Utility commission
Electric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
Where it stands: Decided as of Oct 30, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Resolution E-5420 (adopted October 30, 2025, issued November 7, 2025) approved with modification two agreements to energize a new 90 MW data center for STACK Infrastructure (SI SVY01PG&E, LLC) at 2400 Ringwood Ave, San Jose, including a new 115 kV Ringwood substation; estimated facilities cost $85.9 million including the income tax component of contribution (ITCC). Departing from the standard refund rule, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution states it is non-precedential for the Rule 30 proceeding (A.24-11-007).
The facts
- Regulator
- California Public Utilities Commission
- Docket number
- Resolution E-5420 (Advice Letter 7569-E)
- Type
- Other
- Utility
- Pacific Gas & Electric Co.
- State
- California
- Filed
- Apr 18, 2025
- Status date
- Oct 30, 2025
- Large-load rules
- Yes, for loads of 90 MW or more
Projects served by Pacific Gas & Electric Co.
Related cases and proceedings
- Utility commission · DecidedElectric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
- Utility commission · DecidedExceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
- Utility commission · Pending before the commissionApplication of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
- Court case · PendingImperial Valley Computer Manufacturing, LLC v. City of Imperial, et al.
- Utility commission · Pending before the commissionOrder Instituting Rulemaking to Establish Energization Timelines
- Court case · DecidedOrganizacion Comunidad de Alviso v. City of San Jose (Microsoft Corporation et al., real parties in interest)
In the record
- Utility case, Apr 18, 2025. Utility case filed: Electric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure California Public Utilities Commission, Resolution E-5420 (Advice Letter 7569-E)
Sources
- 1Resolution E-5420: PG&E Advice Letter 7569-E exceptional case, STACK Infrastructure (SI SVY01PG&E, LLC), San Jose
California Public Utilities CommissionTier 1 · Resolution E-5420 text: caption (Advice Letter 7569-E, filed April 18, 2025); proposed outcome (approves with modification two agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues); body (ITCC component; refund period extended to 15 years). · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Electric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure." Last activity 2025-10-30. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5420-stack