced
- Stream Data Centers Goodyear campus (Phoenix I-V)
OperatingGoodyear280 MW announced
- Stream Data Centers Phoenix
OperatingGoodyear280 MW announced
- Tombstone Resources Cochise Supercomputer Campus
In permitting6,000 MW announced
Who serves this place
- Not collected yet.
Counties and cities in Arizona
Counties
- Cochise County1 data center project tracked
- Maricopa County48 data center projects tracked
- Pima County2 data center projects tracked
- Pinal County1 data center project tracked
Cities and towns
- Phoenix12 data center projects tracked
- Mesa9 data center projects tracked
- Goodyear8 data center projects tracked
- Chandler6 data center projects tracked
- Glendale4 data center projects tracked
- Avondale3 data center projects tracked
- El Mirage2 data center projects tracked
- Scottsdale2 data center projects tracked
- Casa Grande1 data center project tracked
- Marana1 data center project tracked
- Tempe1 data center project tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Google Mesa data center (Project Red Hawk):This campus pays a lease excise tax to Mesa instead of regular property tax on the land and buildings it leases from the city.
Comes to the communityMicrosoft PHX 10-11 (Goodyear):The median Maricopa County homeowner paid $237.10 in county property tax in fiscal 2026; the Goodyear campuses' own bills are not published.
Comes to the communityMeta Mesa Data Center:Mesa 2021 development agreement with the campus contains no property tax abatement.
Goes both waysMicrosoft El Mirage datacenter campus:Microsoft's Phoenix-area datacenters paid $5 million in local property tax in 2023; this campus's own bill is not published.
Comes to the community
Tax breaks
Meta Mesa Data Center:Two city agreements govern this campus, a development agreement and a water agreement; neither cuts its taxes.
Goes both waysGoogle Mesa data center (Project Red Hawk):Mesa gave this campus a 25-year GPLET lease in 2019, with excise tax at a 150 percent premium and no full abatement.
Goes both waysMicrosoft El Mirage datacenter campus:No incentive agreement naming this campus is published; Arizona's data center tax program does not publish its certificate holders.
Not known yetMicrosoft PHX 10-11 (Goodyear):No tax abatement or GPLET naming the Goodyear campuses is published; the city's agreements with Microsoft cover infrastructure, not taxes.
Not known yet
Money for schools and services
Microsoft El Mirage datacenter campus:Microsoft reports $2.4 million in Phoenix-area community investment from fiscal 2019 to 2023, including a West Valley Datacenter Academy.
Comes to the communityMeta Mesa Data Center:The water deal moved 5,500 acre-feet of stored water credits to the city when it was signed.
Comes from the communityGoogle Mesa data center (Project Red Hawk):Google has announced $250,000 in Mesa-area community funding: $150,000 for watershed restoration and $100,000 for the Mesa College Promise.
Comes from the communityMicrosoft PHX 10-11 (Goodyear):At the airport-area campus, Microsoft shares the cost of city water facilities, including a $5 million replacement-facilities contract under its 2024 amendment.
Comes to the community
Electricity bill
Google Mesa data center (Project Red Hawk):Salt River Project serves this campus; Google's supply agreement with SRP supports over 430 megawatts of new carbon-free capacity in Arizona.
Not known yetMicrosoft El Mirage datacenter campus:Arizona Public Service is the electric utility for this campus, named as a project partner at its 2019 announcement.
Not known yetMeta Mesa Data Center:The average Salt River Project home paid $159.71 a month in 2025, up from $133.17 in 2016, not adjusted for inflation.
Not known yetMicrosoft PHX 10-11 (Goodyear):Arizona Public Service serves the Goodyear campuses; a city record places an APS substation at the Citrus Road campus.
Not known yet
Water
Microsoft El Mirage datacenter campus:EPCOR provides water for this campus; city minutes show Microsoft applying to EPCOR for the newest building's added demand.
Not known yetMeta Mesa Data Center:The campus water allowance rises to 1,400 acre-feet a year at full buildout under its city water agreement.
Comes from the communityGoogle Mesa data center (Project Red Hawk):Google reports its Mesa campus withdrew 19.4 million gallons of water in 2025, its first reported year.
Comes from the communityMicrosoft PHX 10-11 (Goodyear):Goodyear's city utility provides water and wastewater for the airport-area campus under a 2019 infrastructure agreement amended six times.
Not known yet
Jobs
Meta Mesa Data Center:Job counts for this campus are not in our records yet.
Not known yetMicrosoft El Mirage datacenter campus:Microsoft counted 201 datacenter jobs across its Phoenix-area campuses in 2023; the El Mirage share is not published separately.
