What it is
The Board cut FPPAM prices by $0.0038 per kWh for the summer and summer peak 2026 seasons, an overall temporary price decrease of about 3 percent, worth about $5.57 a month to the average residential customer. The decrease applied to all price plans, which includes the large general service plans E-65, E-66 and E-67 whose bills carry the FPPAM component, so large load customers received it on the same per-kWh terms as every other customer. It ran only for the May through October 2026 billing cycles and then reverted to the November 2025 price levels with the November 2026 billing cycle. Management proposed it because the FPPAM balance, the difference between fuel and purchased power costs and what customers have paid toward them, was projected to sit above its Board-approved target range (a surplus of more than $50 million at the end of April 2026).
The facts
- Regulator
- Board of Directors, Salt River Project Agricultural Improvement and Power District
- Type
- Other
- Utility
- Salt River Project
- State
- Arizona
- Status date
- Mar 26, 2026
- Large-load rules
- Yes
Projects served by Salt River Project
Related cases and proceedings
- Utility commission · ProposedAPS and TSMC Arizona 25-Year Direct Pricing Contract
- Utility commission · Pending before the commissionApplication of Tucson Electric Power Company for the Establishment of Just and Reasonable Rates and Charges Designed to Realize a Reasonable Rate of Return on the Fair Value of the Properties of Tucson Electric Power Company
- Utility commission · Pending before the commissionIn the Matter of the Commission's Inquiry and Review of the Existing Rate Classifications and Other Potential Issues Relating to Data Centers
- Utility commission · Pending before the commissionApplication of Arizona Public Service Company for approval of new rates, charges, and schedules
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
Sources
- 1SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
Salt River ProjectTier 1 · District Board packet for April 13, 2026, minutes of March 26, 2026, consent agenda item B (approval to temporarily decrease FPPAM prices by $0.0038 per kWh effective with the May 2026 billing cycle, summer and summer peak 2026, all price plans); FY26 Annual Report, Electricity Pricing section (Board approved a 3 percent overall summer price decrease through an FPPAM reduction for the May through October 2026 billing cycles, reverting to November 2025 levels) · Open the source - 2SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
Salt River ProjectTier 1 · District Board packet for April 13, 2026, minutes of March 26, 2026, consent agenda item B (approval to temporarily decrease FPPAM prices by $0.0038 per kWh effective with the May 2026 billing cycle, summer and summer peak 2026, all price plans); FY26 Annual Report, Electricity Pricing section (Board approved a 3 percent overall summer price decrease through an FPPAM reduction for the May through October 2026 billing cycles, reverting to November 2025 levels) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Temporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles." Last activity 2026-03-26. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-srp-fppam-summer-2026