Data centers in Goodyear, Arizona
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 8 data center projects in Goodyear, Arizona as of November 2026: 5 operating, 2 expanding and 1 proposed, totaling about 1,474 MW announced where a figure is published.
Goodyear has 8 tracked data centers. Their announced capacity totals about 1,474 MW where a figure is published. Of those, 5 operating, 2 expanding and 1 proposed. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Goodyear
- Compass Datacenters Goodyear campus
OperatingGoodyear350 MW announced
- Compass Datacenters Goodyear Campus (Goodyear; 212 MW campus in development)
ProposedGoodyear212 MW announced
- Microsoft Citrus Road campus (Goodyear)
ExpandingGoodyear
- Microsoft PHX 10-11 (Goodyear)
ExpandingGoodyear
- Stream Data Centers Goodyear campus (Phoenix I-V)
OperatingGoodyear280 MW announced
- Stream Data Centers Phoenix
OperatingGoodyear280 MW announced
- Vantage Data Centers Goodyear campus (AZ1)
OperatingGoodyear176 MW announced
- Vantage Data Centers Phoenix Campus (Phoenix)
OperatingGoodyear176 MW announced
Who serves this place
- Not collected yet.
More places in Maricopa County
Goodyear is part of Maricopa County.
Nearby places
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Microsoft PHX 10-11 (Goodyear):The median Maricopa County homeowner paid $237.10 in county property tax in fiscal 2026; the Goodyear campuses' own bills are not published.
Comes to the community
Tax breaks
Microsoft PHX 10-11 (Goodyear):No tax abatement or GPLET naming the Goodyear campuses is published; the city's agreements with Microsoft cover infrastructure, not taxes.
Not known yet
Money for schools and services
Microsoft PHX 10-11 (Goodyear):At the airport-area campus, Microsoft shares the cost of city water facilities, including a $5 million replacement-facilities contract under its 2024 amendment.
Comes to the community
Electricity bill
Microsoft PHX 10-11 (Goodyear):Arizona Public Service serves the Goodyear campuses; a city record places an APS substation at the Citrus Road campus.
Not known yet
Water
Microsoft PHX 10-11 (Goodyear):Goodyear's city utility provides water and wastewater for the airport-area campus under a 2019 infrastructure agreement amended six times.
Not known yet
Jobs
Microsoft PHX 10-11 (Goodyear):Arizona's 2019 announcement projected more than 100 permanent and 1,000 construction jobs across all three campuses; no Goodyear-only count is published.
Not known yet
Next door: height, setbacks, noise
Microsoft PHX 10-11 (Goodyear):The airport-area campus occupies 279 acres rezoned for it in 2018 inside the Airport Commercenter district, beside Phoenix Goodyear Airport.
Not known yet
Your say
Microsoft PHX 10-11 (Goodyear):Goodyear's council approved Microsoft agreement amendments unanimously in 2023 and 2025, with named votes recorded for both decisions.
Not known yet
Court cases and commission dockets in Arizona (12)
Bills and laws in Arizona
- HB 4168 · In effect · Jul 1, 2026Pauses new data center tax relief applications for three years
- HB 2756 · Signed into law · Jun 4, 2026Lets regulators set special billing rules for very large customers
- HB 2452 · Died or failed · Feb 26, 2026Requires county comprehensive plans to designate land for data centers
- HB 4009 · Died or failed · Feb 26, 2026Requires mapping of data centers on state lands
- SB 1799 · Died or failed · Feb 9, 2026Moves the cutoff for new data center tax certifications to the end of 2026
- HB 2949 · Died or failed · Feb 5, 2026Requires large data centers to pay their full energy costs
- SB 1463 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
- SB 1467 · Died or failed · Feb 2, 2026Repeals the state computer data center tax relief statute
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for Goodyear
The lawmakers and local officials whose recorded jurisdiction is Goodyear, with the bills and votes we have on record for each.
- Benita BecklesCouncilmember
- Bill StippCouncilmember
- Brannon HamptonCouncilmember
- Joe PizzilloMayor
- Laura KainoVice Mayor
- Sheri LauritanoCouncilmember
- Trey TerryCouncilmember
- Vicki GillisCouncilmember
- Wally CampbellCouncilmember
Questions people ask
- How many data centers are in Goodyear?
- Data Center Fact Check tracks 8 data center projects in Goodyear as of November 2026. Of those, 5 operating, 2 expanding and 1 proposed.
- What is the biggest data center in Goodyear?
- By announced capacity, the biggest data center in Goodyear is Compass Datacenters Goodyear campus, announced at 350 MW. It is operating.
- How much power do data centers in Goodyear use?
- The 8 projects tracked in Goodyear have announced about 1,474 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1
- 2
- 3Resolution No. 2024-2417 approving the Fifth Amendment to Infrastructure Development Agreement for Project 10-11, with the Fifth Amendment as Exhibit 1
City of GoodyearTier 1 · Open the source - 4Computer Data Center Program Rules and Guidelines (effective September 29, 2021)
Arizona Commerce AuthorityTier 1 · Open the source - 5Agenda item, Southwest Next rezone request (City of Goodyear AgendaQuick)
City of GoodyearTier 1 · Open the source - 6Microsoft to Build World-Class Sustainable Datacenters and Invest in Solar Power in Arizona (2019-07-30)
Arizona Commerce AuthorityTier 1 · Open the source - 7City Council Regular Meeting minutes, March 6, 2023 (as published in the March 20, 2023 agenda packet)
City of GoodyearTier 1 · Open the source - 8Agenda item, rezone of a portion of Lots 16 and 17, Airport Commercenter (City of Goodyear AgendaQuick)
City of GoodyearTier 1 · Open the source - 9City Council Regular Meeting draft minutes, September 22, 2025 (as published in the October 27, 2025 agenda packet)
City of GoodyearTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Goodyear." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-az-goodyear
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page