Not known yetGoogle Mesa data center (Project Red Hawk):No record we found states how many people work at this campus; its city agreement sets a pay floor, not a headcount.
Not known yetMicrosoft PHX 10-11 (Goodyear):Arizona's 2019 announcement projected more than 100 permanent and 1,000 construction jobs across all three campuses; no Goodyear-only count is published.
Not known yet
Next door: height, setbacks, noise
Microsoft El Mirage datacenter campus:The newest building is capped at 31 feet in the city's approval; the site sits in Luke Air Force Base's noise contour zone.
Not known yetGoogle Mesa data center (Project Red Hawk):This campus was approved in 2019 under its own employment district, six years before Mesa wrote general data center standards.
Not known yetMeta Mesa Data Center:Mesa data center standards exist in the city code; their numbers are not in our records yet.
Not known yetMicrosoft PHX 10-11 (Goodyear):The airport-area campus occupies 279 acres rezoned for it in 2018 inside the Airport Commercenter district, beside Phoenix Goodyear Airport.
Not known yet
Your say
Microsoft El Mirage datacenter campus:El Mirage's council approved the fifth building 7 to 0 on December 3, 2024, after a 4 to 0 planning commission recommendation.
Not known yetMeta Mesa Data Center:The City Council approved the campus agreements 6 to 1 in a public vote on May 17, 2021.
How to take partGoogle Mesa data center (Project Red Hawk):Mesa's City Council approved this campus's development agreement and GPLET lease on July 1, 2019, by Resolution 11372.
How to take partMicrosoft PHX 10-11 (Goodyear):Goodyear's council approved Microsoft agreement amendments unanimously in 2023 and 2025, with named votes recorded for both decisions.
Not known yet
Tax breaks and payments
2021 · Meta Mesa Data Center
Development Agreement and Sustainable Water Service Agreement (no tax terms)
No tax schedule of any kind. The water agreement allows 550 acre-feet per year for Phase 1, rising to 1,100 (Phase 2) and 1,400 (Phase 3), and the company assigns 5,500 acre-feet of long-term storage credits to the city.
All tax records for Meta Mesa Data CenterTransaction privilege and use tax exemption (A.R.S. Section 41-1519, Arizona Commerce Authority Computer Data Center Program)
Tax relief is the deduction of the gross proceeds of sale or gross income from the sale, use, installation, assembly, repair or maintenance of computer data center equipment under A.R.S. sections 42-5061, 42-5075, 42-5159 and 42-6004, in practice an exemption from transaction privilege tax and use tax at the state, county and local levels on qualifying equipment purchases for use at a certified computer data center. Computer data center equipment includes server and networking equipment, enabling software, power transformation, generation and distribution equipment, cooling and water conservation systems, monitoring and security systems, and modular data centers. Relief runs for the qualification period: from the effective date of certification to the end of the tenth full calendar year after that year, or the twentieth full calendar year for a sustainable redevelopment project. The same relief extends to qualified colocation tenants, whose own qualification period cannot run past the owner or operator's.
2019 · Google Mesa data center (Project Red Hawk)
Government Property Lease Excise Tax (GPLET) lease (A.R.S. Section 42-6201 et seq.)
Under the lease form approved with the Development Agreement (Resolution No. 11372), Stone Applications LLC conveys land and improvements to the City of Mesa and leases them back for a Rental Period of 25 years from the first building's certificate of occupancy, at a net rent of $10,000 per year, which the lease states covers the city's administrative costs rather than fair market value. Conveyed property is government property, so the company pays the government property lease excise tax under A.R.S. Section 42-6201 et seq. instead of ad valorem real property tax on the conveyed property. Because the site is outside a Central Business District and a Redevelopment Area, the excise tax is charged at a 150 percent premium over the published excise tax rates, and the site is not eligible for the 8-year full abatement of excise taxes; the council report states this expressly. City staff projected about $32,967,000 in excise taxes over the 25-year term, against an estimated $48,916,134 in real property taxes without the GPLET; the roughly $15.9 million difference is arithmetic on those two city projections, not a figure the city stated.
All tax records for Google Mesa data center (Project Red Hawk)
Local rules for data centers
In effect · Zoning · Adopted Dec 10, 2025
Modernized Maricopa County Zoning Ordinance, data center provisions
The modernized county zoning ordinance defines data centers and addresses them as an emerging technology use. Reporting on the adopted ordinance states that data centers are allowed in the IND-2 and IND-3 industrial districts, and land not zoned for the use must go through the county rezoning process. A county staff report for a February 2026 hearing states that data centers are a permitted use in the IND-2 district, while noting the ordinance does not specifically contemplate the use, which is why that project sought an overlay clarification.
