Vantage Data Centers Goodyear campus (AZ1)
Goodyear,Maricopa County,ArizonaOperatingFirst public 2019Last checked Nov 8, 2026
Vantage Data CentersDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
6 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Confirmed: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Vantage Data Centers Goodyear campus (AZ1) is an operating data center project in Goodyear, Maricopa County, Arizona. Vantage Data Centers is named as operator. It was first public in 2019. It was announced at 176 MW.
Vantage Data Centers Goodyear campus (AZ1) is an operating data center project in Goodyear, Maricopa County, Arizona. Vantage Data Centers is named as operator. It was announced at 176 MW. All six of the core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Goodyear, Maricopa County, Arizona. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · New projectFirst public record of Vantage Data Centers Goodyear campus (AZ1)Operating
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 2756: Lets regulators set special billing rules for very large customers
The act covers new extra high load factor customers of an Arizona electric public service corporation or large public power entity, as defined by the corporation commission or the entity; this project has 176 MW announced on record, but whether its serving utility counts it as a new extra high load factor customer under that definition is not on record.
“An electric public service corporation operating in this state shall file with the corporation commission semiannual reports regarding new extra high load factor customers, AS defined by the corporation commission, that include both of the following WITH RESPECT TO THE IMMEDIATELY PRECEDING six-month period:” (Sec. 3, A.R.S. Sec. 40-207(A))
Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 4168: Pauses new data center tax relief applications for three years
The act covers new computer data centers, for which the Arizona Commerce Authority may not accept applications and which may not qualify for tax relief under A.R.S. Sec. 41-1519 from July 1, 2026 through June 30, 2029; this project has 176 MW announced on record, but whether this project is a new computer data center that applied for or seeks tax relief under section 41-1519 in that window is not on record.
“Notwithstanding any other law, beginning on July 1, 2026 through June 30, 2029, the Arizona commerce authority may not accept applications for any new computer data center pursuant to section 41-1519, Arizona Revised Statutes, and no new computer data centers qualify for tax relief under section 41-1519, Arizona Revised Statutes.” (Sec. 31(A), HB 4168 (Laws 2026, Chapter 140))
Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Arizona
- HB 4168 · In effect · Jul 1, 2026Pauses new data center tax relief applications for three years
- HB 2756 · Signed into law · Jun 4, 2026Lets regulators set special billing rules for very large customers
- HB 2452 · Died or failed · Feb 26, 2026Requires county comprehensive plans to designate land for data centers
- HB 4009 · Died or failed · Feb 26, 2026Requires mapping of data centers on state lands
- SB 1799 · Died or failed · Feb 9, 2026Moves the cutoff for new data center tax certifications to the end of 2026
- HB 2949 · Died or failed · Feb 5, 2026Requires large data centers to pay their full energy costs
Who's involved
- Developer and operatorVantage Data Centers
Public records
7 records found so far. 6 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Proposed · Nov 6, 2026APS and TSMC Arizona 25-Year Direct Pricing Contract
- Utility commission · Pending before the commission · Oct 2, 2026In the Matter of the Commission's Inquiry and Review of the Existing Rate Classifications and Other Potential Issues Relating to Data Centers
- Utility commission · Pending before the commission · Jul 7, 2026Application of Arizona Public Service Company for approval of new rates, charges, and schedules
- Utility commission · In effect · Mar 8, 2024Rate Schedule XHLF, General Service, Extra High Load Factor
Questions people ask
- Where is Vantage Data Centers Goodyear campus (AZ1)?
- Vantage Data Centers Goodyear campus (AZ1) is a data center project in Goodyear, Maricopa County, Arizona.
- Who operates Vantage Data Centers Goodyear campus (AZ1)?
- Vantage Data Centers is named as the operator of Vantage Data Centers Goodyear campus (AZ1).
- How big is Vantage Data Centers Goodyear campus (AZ1)?
- Vantage Data Centers Goodyear campus (AZ1) was announced at 176 MW of capacity. The site covers 50 acres.
- What stage is Vantage Data Centers Goodyear campus (AZ1)?
- Vantage Data Centers Goodyear campus (AZ1) is operating. It was first public in 2019.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
Maricopa County, ArizonaTier 1 · Captured 2026-11-07 · Open the source - 2Public Notice of Hearing and Public Comment Meetings on Arizona Public Service Company Rate Application, Docket No. E-01345A-25-0105
Arizona Public Service CompanyTier 1 · Captured 2026-11-07 · Open the source - 3What's Next in the APS Rate Case?
Arizona Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 4Filing in Docket No. E-00000A-25-0069 (data center rate classifications inquiry)
Arizona Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 5Attorney General Mayes urges Arizona Corporation Commission investigation of APS Power Supply Adjustor (press release)
Office of the Arizona Attorney GeneralTier 1 · Captured 2026-11-07 · Open the source - 6Rate Schedule XHLF, General Service, Extra High Load Factor (A.C.C. No. 6067)
Arizona Public Service CompanyTier 1 · Captured 2026-11-07 · Open the source - 7APS submits long-term energy agreement with TSMC to the Arizona Corporation Commission
Arizona Public Service CompanyTier 1 · Captured 2026-11-08 · Open the source - 8City Council Regular Meeting minutes, March 6, 2023 (as published in the March 20, 2023 agenda packet)
City of GoodyearTier 1 · Captured 2026-11-09 · Open the source - 9City Council Regular Meeting draft minutes, September 22, 2025 (as published in the October 27, 2025 agenda packet)
City of GoodyearTier 1 · Captured 2026-11-09 · Open the source - 10Phoenix Data Center Campus, Arizona
Vantage Data CentersTier 4 · Captured 2026-11-08 · Open the source - 11Vantage Data Centers chooses Goodyear (city news release, January 8, 2019)
City of GoodyearTier 1 · Captured 2026-11-08 · Open the source - 12U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page