Data centers in Mesa, Arizona
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 9 data center projects in Mesa, Arizona as of November 2026: 5 operating, 2 announced and 1 proposed, totaling about 1,431 MW announced where a figure is published.
Mesa has 9 tracked data centers. Their announced capacity totals about 1,431 MW where a figure is published. Of those, 5 operating, 2 announced and 1 proposed. Electricity here comes from Arizona Public Service Company. Every figure comes from the public record linked on this page.
Data center projects in Mesa
- Apple Mesa data center (Global Command Center)
OperatingMesa
- Centersquare PHX3 (Phoenix)
OperatingMesa17 MW announced
- EdgeConneX Mesa campus
AnnouncedMesa100 MW announced
- EdgeCore Mesa campus
ExpandingMesa450 MW announced
- Google Mesa data center (Project Red Hawk)
OperatingMesa
- Meta Mesa Data Center
OperatingMesa24,657 MWh used in 2024, reported
- Novva Data Centers Mesa campus
AnnouncedMesa300 MW announced
- NTT Mesa campus (Elliot Road)
OperatingMesa240 MW announced
- NTT Mesa PH10 campus (Pacific Proving)
ProposedMesa324 MW announced
Who serves this place
- ElectricityArizona Public Service Company
- ElectricityCity of Mesa Energy Resources
- ElectricitySalt River Project
- Grid regionSalt River Project balancing area
- Grid regionWestern Area Power Administration, Lower Colorado balancing area (WALC)
More places in Maricopa County
Mesa is part of Maricopa County.
Nearby places
- Phoenix12 data center projects tracked
- Goodyear8 data center projects tracked
- Chandler6 data center projects tracked
- Glendale4 data center projects tracked
- Avondale3 data center projects tracked
- El Mirage2 data center projects tracked
- Scottsdale2 data center projects tracked
- Tempe1 data center project tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Google Mesa data center (Project Red Hawk):This campus pays a lease excise tax to Mesa instead of regular property tax on the land and buildings it leases from the city.
Comes to the communityMeta Mesa Data Center:Mesa 2021 development agreement with the campus contains no property tax abatement.
Goes both ways
Tax breaks
Meta Mesa Data Center:Two city agreements govern this campus, a development agreement and a water agreement; neither cuts its taxes.
Goes both waysGoogle Mesa data center (Project Red Hawk):Mesa gave this campus a 25-year GPLET lease in 2019, with excise tax at a 150 percent premium and no full abatement.
Goes both ways
Money for schools and services
Meta Mesa Data Center:The water deal moved 5,500 acre-feet of stored water credits to the city when it was signed.
Comes from the communityGoogle Mesa data center (Project Red Hawk):Google has announced $250,000 in Mesa-area community funding: $150,000 for watershed restoration and $100,000 for the Mesa College Promise.
Comes from the community
Electricity bill
Google Mesa data center (Project Red Hawk):Salt River Project serves this campus; Google's supply agreement with SRP supports over 430 megawatts of new carbon-free capacity in Arizona.
Not known yetMeta Mesa Data Center:The average Salt River Project home paid $159.71 a month in 2025, up from $133.17 in 2016, not adjusted for inflation.
Not known yet
Water
Meta Mesa Data Center:The campus water allowance rises to 1,400 acre-feet a year at full buildout under its city water agreement.
Comes from the communityGoogle Mesa data center (Project Red Hawk):Google reports its Mesa campus withdrew 19.4 million gallons of water in 2025, its first reported year.
Comes from the community
Jobs
Meta Mesa Data Center:Job counts for this campus are not in our records yet.
Not known yetGoogle Mesa data center (Project Red Hawk):No record we found states how many people work at this campus; its city agreement sets a pay floor, not a headcount.
Not known yet
Next door: height, setbacks, noise
Google Mesa data center (Project Red Hawk):This campus was approved in 2019 under its own employment district, six years before Mesa wrote general data center standards.
Not known yetMeta Mesa Data Center:Mesa data center standards exist in the city code; their numbers are not in our records yet.
Not known yet
Your say
Meta Mesa Data Center:The City Council approved the campus agreements 6 to 1 in a public vote on May 17, 2021.
