Microsoft San Jose data center (Alviso)

San Jose,Santa Clara County,CaliforniaUnder constructionFirst public 2017Filing entity: Microsoft CorporationLast checked Nov 9, 2026

MicrosoftDeveloperHITT ContractingBuilderPG&EElectric utilityEnchanted RockOther role

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

6 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Microsoft San Jose data center (Alviso) is a under-construction data center project in San Jose, Santa Clara County, California. Microsoft is named as developer. It was first public in 2017. No site capacity figure is published for this project.

Microsoft San Jose data center (Alviso) is an under-construction data center project in San Jose, Santa Clara County, California. Microsoft is named as developer. No site capacity figure is published for this project. All six of the core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in San Jose, Santa Clara County, California. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

15Public records we have found

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    No county assessment or tax payment record for this campus has been collected yet.

    Not known yet
  2. Tax breaks

    No tax break or incentive agreement naming this campus is in our records.

    Not known yet
  3. Money for schools and services

    Microsoft is paying the city at least $9,274,314 for easements and site works at the wastewater facility next door.

    Not known yet
  4. Electricity bill

    PG&E serves this campus, which is approved for a maximum electrical draw of 99 megawatts.

    Not known yet
  5. Water

    The campus is planned to use about 423 acre-feet of water a year, mostly recycled water.

    Not known yet
  6. Jobs

    The approved project projects about 100 operations jobs at this campus.

    Not known yet
  7. Next door: height, setbacks, noise

    The approved project removes 79 trees and relocates a water purification visitor center beside the site.

    Not known yet
  8. Your say

    Residents challenged this project's first approval in court, and the case turned on a filing deadline.

    How to take part

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Santa Clara County, California.See every project on the map

The land, to scale

One football field
64.59 acres, about 49 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionBay Area Air Quality Management District: Authority to Construct issued for the remaining 84 natural gas backup engine generators (SJC03), each abated by a 3-way catalyst system (air permit) for Microsoft San Jose data center (Alviso)Air District Application 704043; 84 generators (document numbering: Sources S-7 through S-90)
  2. · DecisionCity of San Jose City Council: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water for the San Jose-Santa Clara Regional Wastewater Facility adopted (10-0-1; Vice Mayor Foley recused) for Microsoft San Jose data center (Alviso)Resolution RES2025-394; Council File 25-1211
  3. · DecisionCity of San Jose Planning Commission: Conditional use permit and parking development exception approved (9-0) for two single-story data center buildings (about 397,205 sq ft), a substation, pump stations, and 224 standby backup generators on 64.59 gross acres; resolutions certifying the CEC Final...CP23-016; V24-001; ER20-219
  4. · DecisionBay Area Air Quality Management District: Authority to Construct issued under Regulation 2-1-301 for the first 140 natural gas backup generators (SJC02) (air permit) for Microsoft San Jose data center (Alviso)Air District Application #31953; Sources S-1 through S-140
  5. · DecisionCalifornia Energy Commission: Commission Final Decision in the SPPE proceeding: the backup generating facility qualifies for the small power plant exemption (generating capacity will not exceed 100 MW) for Microsoft San Jose data center (Alviso)Order No. 22-0713-6; Docket 19-SPPE-04; TN 244835/244836
  6. · FilingFiled with California Energy Commission for Microsoft San Jose data center (Alviso)Order No. 22-0713-6; Docket 19-SPPE-04; TN 244835/244836
  7. · DecisionCalifornia Energy Commission: Final Environmental Impact Report for the San Jose City Backup Generating Facility (SJ2) small power plant exemption application for Microsoft San Jose data center (Alviso)Docket 19-SPPE-04; CEC-700-2021-003-F; TN 241977
  8. · FilingFiled with California Energy Commission for Microsoft San Jose data center (Alviso)Docket 19-SPPE-04; CEC-700-2021-003-F; TN 241977
All 9 events for this project

