Substation-level service with no MW threshold: a $5,767.02 monthly service charge (one meter) plus a customer-specific facilities charge and seasonal on-peak demand charges. Transmission-voltage service above 69 kV earns a 20.1 percent transmission charge reduction.
The facts
- Regulator
- Board of Directors, Salt River Project Agricultural Improvement and Power District
- Type
- Large load tariff
- Utility
- Salt River Project
- State
- Arizona
- Status date
- Nov 1, 2025
- Large-load rules
- Yes
Projects served by Salt River Project
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Arizona Public Service Company for approval of new rates, charges, and schedules
- Utility commission · DecidedTemporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
- Utility commission · In effectE-67, Standard Price Plan for Large Load Substation Large General Service
- Utility commission · DecidedProposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle
- Utility commission · In effectRate Schedule XHLF, General Service, Extra High Load Factor
Sources
- 1E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
Salt River ProjectTier 1 · E-65 rate book sheet (November 2025 billing cycle), Availability and monthly service charge table · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "E-65, Standard Price Plan for Substation Large General Service." Last activity 2025-11-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-srp-e65