How to take partGoogle Mesa data center (Project Red Hawk):Mesa's City Council approved this campus's development agreement and GPLET lease on July 1, 2019, by Resolution 11372.
How to take part
Tax breaks and payments
2021 · Meta Mesa Data Center
Development Agreement and Sustainable Water Service Agreement (no tax terms)
No tax schedule of any kind. The water agreement allows 550 acre-feet per year for Phase 1, rising to 1,100 (Phase 2) and 1,400 (Phase 3), and the company assigns 5,500 acre-feet of long-term storage credits to the city.
All tax records for Meta Mesa Data Center2019 · Google Mesa data center (Project Red Hawk)
Government Property Lease Excise Tax (GPLET) lease (A.R.S. Section 42-6201 et seq.)
Under the lease form approved with the Development Agreement (Resolution No. 11372), Stone Applications LLC conveys land and improvements to the City of Mesa and leases them back for a Rental Period of 25 years from the first building's certificate of occupancy, at a net rent of $10,000 per year, which the lease states covers the city's administrative costs rather than fair market value. Conveyed property is government property, so the company pays the government property lease excise tax under A.R.S. Section 42-6201 et seq. instead of ad valorem real property tax on the conveyed property. Because the site is outside a Central Business District and a Redevelopment Area, the excise tax is charged at a 150 percent premium over the published excise tax rates, and the site is not eligible for the 8-year full abatement of excise taxes; the council report states this expressly. City staff projected about $32,967,000 in excise taxes over the 25-year term, against an estimated $48,916,134 in real property taxes without the GPLET; the roughly $15.9 million difference is arithmetic on those two city projections, not a figure the city stated.
All tax records for Google Mesa data center (Project Red Hawk)
Local rules for data centers
In effect · Setback · Adopted Jul 8, 2025
Separation from residential districts, height cap, screening, parking, and sound studies for data centers
Planning staff described a minimum separation of 400 feet from residential zoning districts or sensitive uses, measured from the data center property to the nearest residential property line, a maximum building height of 60 feet unless an exception is approved through a PAD, screening for mechanical equipment and substations, and parking at 1 space per 5,000 square feet for the first 200,000 square feet and 1 space per 10,000 square feet after that. Staff also described an initial sound study at the nearest residential property line, a post-occupancy sound study within 30 days of the certificate of occupancy, and annual sound studies for the first five years.
In effect · Generator · Adopted Jul 8, 2025
Backup generator operation and testing notice, Data Centers
An operator using backup generators must announce any routine operation, including testing, on its website and notify the City of Mesa Public Information Office at least 24 hours in advance. Outside a power outage or a utility demand response event, backup generators may run only between 9:00 a.m. and 5:00 p.m., Monday through Friday, excluding holidays. Systems that can run in parallel with the city electric utility or islanded are subject to a generator interconnection process and study at the operator's cost.
In effect · Other · Adopted Jul 8, 2025
Architectural features for data center buildings
Every data center building must include at least five of twelve listed architectural features, such as overhangs, canopies, arcades, window shrouds, raised corniced parapets, tower elements, corner glass, sloped roof forms, murals, decorative grilles or screens, and architectural lighting. The standard aims at visual interest at entryways and areas the public sees.
In effect · Other · Adopted Jul 8, 2025
Water Consumption and Thermal Management Report and Wastewater Report required with applications
Every data center development application must include a Water Consumption and Thermal Management Report stating whether the facility is water-cooled or air-cooled, estimated water use in acre feet per year with a monthly breakdown, use in million gallons per day on a typical day and on the highest-use day, the highest instantaneous flow rate, whether high demand can shift to the city's low-demand periods, the number and size of water meters, and proof of a complete Sustainable Water Service Application. A Wastewater Report with proof of a complete Industrial User Survey under Title 8, Chapter 4 is also required.
In effect · Zoning · Adopted Jul 8, 2025
Data Centers, Mesa Zoning Ordinance (Title 11)
Data centers are allowed as an accessory use in commercial and employment districts and as a principal use in the General Industrial (GI) and Heavy Industrial (HI) districts, but a principal use data center is not allowed by right and needs approval of a Planned Area Development (PAD) Overlay District. A data center that serves only the on-site owner or tenant, does not lease services to third parties, and takes no more than 10 percent of the site's total gross floor area counts as an accessory use and is exempt from the section's standards.
