What it is

PG&E applied on November 21, 2024 for Electric Rule 30, a tariff for new retail customers taking service at transmission voltage (roughly 50 to 230 kV), a class that previously had no tariff and was served deal by deal through exceptional case resolutions. Decision D.25-07-039 (issued July 28, 2025) partially granted interim implementation: transmission-level customers may take service now if they pay in advance or pay actual costs, and they may voluntarily prefund up to 100 percent of specific transmission network upgrades; new transmission-level customers bear the initial cost of all transmission facilities built for them. Refunds, interest, and repayment of prefunding loans are deferred to the final decision, and repayment is not guaranteed. PG&E's compliance Advice Letter 7671-E was rejected in October 2025 because its prefunding loan did not require the customer to prefund 100 percent of all transmission network upgrades as the decision requires. As filed (not adopted), PG&E proposed a minimum demand charge of 75 percent of contracted peak demand and a 15-year minimum contract term. An ALJ ruling of January 9, 2026 re-established the proceeding schedule on cost allocation; the application remains pending.

The facts

Regulator
California Public Utilities Commission
Docket number
A.24-11-007
Type
Large load tariff
Utility
Pacific Gas & Electric Co.
State
California
Filed
Nov 21, 2024
Status date
Jan 9, 2026
Large-load rules
Yes

Projects served by Pacific Gas & Electric Co.

Related cases and proceedings

In the record

  1. Utility case, Nov 21, 2024. Utility case filed: Application of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service California Public Utilities Commission, A.24-11-007

Sources

  1. 1
    Administrative Law Judge's Ruling Setting Schedule on Cost Allocation Issues in A.24-11-007 (PG&E Electric Rule 30)
    California Public Utilities Commission
    Tier 1 · ALJ Ruling Establishing Proceeding Schedule, filed January 9, 2026: procedural background (application filed November 21, 2024) and summary of D.25-07-039 (interim implementation terms; refunds, interest and loan repayment deferred to the final decision). The Advice Letter 7671-E rejection and the as-filed 75 percent minimum demand charge and 15-year term are per the Q5 WG2 notes (Commission disposition letter of November 19, 2025 and party testimony), not from the ruling itself. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service." Last activity 2026-01-09. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-rule30-a24-11-007