Data centers in Maricopa County, Arizona

Last checked Nov 7, 2026

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 48 data center projects in Maricopa County, Arizona as of November 2026: 30 operating, 7 proposed and 4 expanding, totaling about 5,160 MW announced where a figure is published.

Maricopa County has 48 tracked data centers. Their announced capacity totals about 5,160 MW where a figure is published. Of those, 30 operating, 7 proposed and 4 expanding. Electricity here comes from Arizona Public Service Company. Every figure comes from the public record linked on this page.

48Data center projects we track
$237Median homeowner tax bill, FY 2026
1.1591Real property tax rate, USD per 100 USD of assessed value, FY 2026

Data center projects in Maricopa County

Who serves this place

  • ElectricityArizona Public Service Company
  • ElectricityCity of Mesa Energy Resources
  • ElectricitySalt River Project
  • WaterCity of Goodyear Water Services
  • WaterCity of Mesa
  • WaterEPCOR
  • Grid regionArizona Public Service balancing area
  • Grid regionSalt River Project balancing area

A data center is proposed in Maricopa County

11 projects here are at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.

Open the resident checklist

Places in and around Maricopa County

Maricopa County is part of Arizona.

Cities and towns

  • Avondale3 data center projects tracked
  • Chandler6 data center projects tracked
  • El Mirage2 data center projects tracked
  • Glendale4 data center projects tracked
  • Goodyear8 data center projects tracked
  • Mesa9 data center projects tracked
  • Phoenix12 data center projects tracked
  • Scottsdale2 data center projects tracked
  • Tempe1 data center project tracked

Nearby places

For homeowners

What the projects here mean if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    • Google Mesa data center (Project Red Hawk):This campus pays a lease excise tax to Mesa instead of regular property tax on the land and buildings it leases from the city.

      Comes to the community
    • Microsoft PHX 10-11 (Goodyear):The median Maricopa County homeowner paid $237.10 in county property tax in fiscal 2026; the Goodyear campuses' own bills are not published.

      Comes to the community
    • Meta Mesa Data Center:Mesa 2021 development agreement with the campus contains no property tax abatement.

      Goes both ways
    • Microsoft El Mirage datacenter campus:Microsoft's Phoenix-area datacenters paid $5 million in local property tax in 2023; this campus's own bill is not published.

      Comes to the community
  2. Tax breaks

    • Meta Mesa Data Center:Two city agreements govern this campus, a development agreement and a water agreement; neither cuts its taxes.

      Goes both ways
    • Google Mesa data center (Project Red Hawk):Mesa gave this campus a 25-year GPLET lease in 2019, with excise tax at a 150 percent premium and no full abatement.

      Goes both ways
    • Microsoft El Mirage datacenter campus:No incentive agreement naming this campus is published; Arizona's data center tax program does not publish its certificate holders.

      Not known yet
    • Microsoft PHX 10-11 (Goodyear):No tax abatement or GPLET naming the Goodyear campuses is published; the city's agreements with Microsoft cover infrastructure, not taxes.

      Not known yet
  3. Money for schools and services

    • Microsoft El Mirage datacenter campus:Microsoft reports $2.4 million in Phoenix-area community investment from fiscal 2019 to 2023, including a West Valley Datacenter Academy.

      Comes to the community
    • Meta Mesa Data Center:The water deal moved 5,500 acre-feet of stored water credits to the city when it was signed.

      Comes from the community
    • Google Mesa data center (Project Red Hawk):Google has announced $250,000 in Mesa-area community funding: $150,000 for watershed restoration and $100,000 for the Mesa College Promise.

      Comes from the community
    • Microsoft PHX 10-11 (Goodyear):At the airport-area campus, Microsoft shares the cost of city water facilities, including a $5 million replacement-facilities contract under its 2024 amendment.

      Comes to the community
  4. Electricity bill

    • Google Mesa data center (Project Red Hawk):Salt River Project serves this campus; Google's supply agreement with SRP supports over 430 megawatts of new carbon-free capacity in Arizona.

      Not known yet
    • Microsoft El Mirage datacenter campus:Arizona Public Service is the electric utility for this campus, named as a project partner at its 2019 announcement.

      Not known yet
    • Meta Mesa Data Center:The average Salt River Project home paid $159.71 a month in 2025, up from $133.17 in 2016, not adjusted for inflation.

      Not known yet
    • Microsoft PHX 10-11 (Goodyear):Arizona Public Service serves the Goodyear campuses; a city record places an APS substation at the Citrus Road campus.

