What it is

The Commission's energization rulemaking under Public Utilities Code Sections 930 to 939 (SB 410 and AB 50). Decision D.24-09-020 (issued September 17, 2024) set statewide average and maximum energization targets for PG&E, SCE and SDG&E under Electric Rules 15, 16, 29 and 45, set timelines for upstream capacity upgrades, and required biannual utility energization reports; the utilities' September 30, 2025 reports discuss large scope and large load projects as a source of energization delay. The proceeding page shows the rulemaking still ACTIVE, with phases continuing. Rowed once with utility_row_key empty because it binds all three large electric IOUs; type interconnection_rule is the closest staged value for an energization-timelines rulemaking.

The facts

Regulator
California Public Utilities Commission
Docket number
R.24-01-018
Type
Interconnection rule
State
California
Filed
Jan 25, 2024
Status date
Sep 17, 2024
Large-load rules
Yes

Related cases and proceedings

In the record

  1. Utility case, Jan 25, 2024. Utility case filed: Order Instituting Rulemaking to Establish Energization Timelines California Public Utilities Commission, R.24-01-018

Sources

  1. 1
    CPUC proceeding details: R.24-01-018 (Order Instituting Rulemaking to Establish Energization Timelines)
    California Public Utilities Commission (apps.cpuc.ca.gov)
    Tier 1 · CPUC proceeding details page for R2401018 (filed January 25, 2024; status ACTIVE) and Decision 24-09-020 (issued September 17, 2024), summary and Sections 7 and 8 · Open the source
  2. 2
    Decision 24-09-020: Decision Establishing Target Energization Time Periods and Procedure for Customers to Report Energization Delays (R.24-01-018)
    California Public Utilities Commission (docs.cpuc.ca.gov)
    Tier 1 · CPUC proceeding details page for R2401018 (filed January 25, 2024; status ACTIVE) and Decision 24-09-020 (issued September 17, 2024), summary and Sections 7 and 8 · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Order Instituting Rulemaking to Establish Energization Timelines." Last activity 2024-09-17. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-cpuc-energization-r24-01-018