Utility commission

Application of Arizona Public Service Company for approval of new rates, charges, and schedules

Where it stands: Pending before the commission as of Jul 7, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

As proposed, new general service rate structures would end the cross-subsidy APS says comes from significant, concentrated load growth among large high-load-factor customers such as data centers: class revenue up 23.52 percent for Extra Large (E-34, E-35) and 47.03 percent for Extra High Load Factor, the costs of power purchase agreements driven by extra-large customer growth assigned directly to those customers instead of spread through the Power Supply Adjustor, and annual cost-of-service updates for the extra-large classes. APS asked for a $662.44 million (15.99 percent) base rate increase overall.

The facts

Regulator
Arizona Corporation Commission
Docket number
E-01345A-25-0105
Type
Rate case
Utility
Arizona Public Service Company
State
Arizona
Filed
Jun 13, 2025
Status date
Jul 7, 2026
Large-load rules
Yes

Projects served by Arizona Public Service Company

Related cases and proceedings

In the record

  1. Utility case, Jun 13, 2025. Utility case filed: Application of Arizona Public Service Company for approval of new rates, charges, and schedules Arizona Corporation Commission, E-01345A-25-0105

Sources

  1. 1
    Public Notice of Hearing and Public Comment Meetings on Arizona Public Service Company Rate Application, Docket No. E-01345A-25-0105
    Arizona Public Service Company
    Tier 1 · APS Public Notice of Hearing (filing date and revenue figures; General Service Rate Design Changes; class increase table); ACC, What's Next in the APS Rate Case, 2026-07-10 (hearing May 18 to July 7, 2026; recommendation expected late November 2026; vote deadline December 31, 2026) · Open the source
  2. 2
    What's Next in the APS Rate Case?
    Arizona Corporation Commission
    Tier 1 · APS Public Notice of Hearing (filing date and revenue figures; General Service Rate Design Changes; class increase table); ACC, What's Next in the APS Rate Case, 2026-07-10 (hearing May 18 to July 7, 2026; recommendation expected late November 2026; vote deadline December 31, 2026) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Arizona Public Service Company for approval of new rates, charges, and schedules." Last activity 2026-07-07. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aps-rate-case-2025