Utility commission
Application of Arizona Public Service Company for approval of new rates, charges, and schedules
Where it stands: Pending before the commission as of Jul 7, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
As proposed, new general service rate structures would end the cross-subsidy APS says comes from significant, concentrated load growth among large high-load-factor customers such as data centers: class revenue up 23.52 percent for Extra Large (E-34, E-35) and 47.03 percent for Extra High Load Factor, the costs of power purchase agreements driven by extra-large customer growth assigned directly to those customers instead of spread through the Power Supply Adjustor, and annual cost-of-service updates for the extra-large classes. APS asked for a $662.44 million (15.99 percent) base rate increase overall.
The facts
- Regulator
- Arizona Corporation Commission
- Docket number
- E-01345A-25-0105
- Type
- Rate case
- Utility
- Arizona Public Service Company
- State
- Arizona
- Filed
- Jun 13, 2025
- Status date
- Jul 7, 2026
- Large-load rules
- Yes
Projects served by Arizona Public Service Company
- Aligned Data Centers PHX-13 (Glendale)
- Compass Datacenters Goodyear campus
- Digital Realty PHX10 (Phoenix)
- Flexential Phoenix - Deer Valley Data Center
- Iron Mountain Data Centers AZS-1 (Scottsdale)
- Iron Mountain Phoenix campus (AZP-1, AZP-2, AZP-3)
- Microsoft Citrus Road campus (Goodyear)
- Microsoft El Mirage datacenter campus
- Microsoft PHX 10-11 (Goodyear)
- phoenixNAP Phoenix Data Center
- Stream Data Centers Goodyear campus (Phoenix I-V)
- Stream Data Centers Phoenix
Related cases and proceedings
- Utility commission · ProposedAPS and TSMC Arizona 25-Year Direct Pricing Contract
- Utility commission · Pending before the commissionApplication of Tucson Electric Power Company for the Establishment of Just and Reasonable Rates and Charges Designed to Realize a Reasonable Rate of Return on the Fair Value of the Properties of Tucson Electric Power Company
- Utility commission · Pending before the commissionIn the Matter of the Commission's Inquiry and Review of the Existing Rate Classifications and Other Potential Issues Relating to Data Centers
- Utility commission · DecidedTemporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
In the record
- Utility case, Jun 13, 2025. Utility case filed: Application of Arizona Public Service Company for approval of new rates, charges, and schedules Arizona Corporation Commission, E-01345A-25-0105
Sources
- 1Public Notice of Hearing and Public Comment Meetings on Arizona Public Service Company Rate Application, Docket No. E-01345A-25-0105
Arizona Public Service CompanyTier 1 · APS Public Notice of Hearing (filing date and revenue figures; General Service Rate Design Changes; class increase table); ACC, What's Next in the APS Rate Case, 2026-07-10 (hearing May 18 to July 7, 2026; recommendation expected late November 2026; vote deadline December 31, 2026) · Open the source - 2What's Next in the APS Rate Case?
Arizona Corporation CommissionTier 1 · APS Public Notice of Hearing (filing date and revenue figures; General Service Rate Design Changes; class increase table); ACC, What's Next in the APS Rate Case, 2026-07-10 (hearing May 18 to July 7, 2026; recommendation expected late November 2026; vote deadline December 31, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Arizona Public Service Company for approval of new rates, charges, and schedules." Last activity 2026-07-07. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aps-rate-case-2025