      Not known yet
  5. Water

    • Microsoft El Mirage datacenter campus:EPCOR provides water for this campus; city minutes show Microsoft applying to EPCOR for the newest building's added demand.

      Not known yet
    • Meta Mesa Data Center:The campus water allowance rises to 1,400 acre-feet a year at full buildout under its city water agreement.

      Comes from the community
    • Google Mesa data center (Project Red Hawk):Google reports its Mesa campus withdrew 19.4 million gallons of water in 2025, its first reported year.

      Comes from the community
    • Microsoft PHX 10-11 (Goodyear):Goodyear's city utility provides water and wastewater for the airport-area campus under a 2019 infrastructure agreement amended six times.

      Not known yet
  6. Jobs

  7. Next door: height, setbacks, noise

    • Microsoft El Mirage datacenter campus:The newest building is capped at 31 feet in the city's approval; the site sits in Luke Air Force Base's noise contour zone.

      Not known yet
    • Google Mesa data center (Project Red Hawk):This campus was approved in 2019 under its own employment district, six years before Mesa wrote general data center standards.

      Not known yet
    • Meta Mesa Data Center:Mesa data center standards exist in the city code; their numbers are not in our records yet.

      Not known yet
    • Microsoft PHX 10-11 (Goodyear):The airport-area campus occupies 279 acres rezoned for it in 2018 inside the Airport Commercenter district, beside Phoenix Goodyear Airport.

      Not known yet
  8. Your say

    • Microsoft El Mirage datacenter campus:El Mirage's council approved the fifth building 7 to 0 on December 3, 2024, after a 4 to 0 planning commission recommendation.

      Not known yet
    • Meta Mesa Data Center:The City Council approved the campus agreements 6 to 1 in a public vote on May 17, 2021.

      How to take part
    • Google Mesa data center (Project Red Hawk):Mesa's City Council approved this campus's development agreement and GPLET lease on July 1, 2019, by Resolution 11372.

      How to take part
    • Microsoft PHX 10-11 (Goodyear):Goodyear's council approved Microsoft agreement amendments unanimously in 2023 and 2025, with named votes recorded for both decisions.

      Not known yet

Taxes and budget over time

As published by the county, not adjusted for inflation. Projections are labeled.

Total property tax revenue

Total property tax revenue by year
FY 2025$786.9 million
FY 2024$770.4 million
FY 2023$760.1 million
FY 2022$776.4 million
FY 2021$755.9 million
FY 2020$704.8 million

Real property tax rate

Real property tax rate by year
FY 20261.1591 USD per 100 USD of assessed value
FY 20251.1591 USD per 100 USD of assessed value
FY 20241.2044 USD per 100 USD of assessed value
FY 20231.2473 USD per 100 USD of assessed value
FY 20221.3459 USD per 100 USD of assessed value
FY 20211.4009 USD per 100 USD of assessed value

Total assessed value

Total assessed value by year
FY 2026Projection$60.72 billion
FY 2025$58.33 billion
FY 2024$54.72 billion
FY 2023$51.58 billion
FY 2022$48.72 billion
FY 2021$45.7 billion

General fund budget

General fund budget by year
FY 2026$1.79 billion

Median homeowner tax bill

Median homeowner tax bill by year
FY 2026$237

Tax breaks and payments

  • 2021 · Meta Mesa Data Center

    Development Agreement and Sustainable Water Service Agreement (no tax terms)

    No tax schedule of any kind. The water agreement allows 550 acre-feet per year for Phase 1, rising to 1,100 (Phase 2) and 1,400 (Phase 3), and the company assigns 5,500 acre-feet of long-term storage credits to the city.

    All tax records for Meta Mesa Data Center
  • 2019 · Google Mesa data center (Project Red Hawk)

    Government Property Lease Excise Tax (GPLET) lease (A.R.S. Section 42-6201 et seq.)

    Under the lease form approved with the Development Agreement (Resolution No. 11372), Stone Applications LLC conveys land and improvements to the City of Mesa and leases them back for a Rental Period of 25 years from the first building's certificate of occupancy, at a net rent of $10,000 per year, which the lease states covers the city's administrative costs rather than fair market value. Conveyed property is government property, so the company pays the government property lease excise tax under A.R.S. Section 42-6201 et seq. instead of ad valorem real property tax on the conveyed property. Because the site is outside a Central Business District and a Redevelopment Area, the excise tax is charged at a 150 percent premium over the published excise tax rates, and the site is not eligible for the 8-year full abatement of excise taxes; the council report states this expressly. City staff projected about $32,967,000 in excise taxes over the 25-year term, against an estimated $48,916,134 in real property taxes without the GPLET; the roughly $15.9 million difference is arithmetic on those two city projections, not a figure the city stated.