In the news
Data center regulation could be first test of Arizona’s new Democratic trifecta
Arizona Capitol Times
Think you don’t use data centers? Think again.
Arizona Capitol Times
Arizona’s longest-tenured utility commissioner on large loads, affordability and Western markets
Utility Dive
Recent cases and dockets in Arizona
- Utility commission · ProposedAPS and TSMC Arizona 25-Year Direct Pricing Contract
- Utility commission · Pending before the commissionApplication of Tucson Electric Power Company for the Establishment of Just and Reasonable Rates and Charges Designed to Realize a Reasonable Rate of Return on the Fair Value of the Properties of Tucson Electric Power Company
- Utility commission · Pending before the commissionIn the Matter of the Commission's Inquiry and Review of the Existing Rate Classifications and Other Potential Issues Relating to Data Centers
- Utility commission · Pending before the commissionApplication of Arizona Public Service Company for approval of new rates, charges, and schedules
- Utility commission · DecidedTemporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
- Utility commission · In effectE-67, Standard Price Plan for Large Load Substation Large General Service
Bills and laws in Arizona
- HB 4168 · In effect · Jul 1, 2026Pauses new data center tax relief applications for three years
- HB 2756 · Signed into law · Jun 4, 2026Lets regulators set special billing rules for very large customers
- HB 2452 · Died or failed · Feb 26, 2026Requires county comprehensive plans to designate land for data centers
- HB 4009 · Died or failed · Feb 26, 2026Requires mapping of data centers on state lands
- SB 1799 · Died or failed · Feb 9, 2026Moves the cutoff for new data center tax certifications to the end of 2026
- HB 2949 · Died or failed · Feb 5, 2026Requires large data centers to pay their full energy costs
- SB 1463 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
- SB 1467 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
- SB 1380 · Died or failed · Jan 27, 2026Requires large load customers to pay their full energy costs
- HB 2820 · Died or failed · Jan 26, 2026Repeals data center tax relief and adds siting requirements
- HB 2738 · Died or failed · Jan 22, 2026Requires cost responsibility agreements before data center tax relief
- HB 2467 · Died or failed · Jan 22, 2026Repeals data center tax relief and adds siting requirements
- HB 2702 · Died or failed · Jan 22, 2026Directs data center transaction privilege tax revenue to solar programs
- HB 2631 · Died or failed · Jan 22, 2026Repeals the state computer data center tax relief statute
- HB 2119 · Died or failed · Jan 22, 2026Moves the data center tax relief application deadline up to 2026
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for Arizona
The lawmakers and local officials whose recorded jurisdiction is Arizona, with the bills and votes we have on record for each.
- Aaron MárquezState Representative · 5
- Alexander KolodinState Representative · 3
- Alma HernandezState Representative · 20
- Analise OrtizState Senator · 24
- Anna AbeytiaState Representative · 24
- Betty J VillegasState Representative · 20
- Beverly PingerelliState Representative · 28
- Brian FernandezState Senator · 23
- Brian GarciaState Representative · 8
- Carine WernerState Senator · 4
- Catherine MirandaState Senator · 11
- Cesar AguilarState Representative · 26
- Chris LopezState Representative · 16
- Christopher MathisState Representative · 18
- Cody ReimState Representative · 3
- Consuelo HernandezState Representative · 21
- David C. FarnsworthState Senator · 10
- David GowanState Senator · 19
- David LivingstonState Representative · 28
- David Marshall, Sr.State Representative · 7
- Denise "Mitzi" EpsteinState Senator · 12
- Elda Luna-NájeraState Representative · 22
- Eva DiazState Senator · 22
- Flavio BravoState Senator · 26
- Frank CarrollState Senator · 28
- Gail GriffinState Representative · 19
- Hildy AngiusState Senator · 30
- Jake HoffmanState Senator · 15
- James TaylorState Representative · 29
- Janae ShampState Senator · 29
- Janeen ConnollyState Representative · 8
- J.D. MesnardState Senator · 13
- Jeff WeningerState Representative · 13
- John GilletteState Representative · 30
- John KavanaghState Senator · 3
- Julie WilloughbyState Representative · 13
- Junelle CaveroState Representative · 11
- Justin OlsonState Representative · 10
- Justin WilmethState Representative · 2
- Katie HobbsGovernor
- Kevin PayneState Senator · 27
- Kevin VolkState Representative · 17
- Khyl PowellState Representative · 14
- Kiana SearsState Senator · 9
- Lauren KubyState Senator · 8
- Laurin HendrixState Representative · 14
- Lela AlstonState Senator · 5
- Leo BiasiucciState Representative · 30
- Lisa FinkState Representative · 27
- Lorena AustinState Representative · 9
Questions people ask
- How many data centers are in Arizona?
