Tombstone Resources Cochise Supercomputer Campus

Cochise County,ArizonaIn permittingFirst public 2026Filing entity: Tombstone Resources L.L.C.Last checked Nov 10, 2026

Tombstone ResourcesDeveloper

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: City or address
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Tombstone Resources Cochise Supercomputer Campus is a data center project in Cochise County, Arizona. Tombstone Resources is named as developer. It is in permitting. It was first public in 2026. It was announced at 6,000 MW.

Tombstone Resources Cochise Supercomputer Campus is a data center project in Cochise County, Arizona. Tombstone Resources is named as developer. It was announced at 6,000 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Cochise County, Arizona. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

6,000 MWAnnounced capacity
1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Cochise County, Arizona.See every project on the map

The land, to scale

One football field
747 acres, about 565 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · FilingFiled with Cochise County Development Services for Tombstone Resources Cochise Supercomputer CampusSU26-22
  2. · New projectFirst public record of Tombstone Resources Cochise Supercomputer CampusIn permitting

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 2756: Lets regulators set special billing rules for very large customers

    The act covers new extra high load factor customers of an Arizona electric public service corporation or large public power entity, as defined by the corporation commission or the entity; this project has 6,000 MW on record (grid connection), but whether its serving utility counts it as a new extra high load factor customer under that definition is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which leaves the customer definition to the commission or the entity.

    “An electric public service corporation operating in this state shall file with the corporation commission semiannual reports regarding new extra high load factor customers, AS defined by the corporation commission, that include both of the following WITH RESPECT TO THE IMMEDIATELY PRECEDING six-month period:” (Sec. 3, A.R.S. Sec. 40-207(A))

    Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Arizona HB 4168: Pauses new data center tax relief applications for three years

    The act covers new computer data centers, for which the Arizona Commerce Authority may not accept applications and which may not qualify for tax relief under A.R.S. Sec. 41-1519 from July 1, 2026 through June 30, 2029; this project has 6,000 MW on record (grid connection), but whether this project is a new computer data center that applied for or seeks tax relief under section 41-1519 in that window is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Notwithstanding any other law, beginning on July 1, 2026 through June 30, 2029, the Arizona commerce authority may not accept applications for any new computer data center pursuant to section 41-1519, Arizona Revised Statutes, and no new computer data centers qualify for tax relief under section 41-1519, Arizona Revised Statutes.” (Sec. 31(A), HB 4168 (Laws 2026, Chapter 140))

    Rule checks: Project is in Arizona. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Arizona

All 15 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 6,000 MW · Full build-out (applicant estimate)Oct 2026 · grid connection

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Tombstone Resources Cochise Supercomputer Campus?
Tombstone Resources Cochise Supercomputer Campus is a data center project in Cochise County, Arizona.
Who is developing Tombstone Resources Cochise Supercomputer Campus?
Tombstone Resources is named as the developer of Tombstone Resources Cochise Supercomputer Campus.
How big is Tombstone Resources Cochise Supercomputer Campus?
Tombstone Resources Cochise Supercomputer Campus was announced at 6,000 MW of capacity. The site covers 747 acres.
What stage is Tombstone Resources Cochise Supercomputer Campus?
Tombstone Resources Cochise Supercomputer Campus is in permitting. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Special Use Authorization Application SU26-22, Tombstone Resources L.L.C. (54 pages, with appendices)
    Cochise County DocumentCenter
    Tier 1 · Captured 2026-11-10 · Open the source
  2. 2
    Cochise County announces special use application for proposed data center and battery energy storage
    Cochise County
    Tier 1 · Captured 2026-11-10 · Open the source
  3. 3
    Data Centers: SU26-22 application status page
    Cochise County
    Tier 1 · Captured 2026-11-10 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page