Every public record we have for Google Mesa data center (Project Red Hawk)

Mesa, Maricopa County, ArizonaOperatingFirst public 2019Filing entity: Stone Applications LLCLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

3 of 21 records · showing tax breaks and payments only ·

2019

  • Tax agreementApprovedJul 1, 2019City of Mesa

    City of Mesa, Exhibit E to the Development Agreement (Government Property Improvements Lease)

    Form of lease approved with the Development Agreement by Resolution No. 11372 on July 1, 2019; the lease itself is entered on the company's request after a building's certificate of occupancy (Development Agreement Section 5.4)

    Gplet net annual rent:
    $10,000 _per_year
    Gplet rental period:
    25 years
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Exhibit E (GPLET Lease), Sections 4(D), 5(gg), 6(A), 7(G)

  • Tax agreementJul 1, 2019Mesa

    Government Property Lease Excise Tax (GPLET) lease (A.R.S. Section 42-6201 et seq.)

    Under the lease form approved with the Development Agreement (Resolution No. 11372), Stone Applications LLC conveys land and improvements to the City of Mesa and leases them back for a Rental Period of 25 years from the first building's certificate of occupancy, at a net rent of $10,000 per year, which the lease states covers the city's administrative costs rather than fair market value. Conveyed property is government property, so the company pays the government property lease excise tax under A.R.S. Section 42-6201 et seq. instead of ad valorem real property tax on the conveyed property. Because the site is outside a Central Business District and a Redevelopment Area, the excise tax is charged at a 150 percent premium over the published excise tax rates, and the site is not eligible for the 8-year full abatement of excise taxes; the council report states this expressly. City staff projected about $32,967,000 in excise taxes over the 25-year term, against an estimated $48,916,134 in real property taxes without the GPLET; the roughly $15.9 million difference is arithmetic on those two city projections, not a figure the city stated. The lease is entered on the company's request after a building's certificate of occupancy (Development Agreement Section 5.4), with a $2,500,000 title policy and closing costs at the company's expense. The Development Agreement's milestones (building area, taxable construction costs, and capital investment minimums at July 1, 2025, 2027, and 2029, plus a $65,000 average compensation floor for project full-time employees) gate the city's water allowance increases. Title to the premises reconveys to the tenant at the end of the lease (Lease Section 34, as referenced in Section 7(G)).

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Development Agreement Section 5.4 and Exhibit E (GPLET Lease) Sections 5(gg), 6(A), 7(G); OED presentation, GPLET slides; council report, Government Property Improvements Lease section, item 6

  • Public decisionFiledJun 27, 2019City of Mesa, Office of Economic Development

    City of Mesa, Office of Economic Development, Study Session Presentation for Legistar File 19-0809

    Staff presentation of the Project Red Hawk agreement terms and the 25-year GPLET analysis

    Real property tax 2019 as farmland:
    $3,604
    Projected total tax revenue 25 year:
    $156.6 million
    Gplet excise tax rate premium:
    150 percent_of_published_rates
    Gplet excise tax projected 25 year:
    $33 million
    Real property tax projected 25 year without gplet:
    $48.9 million
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Presentation slides: City of Mesa Obligations (GPLET); 25-Year GPLET Analysis; Projected Tax Revenue over 25 years

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Resolution No. 11372, approving and authorizing the City Manager to enter into a Development Agreement and Lease with Stone Applications, LLC (as attached to Legistar File 19-0809)
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Council Report: proposed Development Agreement and Government Property Improvement Lease between City of Mesa and Stone Applications LLC (Project Red Hawk), July 1, 2019
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Project Red Hawk: Development Agreement & Government Property Improvements Lease Presentation, City Council Study Session, June 27, 2019
    City of Mesa, Office of Economic Development
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Development Agreement between City of Mesa, Arizona and Stone Applications LLC (Project Red Hawk), with Government Property Improvements Lease as Exhibit E
    City of Mesa
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Legistar matter record ZON19-00016 (Redhawk): rezone to create the Red Hawk Employment Opportunity Zone
    City of Mesa (Legistar)
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Arizona Technology Council article on the Mesa data center standards
    Arizona Technology Council
    Tier 3 · Captured 2026-11-07 · Open the source
  8. 8
    Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
    Lincoln Institute of Land Policy
    Tier 2 · Captured 2026-11-07 · Open the source
  9. 9
    Development Community Newsletter, September 2025 (data center ordinance summary)
    City of Mesa, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    Mesa, Arizona noise ordinance, Title 6, Chapter 12
    Noise Pollution Clearinghouse (law library copy of City of Mesa code text)
    Tier 2 · Captured 2026-11-07 · Open the source
  11. 11
    Buy-Through Program for large businesses
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  12. 12
    E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    Notice of Changes to SRP Standard Electric Price Plans
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  14. 14
    Management Recommendations for the February 27, 2025 Special Board Meeting
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  15. 15
    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  16. 16
    E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  17. 17
    SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Council Minutes, Regular Council Meeting, May 17, 2021
    City of Mesa, Office of the City Clerk
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Google Announces New Commitment to Arizona (Google news release, September 6, 2023)
    Google, published by the Arizona Commerce Authority
    Tier 1 · Captured 2026-11-09 · Open the source
  21. 21
    How Google brought carbon-free energy to Arizona (Google blog, March 14, 2024)
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  22. 22
    Google Data Centers: Locations
    Google
    Tier 4 · Captured 2026-11-09 · Open the source
  23. 23
    Google 2026 Environmental Report
    Google
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page