Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California

Where it stands: Decided as of Jan 15, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Resolution E-5439 (January 15, 2026) approved with modification four agreements to energize a new 90 MW data center for Microsoft Corporation (project SJC02) at 1657 Alviso-Milpitas Rd, San Jose, with 115 kV upgrades at Los Esteros Substation and a new 115 kV line to Microsoft's substation. Microsoft pays all up-front costs and construction is on an actual-cost basis; operation date January 2027. As in the other exceptional cases, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.

The facts

Regulator
California Public Utilities Commission
Docket number
Resolution E-5439 (Advice Letter 7635-E)
Type
Other
Utility
Pacific Gas & Electric Co.
State
California
Filed
Jul 1, 2025
Status date
Jan 15, 2026
Large-load rules
Yes, for loads of 90 MW or more

Projects served by Pacific Gas & Electric Co.

Related cases and proceedings

In the record

  1. Utility case, Jul 1, 2025. Utility case filed: Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California California Public Utilities Commission, Resolution E-5439 (Advice Letter 7635-E)

Sources

  1. 1
    Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
    California Public Utilities Commission
    Tier 1 · Resolution E-5439 text (Agenda ID 23925, Rev. 1, dated January 15, 2026): caption (Advice Letter 7635-E, filed July 1, 2025); proposed outcome (approves with modification four agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues; refund period to fifteen years). · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California." Last activity 2026-01-15. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5439-microsoft-sjc02