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026California AB 1577: Requires data centers of 10 MW or more to report facility, energy, water-cooling and PUE data to the Energy Commission

    The act requires the owner or operator of a data center with an electrical capacity of 10 megawatts or more in California to submit facility and energy information to the Energy Commission upon energization and at least annually, and excludes facilities under 10 megawatts and publicly funded research, public safety, publicly funded national security, publicly owned, and utility facilities; this project is a California data center with 99 MW of electrical capacity on record and no excluded facility type on record, so every condition the text sets is met by a fact on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    ““Data center” does not include a facility with an electrical capacity of less than 10 megawatts.” (Public Resources Code Sec. 25302.10(a)(2)(B))

    Rule checks: Project is in California; 99 MW on record (grid connection), threshold 10 MW (Public Resources Code Sec. 25302.10(a)(2)(B)). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2383: Requires data center tariffs that make data centers pay societal grid costs and a fair share of generation costs

    The act requires electrical corporations to file transmission, distribution, and generation service tariffs for participating customers, data centers tariffed under the article, with a generation tariff threshold the commission will set at no more than 25 megawatts; this project has 99 MW on record (grid connection), but whether this project is a participating customer tariffed under the article, and its peak demand against the threshold the commission will set, is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “The commission may not set a minimum peak electricity demand threshold that exceeds 25 megawatts.” (Public Utilities Code Sec. 945.5(c))

    Rule checks: Project is in California; 99 MW on record (grid connection), threshold 25 MW (Public Utilities Code Sec. 945.5(c)). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2469: Bars local permit approval for a data center unless the applicant files a water supply assessment, water scarcity plan, projected water use and workforce disclosures, and pays for needed water system improvements

    The act bars a city or county from approving a permit for the construction, or an expansion that increases the maximum peak water use, of a data center unless the applicant provides a water supply assessment and other disclosures and assumes the full cost of required water infrastructure improvements; this project has 99 MW on record (grid connection), but whether this project applies for such a construction or expansion permit is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Notwithstanding any other law, a city, county, or city and county shall not approve a discretionary or ministerial permit or other entitlement that would result in the construction, or expansion that increases the maximum peak water use, of a data center unless all of the following conditions are satisfied:” (Government Code Sec. 65964.7(b))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California AB 2619: Requires urban water suppliers to count data center demand in annual water supply assessments

    The act requires a person who owns or operates a data center in California, of any size class, to provide water use estimates to its water supplier before applying for an initial business license and to report water use on initial and renewal business license applications; this project has 99 MW on record (grid connection), but whether this project's owner or operator applies for an initial or renewal business license for this facility is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Prior to applying to a city for an initial business license, equivalent instrument, or permit, a person who owns or operates a data center shall provide its water supplier, under penalty of perjury, a good faith estimate of the expected water use, the anticipated source of water, and the data center’s projected water use volume for the maximum day, maximum month, and average year.” (Business and Professions Code Sec. 16000.4(b)(1))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 1168: Orders the CPUC to assess rate structures that make data centers pay their share of grid costs and relieve residential ratepayers

    The act directs the Public Utilities Commission, as part of a new or existing proceeding, to assess rate structures that ensure data centers pay their reasonable share of transmission and distribution costs and their proportionate share of load increases and procurements needed to reliably serve their loads; this project has 99 MW on record (grid connection), but whether this project's costs and load are within a rate structure the commission assesses under this article is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Ensure data centers pay their reasonable share of costs associated with transmission and distribution needs, regardless of whether the data centers interconnect at the transmission or distribution level.” (Public Utilities Code Sec. 901(a))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 57: Orders a state study of data center costs for other customers

    The act covers new loads from data centers served by electrical corporations, whose costs the Public Utilities Commission may assess for cost shifts to other customers; this project has 100.8 MW on record (generator capacity), but whether this project is a new load from a data center served by an electrical corporation is not on record.