    All tax records for Google Mesa data center (Project Red Hawk)

Local rules for data centers

  • In effect · Zoning · Adopted Dec 10, 2025

    Modernized Maricopa County Zoning Ordinance, data center provisions

    The modernized county zoning ordinance defines data centers and addresses them as an emerging technology use. Reporting on the adopted ordinance states that data centers are allowed in the IND-2 and IND-3 industrial districts, and land not zoned for the use must go through the county rezoning process. A county staff report for a February 2026 hearing states that data centers are a permitted use in the IND-2 district, while noting the ordinance does not specifically contemplate the use, which is why that project sought an overlay clarification.

  • In effect · Setback · Adopted Jul 8, 2025

    Separation from residential districts, height cap, screening, parking, and sound studies for data centers

    Planning staff described a minimum separation of 400 feet from residential zoning districts or sensitive uses, measured from the data center property to the nearest residential property line, a maximum building height of 60 feet unless an exception is approved through a PAD, screening for mechanical equipment and substations, and parking at 1 space per 5,000 square feet for the first 200,000 square feet and 1 space per 10,000 square feet after that. Staff also described an initial sound study at the nearest residential property line, a post-occupancy sound study within 30 days of the certificate of occupancy, and annual sound studies for the first five years.

  • In effect · Generator · Adopted Jul 8, 2025

    Backup generator operation and testing notice, Data Centers

    An operator using backup generators must announce any routine operation, including testing, on its website and notify the City of Mesa Public Information Office at least 24 hours in advance. Outside a power outage or a utility demand response event, backup generators may run only between 9:00 a.m. and 5:00 p.m., Monday through Friday, excluding holidays. Systems that can run in parallel with the city electric utility or islanded are subject to a generator interconnection process and study at the operator's cost.

  • In effect · Other · Adopted Jul 8, 2025

    Architectural features for data center buildings

    Every data center building must include at least five of twelve listed architectural features, such as overhangs, canopies, arcades, window shrouds, raised corniced parapets, tower elements, corner glass, sloped roof forms, murals, decorative grilles or screens, and architectural lighting. The standard aims at visual interest at entryways and areas the public sees.

  • In effect · Other · Adopted Jul 8, 2025

    Water Consumption and Thermal Management Report and Wastewater Report required with applications

    Every data center development application must include a Water Consumption and Thermal Management Report stating whether the facility is water-cooled or air-cooled, estimated water use in acre feet per year with a monthly breakdown, use in million gallons per day on a typical day and on the highest-use day, the highest instantaneous flow rate, whether high demand can shift to the city's low-demand periods, the number and size of water meters, and proof of a complete Sustainable Water Service Application. A Wastewater Report with proof of a complete Industrial User Survey under Title 8, Chapter 4 is also required.

In the news

More stories about this place

Court cases and commission dockets in Arizona (12)

