Utility commission
Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California
Where it stands: Decided as of Jan 15, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Resolution E-5439 (January 15, 2026) approved with modification four agreements to energize a new 90 MW data center for Microsoft Corporation (project SJC02) at 1657 Alviso-Milpitas Rd, San Jose, with 115 kV upgrades at Los Esteros Substation and a new 115 kV line to Microsoft's substation. Microsoft pays all up-front costs and construction is on an actual-cost basis; operation date January 2027. As in the other exceptional cases, annual refunds are capped at 75 percent of the customer's actual annual net transmission revenues with an ITCC adjustment, and the refund period is extended from 10 years to 15 years. The resolution is non-precedential for the Rule 30 proceeding.
The facts
- Regulator
- California Public Utilities Commission
- Docket number
- Resolution E-5439 (Advice Letter 7635-E)
- Type
- Other
- Utility
- Pacific Gas & Electric Co.
- State
- California
- Filed
- Jul 1, 2025
- Status date
- Jan 15, 2026
- Large-load rules
- Yes, for loads of 90 MW or more
Projects served by Pacific Gas & Electric Co.
Related cases and proceedings
- Utility commission · Pending before the commissionPG&E Advice Letter 7919-E: transmission upgrades for GIC San Jose LLC (Tier 3, resolution required)
- Utility commission · DecidedApplication of Southern California Edison Company (U338E) to Establish Marginal Costs, Allocate Revenues, and Design Rates (2024 General Rate Case Phase 2)
- Utility commission · DecidedElectric Rule 15 and 16 Exceptional Case Submittal for Engineering, Procurement, and Construction Agreement with STACK Infrastructure, Inc.
- Utility commission · DecidedElectric Rules 2, 15, 16 Exceptional Case Submittal, Electric Transmission Interconnection, Sunnyvale Technology Partners LLC c/o Menlo Equities
- Utility commission · Pending before the commissionApplication of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service
- Court case · PendingImperial Valley Computer Manufacturing, LLC v. City of Imperial, et al.
- Utility commission · DecidedElectric Rule 2, 15, and 16 Exceptional Case Submittal for Electric Transmission Service Facilities for STACK Infrastructure
- Utility commission · Pending before the commissionOrder Instituting Rulemaking to Establish Energization Timelines
In the record
- Utility case, Jul 1, 2025. Utility case filed: Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California California Public Utilities Commission, Resolution E-5439 (Advice Letter 7635-E)
Sources
- 1Resolution E-5439: PG&E Advice Letter 7635-E exceptional case, Microsoft Corporation SJC02, San Jose
California Public Utilities CommissionTier 1 · Resolution E-5439 text (Agenda ID 23925, Rev. 1, dated January 15, 2026): caption (Advice Letter 7635-E, filed July 1, 2025); proposed outcome (approves with modification four agreements for a new 90 MW data center; refunds limited to 75 percent of net revenues; refund period to fifteen years). · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Exceptional Case Submittal for Electric Transmission Upgrades for Microsoft Corporation for its SJC02 Project in San Jose, California." Last activity 2026-01-15. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-pge-e5439-microsoft-sjc02