In the news
Mayes brings data center furor to Mesa town hall
East Valley Tribune
Court cases and commission dockets in Arizona (12)
Bills and laws in Arizona
- HB 4168 · In effect · Jul 1, 2026Pauses new data center tax relief applications for three years
- HB 2756 · Signed into law · Jun 4, 2026Lets regulators set special billing rules for very large customers
- HB 2452 · Died or failed · Feb 26, 2026Requires county comprehensive plans to designate land for data centers
- HB 4009 · Died or failed · Feb 26, 2026Requires mapping of data centers on state lands
- SB 1799 · Died or failed · Feb 9, 2026Moves the cutoff for new data center tax certifications to the end of 2026
- HB 2949 · Died or failed · Feb 5, 2026Requires large data centers to pay their full energy costs
- SB 1463 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
- SB 1467 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for Mesa
The lawmakers and local officials whose recorded jurisdiction is Mesa, with the bills and votes we have on record for each.
- David LunaCouncilmember · District 5
- Francisco HerediaCouncilmember · District 3
- Jennifer DuffVice Mayor · District 4
- John GilesMayor
- Julie SpilsburyCouncilmember · District 2
- Kevin ThompsonCouncilmember · District 6
- Mark FreemanCouncilmember · District 1
Questions people ask
- How many data centers are in Mesa?
- Data Center Fact Check tracks 9 data center projects in Mesa as of November 2026. Of those, 5 operating, 2 announced and 1 proposed.
- What is the biggest data center in Mesa?
- By announced capacity, the biggest data center in Mesa is EdgeCore Mesa campus, announced at 450 MW. It is expanding.
- How much power do data centers in Mesa use?
- The 9 projects tracked in Mesa have announced about 1,431 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Form EIA-861 final 2025 detailed data files
U.S. Energy Information AdministrationTier 1 · Open the source - 2City of Mesa Energy Resources Department 2024 Integrated Resource Plan
City of Mesa Energy Resources DepartmentTier 1 · Open the source - 3FERC Audit Report, Docket No. PA12-11-000, Salt River Project Agricultural Improvement and Power District
Federal Energy Regulatory CommissionTier 1 · Open the source - 4
- 5Certificate of Environmental Compatibility, Southeast Power Link Project, Case No. 180
Arizona Power Plant and Transmission Line Siting Committee (filed by Salt River Project)Tier 1 · Open the source - 6Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
City of Mesa, Office of Economic DevelopmentTier 1 · Open the source - 7Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
City of MesaTier 1 · Open the source - 8
- 9Development Agreement, City of Mesa, Arizona and Redale LLC (2021)
City of Mesa (Legistar)Tier 1 · Open the source - 10Resolution No. 11680 (Development Agreement and Sustainable Water Service Agreement with Redale LLC)
City of MesaTier 1 · Open the source - 11Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
City of MesaTier 1 · Open the source - 12Sustainable Water Service Agreement between the City of Mesa, Arizona and Redale LLC (2021)
City of Mesa (Legistar)Tier 1 · Open the source - 13Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
Google, published by the Arizona Commerce AuthorityTier 1 · Open the source - 14How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
GoogleTier 4 · Open the source - 15EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Open the source - 16EIA Form 861 2016, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Open the source - 17Decision No. 78669, Certificate of Environmental Compatibility for Project Huckleberry (Docket No. L-00000B-22-0113-00204)
Arizona Corporation CommissionTier 1 · Open the source - 18
- 19Google 2025 Environmental Report (2024 data), Water use by data center location table
GoogleTier 4 · Open the source - 20Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
City of Mesa (Legistar)Tier 1 · Open the source - 21Development Community Newsletter, September 2025 (data center ordinance summary)
City of Mesa, ArizonaTier 1 · Open the source - 22Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
City of MesaTier 1 · Open the source - 23Arizona Technology Council article on the Mesa data center standards
Arizona Technology CouncilTier 3 · Open the source - 24Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
Lincoln Institute of Land PolicyTier 2 · Open the source - 25Mesa, Arizona noise ordinance, Title 6, Chapter 12
Noise Pollution Clearinghouse (law library copy of City of Mesa code text)Tier 2 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Mesa." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-az-mesa