Project File
Beale Infrastructure Marana Data Center Campus (Luckett Road)
Marana,Pima County,ArizonaApprovedFirst public 2026Filing entity: Herbert Kai S12 LLC; Kai Trst 97 S12, LLC; Jihong S12 LLC (owners of record, South parcel)Last checked Nov 10, 2026
Beale InfrastructureDeveloper
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: First public date
- Still to confirm: Capacity
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Beale Infrastructure Marana Data Center Campus (Luckett Road) is an approved data center project in Marana, Pima County, Arizona. Beale Infrastructure is named as developer. It was first public in 2026. No site capacity figure is published for this project.
Beale Infrastructure Marana Data Center Campus (Luckett Road) is an approved data center project in Marana, Pima County, Arizona. Beale Infrastructure is named as developer. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Marana, Pima County, Arizona. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · DecisionTown of Marana: Approved (rezoning) for Beale Infrastructure Marana Data Center Campus (Luckett Road)Ordinance No. 2026.003
- · DecisionTown of Marana: Approved (rezoning) for Beale Infrastructure Marana Data Center Campus (Luckett Road)Ordinance No. 2026.002
- · New projectFirst public record of Beale Infrastructure Marana Data Center Campus (Luckett Road)Approved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 2756: Lets regulators set special billing rules for very large customers
The act covers new extra high load factor customers of an Arizona electric public service corporation or large public power entity, as defined by the corporation commission or the entity; this project has no capacity figure on record, but whether its serving utility counts it as a new extra high load factor customer under that definition is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which leaves the customer definition to the commission or the entity.
“An electric public service corporation operating in this state shall file with the corporation commission semiannual reports regarding new extra high load factor customers, AS defined by the corporation commission, that include both of the following WITH RESPECT TO THE IMMEDIATELY PRECEDING six-month period:” (Sec. 3, A.R.S. Sec. 40-207(A))
Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 4168: Pauses new data center tax relief applications for three years
The act covers new computer data centers, for which the Arizona Commerce Authority may not accept applications and which may not qualify for tax relief under A.R.S. Sec. 41-1519 from July 1, 2026 through June 30, 2029; this project has no capacity figure on record, but whether this project is a new computer data center that applied for or seeks tax relief under section 41-1519 in that window is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“Notwithstanding any other law, beginning on July 1, 2026 through June 30, 2029, the Arizona commerce authority may not accept applications for any new computer data center pursuant to section 41-1519, Arizona Revised Statutes, and no new computer data centers qualify for tax relief under section 41-1519, Arizona Revised Statutes.” (Sec. 31(A), HB 4168 (Laws 2026, Chapter 140))
Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Arizona
- HB 4168 · In effect · Jul 1, 2026Pauses new data center tax relief applications for three years
- HB 2756 · Signed into law · Jun 4, 2026Lets regulators set special billing rules for very large customers
- HB 2452 · Died or failed · Feb 26, 2026Requires county comprehensive plans to designate land for data centers
- HB 4009 · Died or failed · Feb 26, 2026Requires mapping of data centers on state lands
- SB 1799 · Died or failed · Feb 9, 2026Moves the cutoff for new data center tax certifications to the end of 2026
- HB 2949 · Died or failed · Feb 5, 2026Requires large data centers to pay their full energy costs
Who's involved
- DeveloperBeale Infrastructure
Public records
2 records found so far. 8 kinds of record are still being collected.
See every recordQuestions people ask
- Where is Beale Infrastructure Marana Data Center Campus (Luckett Road)?
- Beale Infrastructure Marana Data Center Campus (Luckett Road) is a data center project in Marana, Pima County, Arizona.
- Who is developing Beale Infrastructure Marana Data Center Campus (Luckett Road)?
- Beale Infrastructure is named as the developer of Beale Infrastructure Marana Data Center Campus (Luckett Road).
- How big is Beale Infrastructure Marana Data Center Campus (Luckett Road)?
- The site covers 611.2 acres.
- What stage is Beale Infrastructure Marana Data Center Campus (Luckett Road)?
- Beale Infrastructure Marana Data Center Campus (Luckett Road) is approved. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Town of Marana Ordinance No. 2026.003: rezoning for the Luckett Road South Data Center Specific Plan
Town of MaranaTier 1 · Captured 2026-11-10 · Open the source - 2Key insights from the Marana, Arizona Town Council meeting
Beale InfrastructureTier 2 · Captured 2026-11-10 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page