Utility commission
E-67, Standard Price Plan for Large Load Substation Large General Service
Where it stands: In effect as of Nov 1, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
A Large Load Account is an account with a load of 20 MW or more, or reasonably expected to reach 20 MW within five years of first taking service. Accounts first taking service on or after November 1, 2025 must take E-67 and are billed per-kW charges on at least 80 percent of their forecasted demand, whether they use it or not; SRP may reduce the floor where the customer pays for load-serving resources itself, or for economic development reasons. The customer signs an Agreement for Electric Service that specifies the minimum billing demand, the maximum load, and forecasting requirements, and pays a customer-specific facilities charge for its substation on top of the $5,767.02 monthly service charge.
The facts
- Regulator
- Board of Directors, Salt River Project Agricultural Improvement and Power District
- Type
- Large load tariff
- Utility
- Salt River Project
- State
- Arizona
- Status date
- Nov 1, 2025
- Large-load rules
- Yes, for loads of 20 MW or more
Projects served by Salt River Project
Related cases and proceedings
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
- Utility commission · DecidedProposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle
- Utility commission · In effectRate Schedule XHLF, General Service, Extra High Load Factor
Sources
- 1E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
Salt River ProjectTier 1 · E-67 rate book sheet (November 2025 billing cycle), Availability, Special Conditions A to H (Condition B, 80 percent minimum billing demand; Condition E, Agreement for Electric Service), Minimum Bill section · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "E-67, Standard Price Plan for Large Load Substation Large General Service." Last activity 2025-11-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-srp-e67