- Data Center Fact Check tracks 52 data center projects in Arizona as of November 2026. Of those, 30 operating, 7 proposed and 4 approved.
- What is the biggest data center in Arizona?
- By announced capacity, the biggest data center in Arizona is Tombstone Resources Cochise Supercomputer Campus, announced at 6,000 MW. It is in permitting.
- How much power do data centers in Arizona use?
- The 52 projects tracked in Arizona have announced about 11,160 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
City of Mesa, Office of Economic DevelopmentTier 1 · Open the source - 2Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
City of MesaTier 1 · Open the source - 3
- 4
- 5Development Agreement, City of Mesa, Arizona and Redale LLC (2021)
City of Mesa (Legistar)Tier 1 · Open the source - 6Resolution No. 11680 (Development Agreement and Sustainable Water Service Agreement with Redale LLC)
City of MesaTier 1 · Open the source - 7Economic contributions of Microsoft's datacenters in Phoenix, Arizona
Microsoft LocalTier 4 · Open the source - 8Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
City of MesaTier 1 · Open the source - 9Computer Data Center Program Rules and Guidelines (effective September 29, 2021)
Arizona Commerce AuthorityTier 1 · Open the source - 10Development Application Staff Report, Case SPA24-09-01, Microsoft PHX83
City of El Mirage Development ServicesTier 1 · Open the source - 11Resolution No. 2024-2417 approving the Fifth Amendment to Infrastructure Development Agreement for Project 10-11, with the Fifth Amendment as Exhibit 1
City of GoodyearTier 1 · Open the source - 12
- 13Sustainable Water Service Agreement between the City of Mesa, Arizona and Redale LLC (2021)
City of Mesa (Legistar)Tier 1 · Open the source - 14Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
Google, published by the Arizona Commerce AuthorityTier 1 · Open the source - 15How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
GoogleTier 4 · Open the source - 16EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Open the source - 17Microsoft to Build World-Class Sustainable Datacenters and Invest in Solar Power in Arizona (2019-07-30)
Arizona Commerce AuthorityTier 1 · Open the source - 18EIA Form 861 2016, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Open the source - 19Decision No. 78669, Certificate of Environmental Compatibility for Project Huckleberry (Docket No. L-00000B-22-0113-00204)
Arizona Corporation CommissionTier 1 · Open the source - 20Agenda item, Southwest Next rezone request (City of Goodyear AgendaQuick)
City of GoodyearTier 1 · Open the source - 21Planning and Zoning Commission minutes, November 12, 2024 (in April 8, 2025 agenda packet)
City of El MirageTier 1 · Open the source - 22Microsoft's newest sustainable datacenter region coming to Arizona in 2021 / West US 3 launch coverage (2020-2021)
Microsoft Azure BlogTier 4 · Open the source - 23
- 24Google 2025 Environmental Report (2024 data), Water use by data center location table
GoogleTier 4 · Open the source - 25City Council Regular Meeting minutes, March 6, 2023 (as published in the March 20, 2023 agenda packet)
City of GoodyearTier 1 · Open the source - 26Expanding cloud services: Microsoft launches its sustainable datacenter region in Arizona
Microsoft Azure BlogTier 4 · Open the source - 27Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
City of Mesa (Legistar)Tier 1 · Open the source - 28Development Community Newsletter, September 2025 (data center ordinance summary)
City of Mesa, ArizonaTier 1 · Open the source - 29Agenda item, rezone of a portion of Lots 16 and 17, Airport Commercenter (City of Goodyear AgendaQuick)
City of GoodyearTier 1 · Open the source - 30Regular Meeting of the Common Council, Minutes (Draft), December 3, 2024
City of El MirageTier 1 · Open the source - 31Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
City of MesaTier 1 · Open the source - 32City Council Regular Meeting draft minutes, September 22, 2025 (as published in the October 27, 2025 agenda packet)
City of GoodyearTier 1 · Open the source - 33Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
Maricopa County, ArizonaTier 1 · Open the source - 3441-1519. Computer data center tax relief; definitions
Arizona State LegislatureTier 1 · Open the source - 35HB 4168 (57th Legislature, 2nd Regular Session), House Engrossed version: taxation; omnibus; 2026-2027
Arizona State LegislatureTier 1 · Open the source - 36Session Laws, 57th Legislature, 2nd Regular Session
Arizona State LegislatureTier 1 · Open the source - 37Computer Data Center Program, Program Rules and Guidelines (effective September 29, 2021)
Arizona Commerce AuthorityTier 1 · Open the source - 38Computer Data Center Program (established under A.R.S. section 41-1519), program summary
Arizona Commerce AuthorityTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Arizona." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-az
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page