What it is
SRP's elected Board, not the Arizona Corporation Commission, sets its prices through a public pricing process. This process raised overall net revenue 2.4 percent from the November 2025 billing cycle and rewrote the E-67 large load plan: new large load customers must take E-67 and are billed on a minimum demand of 80 percent of their forecasted demand. Management committed to put security requirements in place for new E-67 customers, lasting for the duration of the customer's service agreement.
The facts
- Regulator
- Board of Directors, Salt River Project Agricultural Improvement and Power District
- Type
- Rate case
- Utility
- Salt River Project
- State
- Arizona
- Filed
- Dec 2, 2024
- Status date
- Feb 27, 2025
- Large-load rules
- Yes, for loads of 20 MW or more
Projects served by Salt River Project
Related cases and proceedings
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
- Utility commission · In effectE-67, Standard Price Plan for Large Load Substation Large General Service
- Utility commission · In effectRate Schedule XHLF, General Service, Extra High Load Factor
In the record
- Utility case, Dec 2, 2024. Utility case filed: Proposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle Board of Directors, Salt River Project Agricultural Improvement and Power District
Sources
- 1Notice of Changes to SRP Standard Electric Price Plans
Salt River ProjectTier 1 · SRP Notice of Changes, opening paragraph (Board concluded the process February 27, 2025; +2.4 percent net) and item 5 (E-67 changes); Management Recommendations memorandum, 2025-02-21, item 6 (Credit Provisions for E-67 Customers) · Open the source - 2Management Recommendations for the February 27, 2025 Special Board Meeting
Salt River ProjectTier 1 · SRP Notice of Changes, opening paragraph (Board concluded the process February 27, 2025; +2.4 percent net) and item 5 (E-67 changes); Management Recommendations memorandum, 2025-02-21, item 6 (Credit Provisions for E-67 Customers) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Proposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle." Last activity 2025-02-27. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-srp-price-process-2025