    “The commission may assess the extent to which electrical corporation costs associated with new loads from data centers result in cost shifts to other electrical corporation customers.” (Public Utilities Code Sec. 913.22(a))

    Rule checks: Project is in California. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 886: Makes transmission-level data centers pay for the upgrades their interconnection triggers, with refunds capped and an early termination fee

    The act's transmission interconnection tariff section applies only to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027; this project has 99 MW on record (grid connection), but whether this project enters into such an agreement on or after that date is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “This section shall only apply to a data center that enters into a new interconnection agreement to receive retail electric service at the transmission level on or after January 1, 2027.” (Public Utilities Code Sec. 945.3(d))

    Rule checks: Project is in California. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026California SB 887: Lets a data center project win CEQA judicial streamlining only if it meets strict energy, water, storage and community-benefit conditions

    The act gives a data center project environmental leadership status under the California Environmental Quality Act, with judicial streamlining, only when the lead agency certifies that it meets all listed conditions, including paying the full cost of interconnection in advance, zero-carbon energy storage of at least four hours at 100 percent of forecasted peak demand, and a legally binding community benefits agreement; this project has 99 MW on record (grid connection), but whether this project is certified as an environmental leadership development project or meets those conditions is not on record. Status part: the bill's status (signed into law on September 21, 2026) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “Includes zero-carbon energy storage with at least four hours of capacity at 100 percent of forecasted peak demand for the facility.” (Public Resources Code Sec. 21180(b)(5)(B)(iii))

    Rule checks: Project is in California. Still to check: who it covers: not checked

Bills and laws in California

All 19 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 99 MW · SJC02 and SJC03, full approved buildoutFeb 2022 · grid connection
  • 77 MW · SJC02 and SJC03, full approved buildoutFeb 2022 · it_load
  • 99 MW · Campus total (maximum electrical load)Feb 2022 · grid connection
  • 77 MW · Campus total (estimated load)Feb 2022 · grid connection
  • 99 MW · SJC02 and SJC03, full approved buildoutJul 2022 · generator_capacity

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Bay Area Air Quality Management District, Air District Application #31953; Sources S-1 through S-140

    Stated in the filing
    140 generators (Sources S-1 through S-140)
    Stated in the filing
    459 hours per year per generator
    Stated in the filing
    50 hours per year per generator
  • City of San Jose City Council, Resolution RES2025-394; Council File 25-1211

    Stated in the filing
    $9.3 million no less than
    Stated in the filing
    early fall 2028 data center completion target (council memorandum timeline)
  • Bay Area Air Quality Management District, Air District Application 704043; 84 generators (document numbering: Sources S-7 through S-90)

    Stated in the filing
    84 generators (remaining SJC03 fleet)
  • California Energy Commission, Docket 19-SPPE-04; CEC-700-2021-003-F; TN 241977

    Stated in the filing
    244,676 gross square feet (SJC02)
    Stated in the filing
    0.45 MW standby output per natural gas generator
    Stated in the filing
    224 natural gas backup generators
    Stated in the filing
    396,914 gross square feet
    Stated in the filing
    99 MW
    Stated in the filing
    215 workers per month (maximum, applicant projection)
    Stated in the filing
    108 workers per month (average, applicant projection)
    Stated in the filing
    less than 1 acre-feet per year
    Stated in the filing
    100 employees (applicant projection)
    Stated in the filing
    152,238 gross square feet (SJC03)
    Stated in the filing
    2 Tier 4 diesel admin generators (1.25 MW at SJC02, 0.5 MW at SJC03)
    Stated in the filing
    2 single-story data center buildings (SJC02 and SJC03)
    Stated in the filing
    423 acre-feet per year
    Stated in the filing
    77 MW (8 colos at 9.6 MW)
  • City of San Jose Planning Commission, CP23-016; V24-001; ER20-219