Bills and laws in Arizona

All 15 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Maricopa County?
Data Center Fact Check tracks 48 data center projects in Maricopa County as of November 2026. Of those, 30 operating, 7 proposed and 4 expanding.
What is the biggest data center in Maricopa County?
By announced capacity, the biggest data center in Maricopa County is QTS Phoenix 3 campus (Glendale), announced at 750 MW. It is proposed.
How much power do data centers in Maricopa County use?
The 48 projects tracked in Maricopa County have announced about 5,160 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Resolution No. 2024-2417 approving the Fifth Amendment to Infrastructure Development Agreement for Project 10-11, with the Fifth Amendment as Exhibit 1
    City of Goodyear
    Tier 1 · Open the source
  2. 2
    Utility Rates
    City of Mesa
    Tier 1 · Open the source
  3. 3
    Planning and Zoning Commission minutes, November 12, 2024 (in April 8, 2025 agenda packet)
    City of El Mirage
    Tier 1 · Open the source
  4. 4
    Allowable Entries for Balancing Authorities and Hubs (Electric Quarterly Reports)
    Federal Energy Regulatory Commission
    Tier 1 · Open the source
  5. 5
    FERC Audit Report, Docket No. PA12-11-000, Salt River Project Agricultural Improvement and Power District
    Federal Energy Regulatory Commission
    Tier 1 · Open the source
  6. 6
    Form EIA-861 final 2025 detailed data files
    U.S. Energy Information Administration
    Tier 1 · Open the source
  7. 7
    FY 2026 Budget Book
    Maricopa County, Arizona
    Tier 1 · Open the source
  8. 8
    FY 2026 Budget Schedules
    Maricopa County, Arizona
    Tier 1 · Open the source
  9. 9
    Annual Comprehensive Financial Report, June 30, 2025
    Maricopa County, Arizona
    Tier 1 · Open the source
  10. 10
    Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
    City of Mesa, Office of Economic Development
    Tier 1 · Open the source
  11. 11
    Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
    City of Mesa
    Tier 1 · Open the source
  12. 12
    Development Agreement, City of Mesa, Arizona and Redale LLC (2021)
    City of Mesa (Legistar)
    Tier 1 · Open the source
  13. 13
    Resolution No. 11680 (Development Agreement and Sustainable Water Service Agreement with Redale LLC)
    City of Mesa
    Tier 1 · Open the source
  14. 14
    Economic contributions of Microsoft's datacenters in Phoenix, Arizona
    Microsoft Local
    Tier 4 · Open the source
  15. 15
    Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
    City of Mesa
    Tier 1 · Open the source
  16. 16
    Computer Data Center Program Rules and Guidelines (effective September 29, 2021)
    Arizona Commerce Authority
    Tier 1 · Open the source
  17. 17
    Development Application Staff Report, Case SPA24-09-01, Microsoft PHX83
    City of El Mirage Development Services
    Tier 1 · Open the source
  18. 18
    Arizona - Microsoft Local (Greater Phoenix)
    Microsoft Local
    Tier 4 · Open the source
  19. 19
    Sustainable Water Service Agreement between the City of Mesa, Arizona and Redale LLC (2021)
    City of Mesa (Legistar)
    Tier 1 · Open the source
  20. 20
    Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
    Google, published by the Arizona Commerce Authority
    Tier 1 · Open the source
  21. 21
    How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
    Google
    Tier 4 · Open the source
  22. 22
    EIA Form 861 2025, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  23. 23
    Microsoft to Build World-Class Sustainable Datacenters and Invest in Solar Power in Arizona (2019-07-30)
    Arizona Commerce Authority
    Tier 1 · Open the source
  24. 24
    EIA Form 861 2016, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  25. 25
    Decision No. 78669, Certificate of Environmental Compatibility for Project Huckleberry (Docket No. L-00000B-22-0113-00204)
    Arizona Corporation Commission
    Tier 1 · Open the source
  26. 26
    Agenda item, Southwest Next rezone request (City of Goodyear AgendaQuick)
    City of Goodyear
    Tier 1 · Open the source
  27. 27
    Microsoft's newest sustainable datacenter region coming to Arizona in 2021 / West US 3 launch coverage (2020-2021)
    Microsoft Azure Blog
    Tier 4 · Open the source
  28. 28
    Google 2026 Environmental Report
    Google
    Tier 4 · Open the source
  29. 29
    Google 2025 Environmental Report (2024 data), Water use by data center location table
    Google
    Tier 4 · Open the source
  30. 30
    City Council Regular Meeting minutes, March 6, 2023 (as published in the March 20, 2023 agenda packet)
    City of Goodyear
    Tier 1 · Open the source
  31. 31
    Expanding cloud services: Microsoft launches its sustainable datacenter region in Arizona
    Microsoft Azure Blog
    Tier 4 · Open the source
  32. 32
    Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
    City of Mesa (Legistar)
    Tier 1 · Open the source
  33. 33
    Development Community Newsletter, September 2025 (data center ordinance summary)
    City of Mesa, Arizona
    Tier 1 · Open the source
  34. 34
    Agenda item, rezone of a portion of Lots 16 and 17, Airport Commercenter (City of Goodyear AgendaQuick)
    City of Goodyear
    Tier 1 · Open the source
  35. 35
    Regular Meeting of the Common Council, Minutes (Draft), December 3, 2024
    City of El Mirage
    Tier 1 · Open the source
  36. 36
    Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
    City of Mesa
    Tier 1 · Open the source
  37. 37
    City Council Regular Meeting draft minutes, September 22, 2025 (as published in the October 27, 2025 agenda packet)
    City of Goodyear
    Tier 1 · Open the source
  38. 38
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Open the source
  39. 39
    Arizona Technology Council article on the Mesa data center standards
    Arizona Technology Council
    Tier 3 · Open the source
  40. 40
    Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
    Lincoln Institute of Land Policy
    Tier 2 · Open the source
  41. 41
    Mesa, Arizona noise ordinance, Title 6, Chapter 12
    Noise Pollution Clearinghouse (law library copy of City of Mesa code text)
    Tier 2 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Maricopa County." Last checked 2026-11-07. Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-az-maricopa

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page