Utility commission
APS and TSMC Arizona 25-Year Direct Pricing Contract
Where it stands: Proposed as of Nov 6, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
A proposed 25-year Direct Pricing Contract, APS's instrument for extra-large energy users, which APS describes as covering semiconductor fabs and data centers alike. Under the contract as APS summarises it, TSMC Arizona takes full long-term financial responsibility for 100 percent of the new power plants, transmission lines and equipment needed to serve its facilities, plus its usage of shared system resources, so no part of that cost falls on other customers. The instrument's protections, per APS, are cost protection (the large customer funds its own dedicated infrastructure), reliability protection (new dedicated generation preserves existing grid capacity), risk protection (upfront financial security covers early departure risk) and financing protection (the direct agreement protects APS's credit metrics). APS states TSMC receives no discounted rate or subsidy under the contract.
The facts
- Regulator
- Arizona Corporation Commission
- Type
- Other
- Utility
- Arizona Public Service Company
- State
- Arizona
- Filed
- Nov 6, 2026
- Status date
- Nov 6, 2026
- Large-load rules
- Yes
Projects served by Arizona Public Service Company
- Aligned Data Centers PHX-13 (Glendale)
- Compass Datacenters Goodyear campus
- Digital Realty PHX10 (Phoenix)
- Flexential Phoenix - Deer Valley Data Center
- Iron Mountain Data Centers AZS-1 (Scottsdale)
- Iron Mountain Phoenix campus (AZP-1, AZP-2, AZP-3)
- Microsoft Citrus Road campus (Goodyear)
- Microsoft El Mirage datacenter campus
- Microsoft PHX 10-11 (Goodyear)
- phoenixNAP Phoenix Data Center
- Stream Data Centers Goodyear campus (Phoenix I-V)
- Stream Data Centers Phoenix
Related cases and proceedings
- Utility commission · Pending before the commissionApplication of Tucson Electric Power Company for the Establishment of Just and Reasonable Rates and Charges Designed to Realize a Reasonable Rate of Return on the Fair Value of the Properties of Tucson Electric Power Company
- Utility commission · Pending before the commissionIn the Matter of the Commission's Inquiry and Review of the Existing Rate Classifications and Other Potential Issues Relating to Data Centers
- Utility commission · Pending before the commissionApplication of Arizona Public Service Company for approval of new rates, charges, and schedules
- Utility commission · DecidedTemporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles
- Utility commission · DecidedApplication of Tucson Electric Power Company for Approval of a Special Agreement for Electric Service with Humphrey's Peak Power, LLC
- Utility commission · In effectBuy-Through Program
- Utility commission · In effectE-65, Standard Price Plan for Substation Large General Service
- Utility commission · In effectE-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load
In the record
- Utility case, Nov 6, 2026. Utility case filed: APS and TSMC Arizona 25-Year Direct Pricing Contract Arizona Corporation Commission
Sources
- 1APS submits long-term energy agreement with TSMC to the Arizona Corporation Commission
Arizona Public Service CompanyTier 1 · APS newsroom release, November 6, 2026, opening paragraphs (filed with the ACC November 6, 2026; 25-year Direct Pricing Contract) and Frequently Asked Questions (100 percent of new plants, transmission, equipment and shared system usage; DPC defined for extra-large users including data centers; four protections including upfront financial security) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "APS and TSMC Arizona 25-Year Direct Pricing Contract." Last activity 2026-11-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-aps-tsmc-dpc-2026