    Stated in the filing
    397,205 square feet (approximate, per Planning Commission minutes)
    Stated in the filing
    79 trees
    Stated in the filing
    64.59 gross acres
    Stated in the filing
    98,600 square feet (approximate)
  • California Energy Commission, Order No. 22-0713-6; Docket 19-SPPE-04; TN 244835/244836

    Stated in the filing
    99 MW (Commission finding)

Public records

15 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Microsoft San Jose data center (Alviso)?
Microsoft San Jose data center (Alviso) is a data center project in San Jose, Santa Clara County, California.
Who is developing Microsoft San Jose data center (Alviso)?
Microsoft is named as the developer of Microsoft San Jose data center (Alviso).
How big is Microsoft San Jose data center (Alviso)?
The site covers 64.59 acres.
What stage is Microsoft San Jose data center (Alviso)?
Microsoft San Jose data center (Alviso) is under construction. It was first public in 2017.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Notice of Determination: Issuance of an Authority to Construct for Emergency Backup Natural Gas Generators Sources S-1 through S-140 (Air District Application #31953)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Council Memorandum, File 25-1211: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (October 27, 2025)
    City of San Jose
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    City Council Meeting Minutes, Tuesday, November 18, 2025
    City of San Jose (City Clerk, via Legistar)
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Notice of Determination: Issuance of Authority to Construct for Eighty-Four Emergency Backup Natural Gas Engine Generators, Sources S-7 through S-90 (Air District Application 704043)
    Bay Area Air Quality Management District (via CEQAnet, SCH 2021020002)
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Final Environmental Impact Report, San Jose Data Center / SJ2 (CEC-700-2021-003-F), Docket 19-SPPE-04
    California Energy Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    San Jose Planning Commission Action Minutes, April 9, 2025 (Microsoft CP23-016 conditional use permit, 1657 Alviso-Milpitas Rd)
    City of San Jose
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Commission Final Decision, Order No. 22-0713-6, Docket 19-SPPE-04 (San Jose City Backup Generating Facility)
    California Energy Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Organizacion Comunidad de Alviso v. City of San Jose, 60 Cal.App.5th 783 (2021), Appeal No. H046458
    California Court of Appeal, Sixth Appellate District
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Advice 7919-E: Electric Rules 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Upgrades for GIC San Jose LLC
    Pacific Gas and Electric Company (CPUC advice letter)
    Tier 2 · Captured 2026-11-08 · Open the source
  10. 10
    Resolution E-5447: PG&E Advice Letter 7653-E non-standard EPC agreement for the Ringwood Switching Station (STACK)
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    Resolution E-5420: PG&E Advice Letter 7569-E exceptional case, STACK Infrastructure (SI SVY01PG&E, LLC), San Jose
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Administrative Law Judge's Ruling Setting Schedule on Cost Allocation Issues in A.24-11-007 (PG&E Electric Rule 30)
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Resolution E-5433: PG&E Advice Letter 7667-E exceptional case, Sunnyvale Technology Partners LLC, Sunnyvale
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  14. 14
    Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
    California Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    Microsoft's data center plan is approved (San Jose, 99 MW maximum load)
    San Jose Mercury News
    Tier 3 · Captured 2026-11-08 · Open the source
  16. 16
    Alviso datacenter construction update
    Microsoft (Microsoft Local blog)
    Tier 1 · Captured 2026-11-09 · Open the source
  17. 17
    HITT Contracting Breaks Ground on Microsoft Alviso Datacenter Campus in San Jose
    HITT Contracting Inc.
    Tier 1 · Captured 2026-11-09 · Open the source
  18. 18
    California Awards $71.1 million in Tax Credits Projected to Create More Than 5,200 Jobs
    California Governor's Office of Business and Economic Development (GO-Biz)
    Tier 1 · Captured 2026-11-09 · Open the source
  19. 19
    San Jose Data Center
    California Energy Commission
    Tier 1 · Captured 2026-11-08 · Open the source