What it is

A large customer arranges its own generation supply from an eligible third party and SRP delivers it for a Buy-Through Charge, $4.03 per kW from November 1, 2025. The customer needs a minimum annual peak demand of 5 MW and a minimum average monthly load factor of 60 percent, and must be on plan E-63, E-65, or E-67. Total program participation is capped at 200 MW of customer demand.

The facts

Regulator
Board of Directors, Salt River Project Agricultural Improvement and Power District
Type
Other
Utility
Salt River Project
State
Arizona
Filed
Jan 1, 2024
Status date
Nov 1, 2025
Large-load rules
Yes, for loads of 5 MW or more

Projects served by Salt River Project

Related cases and proceedings

In the record

  1. Utility case, Jan 1, 2024. Utility case filed: Buy-Through Program Board of Directors, Salt River Project Agricultural Improvement and Power District

Sources

  1. 1
    Buy-Through Program for large businesses
    Salt River Project
    Tier 1 · SRP Buy-Through Program page, About the program (200 MW cap, 5 MW and 60 percent minimums) and Buy-Through Program Updates (November 1, 2025 charge change) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Buy-Through Program." Last activity 2025-11-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-srp-buy-through